CHARM ERROR

Hi,
I have added some actions and start conditions for those actions only to the custom action profile for mailing on each status change. the action profile was functioning perfectly before the changes.
Currently I am having the below error when I raise a CR. there are no further status changes available to me.
An action was terminated due to an exceptional situation.
Message no. SOCM_ACTION_LOG 090
Diagnosis
An exception has been triggered in PPF action processing.
System Response
Action processing has been terminated. The status of the transaction is still incorrect.
Procedure
You cannot execute the action until the cause of the error has been removed.
The error messages will be kept until the transaction is next checked for subsequent analysis.
Procedure for System Administration
If necessary, analyze other messages in the application log for the incorrect transaction. To analyze the termination, you can activate the breakpoints in the checkpoint group socm_exception.
Additional Information:
Exception CX_SOCM_PRECONDITION_VIOLATED occurred (program:
CL_IM_CHM1_HF_CHECK_SET=======CP, include:
CL_IM_CHM1_HF_CHECK_SET=======CM002, line: 107
Any help on this error is appreciated, went through some other inks on SDN, but the only link which points to CX_SOCM_PRECONDITION_VIOLATED, does not explain the resolution.
SAP SolMan ChaRM Actions
Regards,
Kaustubh.

Hi,
I did not change the transaction type for these changes.
I also read a sdn thread saying the transaction types revert back to original transaction types after SP22 upgrade.
can u explain ..
I think I found the problem , the change manager client was changed to another client.
Regards,
Kaustubh.
Edited by: Kaustubh Krishna on Oct 22, 2010 8:40 PM

Similar Messages

  • ChaRM: Error while releasing transport

    Hi Team,
    I have configured ChaRM in Sol Man (Sol Man 7.0 EHP1, SP24). When i try to release transport thro ChaRM, i am getting below error.
    No valid TM target found. Message number:/RTC/TMM00154
    Your valuable inputs required
    Thanks
    Kumar

    Hello,
    Perhaps you would like to review this [guide|http://service.sap.com/~form/sapnet?_SHORTKEY=00200797470000089860&_SCENARIO=01100035870000000112&_OBJECT=011000358700000657692007E]
    Regards,
    Paul

  • ChaRM Error - "No maintenance cycle is open for the current system"

    Hello All,
    I am setting up ChaRM in development system after EGI session with SAP support. I have copied standard transactions to custom ones and created Maintenance and Implementation project to run test of all scenarios.
    I now come across error of "No maintenance cycle is open for the current system" after I create a change request and in the change document, I cannot see it link with task list and the error message is displayed. I tried it with custom transaction as well as standard SAP transaction (SDCR) and get the same error.
    What links a document to a maintenance cycle? Where can I see the config of this setup? I am trying to see where it is broken. I am using the correct IBASE number (production client in logical component), I tried to create a new logical component, new projects with correct settings but it still gives this error message. Please advice.
    Thanks and regards,
    Nischal

    Hi
    did you also unlock the maintenance cycle and open for changes in solar_project_admin by right click
    do check this blog
    /people/dolores.correa/blog/2009/07/23/change-request-management-scenario-working-examples
    /people/dolores.correa/blog/2009/07/23/change-request-management-scenario-working-examples-final-points-and-appendix
    Question no 17
    /people/dolores.correa/blog/2009/07/22/change-request-management-scenario-usual-questions-and-known-errors
    Hope it solves
    Regards
    Prakhar

  • ChaRM error while creating tasklist

    Hello everyone,
    We are facing an issue with creating implementation projects and task lists.
    After defining logical components and creating IMG, we have activated ChaRM, but when clicking on "Create tasklist" button, we have this following error :
    Open transport request xxxxxx in system <SID> is not managed by chaRM.
    /TMWFLOW/MISC202
    The transport request does exists in SE10 of the satellite system.
    Furthermore, the background job for generating the IMG project has been created in the satellite system and not in SolMan. Weird isn't it ??
    Have anyone ever had this kind of issue ? Have we missed some configuration ?
    Please help us, many thanks to you.
    Regards.

