CJ88 - Settlement error

Dear All
The WBS DGP-0001-FS-PM-01-M unable to settled for AUC 4000029 through CJ88. Where as these wbs DGP-0001-CW-PM-01-M,DGP-0001-CW-L,-01-S,DGP-0001-EX-CS-01-M,DGP-0001-EX-CS-01-S has been settled to AUC which are same nature with DGP-0001-FS-PM-01-M.
The systmen error is
Complete allocation structure GI
Message no. KD503
Diagnosis
During settlement, the system puts the sender debits into groups (assignments), which are settled using the same settlement cost element. The settlement assignment is made in the allocation structure, which is stored in the settlement rule for the sender (under settlement parameters).
Cost element 80011 cannot be assigned to a settlement cost assignment in allocation structure GI, and therefore it cannot be assigned to a settlement cost element.
Procedure
Possible solutions are as follows:
u2022     If the posting under cost element 80011 was made to the sender because of an incorrect entry, and you can reverse the posting, and do not need to update the allocation structure. You only need to reverse the incorrectly assigned posting before repeating the settlement. Exception: For an investment measure with a line item settlement, you need to extend the allocation structure, even after the reversal.
u2022     If the posting was made correctly, you can do the following:
a) You can assign a different allocation structure to the sender: In the master data maintenance for the sender, choose "Settlement rule -> Goto -> Settlement parameters" and then enter a different allocation structure.
If necessary, also check whether the correct allocation structure is entered in the settlement profile. The allocation structure is defaulted in the settlement profile when you create sender master data or when you maintain the settlement rule.
o     You can update allocation structure GI
The  Cost Element 80011 (Balance sheet GL & Cat :90  Statistical Cost element for BS), which is not applicable for allocation structure.
Please advice for the same.
Regards
Avijit

Avijit,
You have to include the cost element 80011, in the cost element group. Use transaction KAH2, for knowing the cost element gruoup go to IMG-PS-Costs-Automatic and periodic allocation - Settlement - Settlement Profile - Create  allocation structure.
Here select the allocation structure GI, double click on Assignments, select the appropriate assignment line item then double click on Source.  Here check the cost element group, copy it enter the same in KAH2 then add the cost element 80011 Save.
Now come out of settlement and retry the settlement.
I suggest you to talk your FICO consultant for resolving this issue.
Praveen

Similar Messages

  • WBS Element settlement error

    Dear All
    My query is the prj is EP & WBS El is EP-99, under EP-99 the avialable values are Rs192,523/- as per different cost element wise. Those values have to settled on an one AUC-asset & the value will be settled periodicaly. My posted values are in 10th/2008 & I want to settled the said  values in 10th prd. But after processing of CJ88 the error has been raised "There no accured amounts settlement is not possible" Also note that Other WBSE has been settled under said prj.
    Please help me.
    Regards
    Avijit Barman

    Dear All
    My query is the prj is EP & WBS El is EP-99, under EP-99 the avialable values are Rs192,523/- as per different cost element wise. Those values have to settled on an one AUC-asset & the value will be settled periodicaly. My posted values are in 10th/2008 & I want to settled the said  values in 10th prd. But after processing of CJ88 the error has been raised "There no accured amounts settlement is not possible" Also note that Other WBSE has been settled under said prj.
    Please help me.
    Regards
    Avijit Barman

  • CJ88 settlement profit center error.

    Hi,
    I'm trying to do settelment using CJ88 however system is giving balncing profit center is not filled.
    i have checked AUC asset profit center and cost center was maintained, maintained aa cost object through ACset t-code.
    when i try to settle why system is not picking profit center and cost center from second leg.
    Regards,
    Raman

    Hi,you need to customize doc splitting.
    1.You need to clasify all accounts from future document in  Document Splitting-Classify G/L Accounts for Document Splitting(e.g. all accounts 2000) 03000-VENDOR.
    2.in IMG: Classify Document Types for Document Splitting    check for Document type  transaction and Variant (e.g. Doc=KR, Trans.=1010, Variant= 0001)
    3.In IMG:  Activate Document Splitting   check  assigned method(e.g. 000012)
    4. in IMG- Document Splitting-Extended Document Splitting-Define Document Splitting Rule
    For find your method and transaction(e.g. Method=00012, trans.=1010) and double click on Item categories(on left of the top of screen)
    There'd be record with category from first step (e.g. Cat.=0300), select one and double click on Base item cat. - there'd be Category 0300 and with check box Automatically split.
    I hope it'd be helpful

