ChaRM in two system landscape

Hello Everyone,
I want to implement ChaRM for BIW systems which is a two system landscape: BIWDEV and BIWLIVE . Is it posible to implement ChaRm in a two system landscape /we need three system landscape only for it.I started the ChaRM configuration work but faced certain issues over which i was told tat Charm needs three systems for implementation. Kindly plz suggest and confirm.
Regards,
Somya

Hey Somya,
2 system landscape will also work with CHARM.
CHARM can also be configured in single system landscape.
But the bottomline is you require in all 3 clients to realize charm.
These three clients can belong to same or diffrent systems altogether.
For you i would say, u will require 2 clients in BIWDEV system ( Say BIWDEV:100 as development cleint and BIWDEV:200 as Test client ).
Now you have BIWLIVE system which is our production system, so you require 1 client BIWLIVE system..
So your 3 clients are ready and Change Request management can be realized..
Please Reward with points if this postv was usefull..
Revert For ne clarifications ..
Regards,
Suzzane

Similar Messages

  • Converting a two system landscape to three system landscape

    Currently, I have a two system landscape: DEV (development)  and PRD (production) in STMS
    I would like to add a QAS system so I will end up with DEV-QAS-PRD in STMS
    I would like to keep all data the way it is. I don't want to lose any logs or files in the data and cofiles directories.
    This is how I have this planned:
    -Include the QAS system in the existing Tranport Domain.(stms in QAS)
    -In transaction STMS go to OVERVIEW -> Transport Routes -> Standard Configuration -> Three systems in group
    and then save the configuration.(stms on the TDC)
    I'm thinking this will preserrve the current log files and the corresponding data and cofile files.
    If you have done this, I would appreciate any comment or advise.
    Thanks.

    Addition to above suggestion - Adding new system to existing landscape doesn't make any change to the data/cofiles. Process just adds additional system.
    Regards,
    Nick Loy

  • ChaRM - Mainenance Cycle in two system landscape - possible?

    Hi Experts,
    we are trying to create a maintenace cycle with two systems.
    We have a system defined as "Evaluation System" and the second is defined as "Production System".
    Generally Question
    Is it possible to create a maintenace cycle for a two-system-scenario?
    Specific Question - Erorrs/Warnings
    While checking the project we got several errors/problems:
    1 Differences between BC Set SOLMAN40_CHARM_BASICFUNC_001 and database
    2 Differences between BC Set SOLMAN40_SDESK_BASICFUNC_000 and database
    3 No consolidation system found for EID-800 (project Z_CRM_T)
    4 No track for project Z_CRM_T with log. system EID/800
    5 Message from function module /TMWFLOW/CHECK_PRJ_CONS: No export system for CBI-001
    CTS
    The transport system is configured correct - Check in STMS is OK
    Question:
    The comparison checks seem to be OK - is it necessary to reactivate the BC Sets?
    Kind regards
    Tom

    Hi,
    the system role for your client/systems in the logical component is very important:
      - The development system needs to be defined as a Source System.
      - If you don't have a QA, leave all target systems empty. If there are one or more consolidation/integration/regression systems, assign them to system role Target System.
      - Your production system uses system role Production System.
    The defined Development client needs a client dependent (TMS parameter CTC=1) consolidation track to the QA, or in a 2 Tier landscape to the production system. In a 3 Tier landscape you need a delivery track from QAS client to your production client. But as you wrote, TMS has been set up already. I just would like to mention all steps....
    Check that all RFC connections have been set up correctly. Especially the Trusted RFC. Don't forget the Trusted RFC to client 000 ot the TMs domain controller.
    In tab Systems ( transaction code SOLAR_PROJECT_ADMIN => System Landscape ):
    Make sure you see all clients of your logical component. If not hit button System Role Assignment and add your System role.
    Then still in the same tab: Hit button Shipment Routes and make sure, you see the complete transport track and only this track here!
    After correct setup of TMS, RFCs, logical components and assignment of LC to your project:
    First perform a Refresh and a Check in transaction code SOLAR_PROJECT_ADMIN => System Landscape => Change Requests. Then please recreate the maintenance cycle (and task list).
    Regards,
    Holger

  • How to configure in Charm in three system landscape

    Hi Experts
    I want to configure the charm in the three system landscape system. Please help me to configure
    Thanks & Regards

    It is same whether it is two or it is three system landscape, i guess you already must have gone through the following
    charm setup
    Re: Can Any one Provide Step by Step Config of CHARM??
    http://sap.ittoolbox.com/groups/technical-functional/sap-basis/charm-in-2tier-system-1231210

  • ChaRM with 4 system Landscape.