    Hi,
    I have not seen this and I could not recreate the problem.  What release of SolMan are you using?
    When you create the IMG project from SolMan the IMG Project is actually created in the managed system, and therefore the background job is actually run in the managed system.  This is correct.
    Regards,
    Rich Labib

  • CHARM error - No Target system for Normal transport generated from another client

    Hi Gurus,
    This is regarding normal change. We have two clients in development. (Workbench and Customizing)
    We were trying to do Automatic import from development client to Quality. When importing the job, I’m getting an error related to Project Status switch. "you cannot import any request for the project at the moment" It works fine for another development client and we can see the target system in Project status switch.
    But, checking the Project Status switch, looks like there’s no Target System defined for Normal transport generated from another client of development.
    I attached some screenshots related to this.
    Can you please help how to add a target system for another client of development ?
    Regards,
    Salman

    yes, client 110 is present in the task list of the project. yes route is defined because it is working for urgent change

  • Error while creating IMG project in solar_project_admin for the CHARM maint

    Dear Experts,
       I  am integrating the r3 system to the charm process.
    I have created the maintainenace project in SOLAR_PROJECT_ADMIN
                                               gave tha logiccal component(TMS is configured ( DEV--> QA --> PRD) .
    Now when i create teh img project for this it is throwing the error as below.
    *S:No authorization to:000 on as a trusted system (Trusted RC=1).
    Message no. No authorization to000
    \I have all the roles to my user id mapped
    Trusted rfc's
    S_RFC
    S_RFCacl
    etc......
    What might be the error................??
    my need to be create in the clients 000 for which i am omplementing the charm..........??
    What are the roles should be given in 000 client.
    Regards,
    Umesh
    jsumesh85  at  gmail

    Hi Umesh,
    Please confirm your problem by as issue with the trusted system, check the link below
    [Trouble trusted system|http://help.sap.com/saphelp_nw04/helpdata/en/8b/0010519daef443ab06d38d7ade26f4/content.htm]
    No authorization to log on as a trusted system (trusted RC = <0 1 2 3>).                                                                               
    Here, the trusted return codes ( = 0, 1, 2 or 3 ) have the following meanings:                                                                               
    1   Calling system is not a trusted system, or security                         
         ID for the system is invalid.                             
         Solution: Create (again) the trusted system (see above).
    as of in trusted system, you supposed to get the same user in both the systemm witht the respected access like S_RFCACL.
    complete explanation of trusted RFCs is in note 128447.Please follow the note
    Thanks
    Jansi

  • Error when creating Task List in ChaRM

    I am getting this error after I activate Change Request Management and attempt to create a task list.
    Error writing to table /TMWFLOW/PROJCTC
    Message No. /TMWFLOW/TASKLIST177
    There is no long text. Please advise

    Configuring ChaRM in a new client, entries in the table above already existed for the maintenance cycle the new client was trying to generate. deleted entries form database.

  • Error when importing a Transport request in CHARM???

    Hi all,
              when i am trying to import a transport a request( thru CHARM) , its throwing an error " No valid system specified (Q11)" and "Import error: Check TMS Alert Viewer in target system"
    Note::I was able to create a Transport request , release it but facing problem while importing to quality system.development system is ECC5.0 and quality is ECC6.0
    rgds,
    Anand

    HI abhi,
            i havecreated the domain link, my ECC5.0 and ECC6.0 are in one domain of which ECC5.0 is domain controller,now i configured Solution manager as new domain controller and created a link between these two domains...
    now my queries are:
    1.is it enuf if i create a link between or even shud i create som transport routes between the newly added system from other domain and the existing domain
    2.i am not able to see the STMS configuration in solution manager system.ie in my ECC5.0 system( domain ctrller)if i goto STMS->Overview menu-> transport routes i see the configuration, which i cannot see by logging  into solution manager and wentto STMS->Overview menu-> transport routes i dont see
    rgds,
    Anand

  • Error when creating transport request in Charm for Portal

    Hello Guru's,
    I'm configuring ChaRM for our Portal environment using CTS+
    When I create a transport request I get the following error message:
    Parameter EPD not in version of tp configuration.
    Any thoughts????
    Regards,
    David

    Hello David,
    Please review the following SAP Notes to see if they will assist you on resolving the issue that you are having:
    1107361 - Migration BAdI-Implementation Error Message XT 465
    45548   - Transporting language-dependent objects
    Hope this helps you out!
    Thanks,
    Mark