  • CJ88 Settlement to Fix Asset

    Hi experts,
    I tried to do settlement from a WBS to a fix asset. After maintaining the settlement rule I went to CJ88 to do the actual settlement, however i got the following error message:
    Dignosis
    Duriing settlement of sender WBS there was an atempt to settle  a posting that has account assignment OPERATING / /(fund/functional area/ grant) to an assset subnumber. However, the receiving asset XXXXXX does not have an asset subnumber with this assignment.
    Can an expert please advice on what I can do and if it has anything to do with PS side or asset side?
    Thanks.

    Hi,
    I would suggest you to take the help of your FI/CO consultant in this case.After going through your post i don't think it has got anything to directly from the PS perspective.
    Request others to comment if am wrong.
    Regards,
    Gokul

  • AIAB Distribution Rule for Settlement Error, "Asset cannot settle to itself"

    Hello Everyone,
    I have a customer who is getting the "asset cannot settle to itself" error when trying to set up a distribution rule to settle the remaining items of a Line Item Managed AUC to multiple Assets.  The Asset numbers and AUC number do NOT match.  Here are the steps that have been followed.
    Created an Internal Order, #2000####. (1998)
    Created the AuC asset. #600####(2011)
    Created Settlement Rule (Sender – Internal Order, Receiver - AUC) (2011
    Settle Internal Order to AUC.
    Create Assets. (2014). #900###1 - #900##99 etc.
    Create Settlement Rule (Sender – AUC, Receiver – Multiple Assets)  This is where my customer gets the error. 
    They were able to settle other items from this AuC to Assets last October.  It seems very strange to me that the Internal Order was created in 1998 and the AUC was created in 2011 but as I said, this was working at least last October and possibly in March of this year. 
    Thanks for you help.
    Rick 

    Hello Stacy, 
     Sorry I didn't get back to you sooner but I just had a major implementation go live on the 2nd so I've been rather busy.  I opened a ticket with SAP on this and this is what was found.   
    Joachim from SAP Support explained that the AUC had been settled to itself last year, that is the posting the program was throwing the error on.  My assumption is that we were able to settle AUC's to themselves prior to our March upgrade.  This explains the problem and we have a resolution.  We are transferring AUCs that this has happened with to a new AUC and then settling the new AUC as usual.  
    I believe SAP fixed a bug that had previously allowed AUC's to settle to themselves in one of the updates but because this AUC had a record from the past where it settled to itself the program was validating old line items and that is why it throws the error.   
    Ramnik's suggestion was another option but we didn't want to change the message to a warning because we didn't want anyone to settle an asset to itself.
    Hope this helps.
    Thanks,
    Rick

  • Settlement error

    Hi experts,
    While doing settlement through KO88,system gives following error:
    Complete allocation structure A1
    Message no. KD503
    Diagnosis
    During settlement, the system puts the sender debits into groups (assignments), which are settled using the same settlement cost element. The settlement assignment is made in the allocation structure, which is stored in the settlement rule for the sender (under settlement parameters).
    Cost element 800315 cannot be assigned to a settlement cost assignment in allocation structure A1, and therefore it cannot be assigned to a settlement cost element.
    Procedure
    Possible solutions are as follows:
    If the posting under cost element 800315 was made to the sender because of an incorrect entry, and you can reverse the posting, and do not need to update the allocation structure. You only need to reverse the incorrectly assigned posting before repeating the settlement. Exception: For an investment measure with a line item settlement, you need to extend the allocation structure, even after the reversal.
    If the posting was made correctly, you can do the following:
    a) You can assign a different allocation structure to the sender: In the master data maintenance for the sender, choose "Settlement rule -> Goto -> Settlement parameters" and then enter a different allocation structure.
    If necessary, also check whether the correct allocation structure is entered in the settlement profile. The allocation structure is defaulted in the settlement profile when you create sender master data or when you maintain the settlement rule.
    You can update allocation structure A1
    Please advise,
    Regards,
    Samaar