    Hi,<br />
    We are trying to implement ChaRM in a four system landscape <br />
    <br />
    AFD --&gt; AFQ --&gt; AFI --&gt; AFP<br />
    <br />
    defined logical components, project, created maintenance cycle. U'gent correction works fine.<br />
    <br />
    but for regular correction, we are able to create TRs release it, but not getting imported into AFQ and of course further steps are not happening. When the status is "Development Completed", we perform "Log on to system", this pops up with a dialogue with options<br />
    <br />
    AFQ           200<br />
    AFI             100<br />
    <br />
    to logon to system.<br />
    <br />
    This is the only clue we got.   <br />
    <br />
    When we perform the actions, the status keeps changing and goes to status "Production". It doesn't obey the phases maintenance cycle as well, irrespective of the phases the status keeps changing and goes to status "Production"<br />
    We are missing some minor thin's.<br />
    <br />
    Have we defined the system roles properly? IF not, how does the flow works perfectly fine with respect to U'gent correction.<br />
    <br />
    Please help.<br />
    <br />
    <br />
    Regards,<br />
    Ragu<br />
    <br />

    Hi Ragu,
    I have a few questions here:
    1. What normal correction type are you using - SDMI or SDMJ
    2. What roles are assigned to the systems in Logical Components? I believe they are setup as Target Systems and thats why you get the pop-up with both systems when you execute 'Logon action' after 'Development Completed'
    3. What is the STMS setup for this landscape?
    4. Urgnt should behave properly coz it takes the shortest route to production. Can you check the tasklist of Urgnt and see if there are only 3 systems there?
    Regards,
    Kriti Bhalla

  • ChaRM in 5 system landscape.

    Hi All,
    I have configured 5 system workflow for ChaRM . the difficulty that i am facing is.
    once after moving from dev- QA1 when i reset into development and again move to QA1 without making any changes,
    in the second time it imports the changes to QA2. similarly the same is happening for QA3.
    in Action, we are giving as import test only. how will the system recognize it is the first quality or second quality system.
    and also the logon to system takes to the latest test system suppose iam in QA3 and reseting into development, in the subsequent steps logon to system takes me to QA3 inly(since we have given status attribute as test system the latest test system is taken).
    i could understand why it is happening. but dunno how to rectify this.
    kindly advice in this regard.
    Thanks,
    Subhashini.

    Hi,
    Is this happening for your urgt. correction as well?
    Check your TMS again, if the route is defined properly (Check if there is any simultaneous import).
    Open your Maintenance Cycle in SCMA and check the takslist in sequence. Check if the sequence is as per your expectation/requirement.
    Check if "Make Settings for Change Transaction Types" under Change Transaction types can help you.
    Especially check if 'Type' and 'Sequence' under "Specify status attributes" Can help you.
    Feel free to revert back.
    -=-Ragu

  • ChaRM for a 5 system landscape

    Hi all,
    we got a requirement to implement charm for 5 system landscape. but the problem is
    currently the scenario followed for the rollout is
    1. AA(DEV-proj)--> BB(QUA - proj)
    Then the TR is forwarded from BB system to the maintenance landscape
    DEV>QUA> PROD
    they don't want to implement retrofit functionality.
    is there any way we can mapp this scenario to charm.
    kindly advice in this regard.
    Thanks,
    Subhashini.

    Hi Ragu,
    Thanks for the reply.
    currently a two systems are separated from the maintenance landscape.
    they are forwarding the TRs to the development system.
    is there any way we create 2 tracks.
    1. AA-BB-DEV-QUA-PROD
    2. DEV-QUA- PROD
    again i not having a clear idea on how to differentiate the tracks as both leads to the same production system.
    or is there any way develop a custom method for forwarding this TR to the DEV system.
    kindly sugggest on how to go about.
    Thanks ,
    Subhashini.