  • Error when releasing Transports in ChaRM

    Good Day;
    When releasing a transport thru ChaRM I get the following error
    "Release of system could not be determined. The error message is "/TMWFLOW/CRIT_OBJ061"
    Any ideas?
    Thanks
    Don

    Good Day Farzan;
    We have the following systems
    Solution Manager      (Netweaver)
    Development System (Client 100 SAP 4.7)
    Quality System      (Client 100 SAP 4.7)
    Production System      (Client 100 SAP 4.7)      
    Regards
    Don

  • Error while Creating Charm Project

    Hi
    I am configuring CHARM Sol 7.1 SP11.
    TMS landscape is as follows
    DEV100-->QAS200-->PRD300 (QAS & PRD as Virtual systems). we have created virtual systems and flagged as a virtual system in smsy.
    I have created the project in SOLAR_PROJECT_ADMIN and assigned the  logical components.
    While performing the CHECK under Change Management tab in Check TMS domains "RFC destination Cannot be determined"
    Any pointers on how to resolve this?
    Regard

    Before you start with activating CHARM it is important that you create a transport link from the Solution Manager to the ABAP managed system domain controller. Once this is done, your Solution Manager is able to retrieve the TMS information from the transport domain controller.
    To create a trasport link, open transaction STMS on the Solution Manager and link with the ABAP target system via a trusted RFC.
    You will then not receive the error messages in TMS anymore.
    I hope this helps

  • Error in CHARM configuration to move JAVA objects 'The project is not relea

    Hi,
    I have BI 7.0 (ABAP + JAVA) landscape (i.e. CBD, CBQ and CBP) on SPS12 and SolMan 7.0 (SMD) on SPS14.  My goal is to move both ABAP and JAVA transports through CHARM. I performed following tasks:
    1.  Configured TMS by selecting CBD as Transport Domain controller to move Java transports
    2.  Configured CHARM for BI landscape to move ABAP transports in SMD and it is working fine
    3.  Configured CTS+ to move JAVA transports on SMD instead of CBD because CTS_BROWSER service is not available on CBD due to SPS12. While configuring CTS+ in SMD, I used SIDs for BI Java landscape as reverse SID (i.e. DBC, QBC and PBC) and used mapping parameter to map to original SID.  I used reverse SID because already in SMD (CBD, CBQ and CBP) has been defined for CHARM purpose. Now, I am able to move successfully JAVA transports of BI landscape from SMD.
    4.  I am having issue in configuring CHARM on SMD for JAVA transports.  I am following http://service.sap.com/solutionmanager --> Media Library --> TechnicalPapers --> How to Set Up and Use eCTS/ChaRM Solution Manager 4.0 SP12 document.  Following are the steps, I performed to move JAVA transport through CHARM:
         a.  Defined JAVA systems (i.e. DBC, QBC and PBC) in SMSY as Enterprise portal systems
         b.  Defined ABAP system (i.e. Where Transport request is created, in my case it is SMD) in SMSY
         c.  Defined logical component for both ABAP and JAVA systems
         d.  Defined solution manager project by adding two logical components created at step C (i.e. ABAP and JAVA)
         e.  I am getting error when I am trying to activate CHARM and create task list.  The error is as follows:
    /TMWFLOW/TRACKN 101: 'Warning: Problems occurred during synchronization of the system landscape'.
    If you choose 'Check', the system displays the following message in the results list of the check:
    /TMWFLOW/TRACK_N 806: 'No consolidation system found for SMD-200 (project zjava3)'
    If you try to create a task list by choosing the relevant pushbutton, the system issues message
    /TMWFLOW/CONFIG_UI 017: 'The project is not released. Hence cycle can not be created'.
    I found a relevant sap note for this 1054264 but it is not useful me, as it suggest to upgrade SolMan to SPS12 but whereas I am on SPS 14.
    Any suggestion are welcome.  Thanks in advance.
    Regards
    Shiv

    Hello
    You should first fix the errors you get such as the missing consolidation system
    Please see thread [Re: No consolidation system found for SID in solman; or check the forum on the error message "'No consolidation system found for" and you will find relevant information.
    I would advise to update your SAP Solution Manager though to one of the latest available levels, there are a lot of fixes and enhancements to Charm (and also availability of quality gate management which gives some of the functionality of Charm but is more compact).
    Kind regards
    Tom

  • Error with Transport system not configured that may be related to CHaRM

    Who has in depth knowledge on setting up SAP Solution Manager CHaRM. Had an odd problem with the transport system failing when the QA system was shut down for maintenance. Transports were not able to be created or save to.  Error message was Transport System not configured.  Brought up QA and re-distributed system and Transport group and transport requests started working again.