  • System Landscape (Dual Development System)

    Dear SAP Experts,
    We have Two-System Landscape(DEV-PRD) Whereas cross-client data is used in both the Customizing and quality assurance clients.
    Currently, our company, just merged with another non-SAP-using company. The First move is to implement FI module and subsequently, all modules that we are now using.
    My boss discussed with me if we could create another DEV server for company B to use for their customizing  and QA clients as not to impenge on our already customized set up.
    Please advise if this set up is possible, and if not, Can anyone kindly give an advise how to approach my problem?
    I'll give good points for the help that i can get.
    Best Regards,
    Jay

    You can do this.  We currently have two Dev environments one for projects based on NetWeaver integration with our ECC systems and one for regular development / run and maintain.
    I suggest doing a system copy of your development and rename the SID / hostname were it appears in the profiles and home directories for UNIX platforms.   Then perform post steps for SE06, printers, profiles, RFC etc...
    For Microsoft install a CI instance and do a database copy to have current data.  Then do post copy steps in SAP.
    Although SAP suggests not to refresh Development systems, we do it at least once a year to get current applicaiton data. 
    Think of it as a sandbox.
    If you don't want to integrate your data with the new system, skip the database copy portion for Microsoft and do a fresh install for Unix.
    Hope this helps.

  • Regarding set up of system landscape

    We want to have only a 2 system landscape for our SAP deployment i.e. Within the development server, we shall have development client and quality client and then just have another production server.
    Since we have confirmed that this is possible, please let me know the disadvantages in doing so and also if we need to anticipate for trouble shooting.
    Thanks & regards,
    Tommy.

    HI,
    1.Small and simple R/3 installation for up to 50 users and 2-system might beadequetly administrated with 2 system managers doing most of the tasks and external resources for occasional help.
    2.A Two system landscape is not optimal because development and quality assurance testing both occur in the development system.since no separate quality assurance system is available,all objects transported to the consolidation system immediately become part of production.
    Mainly Disadvantages:
    1. Development quality assurance are perfomed in the same R/3 system.
    2. Unable to fully test Repository objects and cross client customizing before these are transported to production.
    3. No verification of transports before delivery to production.
    Feel free to revert back.
    Please provide points if u get the answer.
    ---venkat.

  • ChaRM: 4-System-Landscape possible?

    Hello,
    regarding our system landscape we have no clue how ChaRM will handle following situation
    DEV-System: Development-System were the developments should be done.
    QAS-System: Test-System were the tests should be done.
    FNC-System: nothing to do here, just for functional tests
    PRD-System: Production System
    Transport routes are DEV -> transport group which deliveres QAS and FNC, and from QAS -> PRD.
    What needs to be done to set this up correctly for ChaRM (e.g.: SMSY-logical components)?
    Thanks in advance.

    Hi
    You have two options:
    1) assign FNC to task list: you can start the import to this system in the task list manually
    2) or task list without FNC: you can schedule a job 'import all' at FNC or import manually via STMS
    Confiiguration:
    1) One log. component with D-Q-FNC-P (Q and FNC are of role target systems)
    2) One log. component with D-Q-P
    regards
    Andy

  • ChaRM  4-System landscape

    Hello,
    We have setup our landscape to have a Dev system which goes to two different QA systems, then from the QA systems into Production. Dev has 4 clients going into QA 1 and 2 clients going to QA2, There are then two productive clients, one for HR, One for FI.
    The Transport system has been setup and is working.
    Can ChaRM handle sending a transport to two systems for testing?
    How should the logical systems be set up?
    DEV - -> QA1 - - - - >PRD
            -- >QA2 - - -
    Regards,

    Hi Avrohom Weissman 
    We had same setup and this is what we did to come up with this issue.
    We have added the new client in the Transport Path of STMS as required. We have used  standard Change Management program*(/TMWFLOW/SCMA_BTCH_SYNC_TEST)* where we can setup a variant. This is done after adding the new clients in an existing transport group to landscape.
    We have copied this to to Custom Module. When ever a transport moved to Dev usually transport move to QA( Which configured in Task list). We need schedule this program as background job for every 15mins or  what ever is good for you.
    It will transport same.
    Hope this will help.
    Regards
    Bhaskar

  • Activate CHaRM using Virtual Systems in Landscape

    Is it possible to activate a CHaRM project against a landscape that
    contains virtual systems?
    We currently have a Development system (DEV) with a virtual Test system
    (QAS) and virtual Production system (PRD).  These systems are marked as
    Virtual in TMS and SMSY System Landscape.  We have added these systems t
    o
    the Logical Components and created a new Solution Manager project and
    want to activate CHaRM against this scenario. .
    The TMS routes are defined with Dev -> QAS(virtual) -> PRD(virtual).  Is
    this scenario possible?  Do the standard CHaRM activation checks (RFC's,
    Authorizations, etc) get bypassed because these systems are virtual?
    When activating CHaRM, we still receive the error that no consolidation
    system exists for our Dev system even though the TMS routes have been
    defined properly.  However, since these systems are virtual, we cannot
    add client information to them.
    Thanks