    Hello,
    if a system, e.g. QA system, will not be available due to a maintenance task,
    we set the status of this system to "temporarily inactive" (see header data in transaction SMSY).
    This status allows us, to create new transport requests in DEV-System although consolidation system QA is not available.
    (Of course you have to reset the status, when QA-system ist started again.)
    Hint: it is not possible to release or to import a transport request, when consolidation system is shut down.
    Therefore the developer should pay attention to the messages, which raise in urgent corrections.
    best regards
    Horst

  • CHARM Import Transport Request (Background) Error

    Dear Experts,
    We are Facing problem in Charm TR import with below error.
    Current phase of project: Development with Release
    Action to be checked: Schedule Manager: Import into Test Systems
    Start Import (Project SID_P00005)...
    Try to connect via TMS-internal RFC destination...
    TMS communication error with TMSSUP#SID.DOMAIN_SID
    Import error. Check TMS Alert Viewer in target system
    RFC TMSSUP#SID.DOMAIN_SID is failing with authorization test.
    Diagnosis
    There was an error during communication with the RFC destination
    TMSSUP#SID.DOMAIN_SID
    System Response
    The exact error message of the system is:
    Name or password is incorrect (repeat logon)
    please suggest how to correct this Authrization error
    Regards,
    Siva.

    Dear Laxman,
    Kindly give me a link for any authorization docs, for SOLMAN and MANAGED SYSTEMS which roles need to be assigned for general Team member , Change manager and BASIS admin.
    Please  provide any docs.
    i reffered to standard , where i am littlebit confused.
    please provide some docs.
    Regards,
    Siva

  • ChaRM config  - system check error

    Hi All ,
      I am working with the basis team to move forward with ChaRM - Solution Manager. We have a two system landscape with Development (DSM)  and Production (PSM) (domain is set up as DOMAIN_DSM - exists in STMS).
    We have most of the configuration  / system landscapes done . When we do the ChaRM check ( solar_project_admin--> select project --> system lanscape --> Change request --> check)   for a project that involves system (DBW - BW  Development and a different transport domain DOMAIN_DBW , does not exist in STMS for DSM)  it comes up with a system error saying - No domain for system DBW.
    It seems to be checking the tabel TMSCSYS for systems DBW and when it does not find it there it complains. The question is do we have to set up these system in STMS in solution manager ?
    any help would be appreciated . if you want to send me a doc please do it at amohamm at yahoo
    thanks.
    ali.

    The problem was solved by activating the domain links for the multiple domain scenario . Please make sure that you carry out this activity - " You must perform all TMS activities in your satellite systems and not in your SAP Solution Manager system " .
    Ali.

Maybe you are looking for

  • Droid Slow/ lack of customer service

    For the past 6 months my phone has been acting up. It freezes, websites refuse to load, apps stop working. The phone turns on and off itself, and crashes with no known point of return. I have gone to 4 different Verizon stores in 2 different states,

  • 10.4.8 and a first RSD!

    Updated last night, woke the macbook from sleep this morning and 10 seconds later - BAM! Simply turning it on brought it back -- so far. No idea if the update and shutdown are connected, but I was going on 4 months of heavy use without a hint of a pr

  • Advice for moving entire photo collection from one computer to another?

    I'm in the process of getting a new desktop. However, I already have gigs of photos that I've processed through Lightroom on my old computer. I'd like to move the entire collection to my new computer. Is there a simple way of doing this? It sounds li

  • What is the orbrandom.txt file?

    I've seen that in some cases, in the instance config directory there is a modified file called orbrandom.txt. For that reason, the administration console asks for applying changes to the instance because this file has changed. What's the purpose of t

  • Cannot change From when replying

    [Originally part of a discussion in the Admin Forum but moved here as looks like a Client specific issue] Users have full proxy rights to a Workgroup mailbox. When logged in as themselves they can write a NEW mail and change the From field to the Wor