    Hi,
    >
    Thiago Luttig wrote:
    > Is it possible to activate a CHaRM project against a landscape that
    > contains virtual systems?
    > The TMS routes are defined with Dev -> QAS(virtual) -> PRD(virtual).  Is
    > this scenario possible? 
    A virtual system cannot export any TR. So any request imported to QAS cannot be exported
    So
    >
    Thiago Luttig wrote:
    > The TMS routes are defined with Dev -> QAS(virtual) -> PRD(virtual).  Is
    > this scenario possible? 
    is not possible.
    Hope this answers your question.
    Feel free to revert back.
    --Ragu

  • URGENT: Changing System Landscape in ChaRM

    Ok...here is our situation:
    We use ChaRM with a 3 tier system landscape (DEV > USER  >  PROD).
    Out USER system has been down for a month (maintenance) so we went live with ChaRM as follows:
    DEV > PREPROD >PROD
    Our USER system is now back up and running so we have replaced the Logical Component on the project to reflect this.  This has worked ok but the task list is still showing the old system landscape.  i.e. its showing PREPROD still instead of USER.  How do I resolve this?
    Do I have to complete the existing cycle and then create a new one?  This would be fine except I would lose all the jobs I have scheduled in the task list (schedule every 15min EVERY day....took me ages).
    Any suggestions?
    Thanks!!!!!!!!!!!!

    Hi,
    About this issue, there is a detail information about this in blog point 6  u201CChanges in the logical components of a project where Charm is already activatedu201D.
    This is the link:  http://www.sdn.sap.com/irj/scn/weblogs?blog=/pub/wlg/15116
    So, you have to change the transport route accordingly and then close current maintenance cycle and generate a new one.
    Following is the steps.
    1: please import all the transport requests which were associated in the current maintenance cycle task list by STMS manually import.
    1: change transport route from DEV > PREPROD >PROD to DEV > USER > PROD on the domain controller system.
    2: close current maintenance cycle.
    3: change the system landscape to DEV > USER > PROD in solar_project_admin.
    4: generate a new maintenance cycle.
    Thanks
    Regards,
    Vikram

  • Need help in configuring CHARM with R/3 System landscape with seven systems

    Hi All,
    we are planning to configure CHARM for our R/3 landscape.our current STMS includes seven systems.in the current STMS the transports flow as below.
                  D20->C20->C21->C22->C23->T20->P20
    we require the transports to move in the same way as stated above even after CHARM is configured
    1.please let me know if we can configure CHARM with seven systems.
    2.if yes, how would the import happen( ie Action for import appears for all systems?).
    Regards,
    Anand Reddy

    HI andy,
    the transports will move in the following order.
    D20(DEV)->C20(Consolidation)->C21(integ)->C22(reg)->C23(unit)->T20(final test)->P20(production)
    transport will start in D20,then imported C20 followed by  C21,C22,C23,T20 imports and finally reach P20
    the systems are not in parallel they are one behind the other
    Anand Reddy

  • 4 System Landscape // ChaRM // No Export System found

    Hi Folks,
    I got some problems with a 4 system landscape in ChaRM.
    The error message I get when doing a consistency check within my SMI project is:
    Message from function module /TMWFLOW/CHECK_PRJ_CONS: No export system for NWA-303
    Message no. /TMWFLOW/TRACK_N159
    Transport route should be as follows:
    DEV -> QAS -> INT -> PRD
    Since I am still in testing phase I used clients instead of real systems in my configuration (TMS, Logical component,....)
    My configuration looks like this:
    NWA client 300 -> 301, transport layer ZCHM, transport layer SAP, consolidation
    NWA client 301 -> 302, delivery
    NWA client 302 -> 303, delivery
    Logical Component defined as follows:
    Developement System (Source: SAP): NWA:300
    Type of Role: D Source System
    Quality Assurance System (Source: SAP): NWA:301
    Type of Role:  O Target System
    Integration System (Source: User): NWA:302
    Type of Role:  O Target System
    Production System (Source: SAP): NWA:303
    Type of Role:  P Production System
    Anyone got an idea what is wrong? did I miss anything?
    The same configuration works for a 3-tier Landscape (without Integration System).
    Any help is appreciated.
    Thanks.

    Hi Raquel,
    Ours problems with RFC and with connections had be corrected with the note below:
    1833778 - Activate Change Request management - Check error
    Thank you very much!!
    Adriana