    Hi Guru's
    We are also facing same issue.  By mistake our implementation partner has configured cost element category as 01 instead of 22.  When we try to run S_ALR_87013558 -- actual cost in the report is getting doubled.  The cost element for settlement created by the CO team is of category 1 ( expense type) because of this after settlement the expenses get added. The cost element for settlement should be of category 22 which is by default exempt from budget.
    This is s serious problem.  Please help us urgently

  • Sales order settlement error

    Hi all,
    I getting an error when i created a sales order, while saving the system through an error : settlemet profile zz1 does not exits"
    the same i simulated in the Quality system it is working fine.
    when i have done the analysis, the settlement profile ZZ1 is not there in both the system.
    can any on please give  light on this.
    thanks
    Kuntla

    Dear GopalKrishna,
    Check with:
    T. Code: VA88
    > Environment> Customize Settlement.
    For more, read:
    Sales order settlemet-VA88
    Hope, this information may help you.
    Best Regards,
    Amit

  • Settlement Error : Message No. KD561

    My client has the following requirement,
    For Example,
    Client has undertaken a million dollar project for a customer. It has encurred a cost (for example say $500k). The WBSE element used to caputre the cost is defined as Account Assignment as well as Billing element. The project reaches a certain milestone and the customer is send a invoice for a payment of $100K. We have assigned the same WBSE during the creation of Sales order and created the billing invoice of $100K. We are not using the milestone. The above cost is Expense and not to be captalized. The revenue received from the customer is to be booked against the cost incuured on the project. At the end of the month, we settle all the cost on the expense project to the Cost Center.
    When I run CJI3 for that particular WBSE, following are the entires,
    a.........Dr. 500K
    b........Cr.  100K
    Total Cost ...400K
    At the end of the month, when I am trying to settle the WBSE to the cost center (in the settlement profile, CCtr is a valid reciever), it gives me the below error message,
    "Settlmnt from revenues/debit-side down paymnts to receiver CTR 101500015 not allowed
    Message no. KD561
    Diagnosis
    The sender has revenues or customer down payments with cost element 51810010 (business transaction: CO Through-postings from FI).
    You cannot settle these revenues or customer down payments to receiver CTR 101500015.
    Procedure
    Change the settlement rule for the sender. It can be useful, for example, to use a source structure to settle costs and revenues separately to different receivers.
    Note
    Revenues or customer down payments can only be settled to G/L accounts, profitability segments, sales documents, real estate objects, orders with revenues, or WBS elements."
    Any suggestion would be appreciated. Any suggestion for the alternative ways to perform the above scenarios.?
    Regards,

    Dear Jatin,
    There is a confusion in your statement, in the first line you have mentioned
    Client has undertaken a million dollar project for a customer
    So we understand it to be a Customer Project, for which there will be a revenue.Further in your query you have mentioned,
    At the end of the month, we settle all the cost on the expense project to the Cost Center
    Here you have mentioned it as Expense project, so should we assume it as "Overhead Cost Project",If it is so then your settlement to cost center is correct,In this case you should not generate any revenue.
    But if your first statement is correct, then your settlement reciever should be reconsidered as mentioned by Praveen.

  • Process order settlement error

    Hi all
            while doing settlement of process order in KO88, system throwing the follwing error.
                     '' valuation data for the material is being locked by the user xxxxxx'' .     If we check in transaction: SM12 , here system showing MARA, MARC tables being locked.
            Some background jobs also running which include MARA,MARC tables.   so please suggest me the best way to do settlement of process orders.  The background jobs should not stop.
    thanks
    sapproduction

    HI
    At the  same time one masters like material WC or PV cannot be processed the database tables used are locked while processing the same to get resolve this  check the time  of scheduled jobs which uses tables like MARA MARC after the finish of these jobs you can process the settlement if you get unlock the data from T code SM12 there is possibility of getting data lost. so
    you can define your settlement process and schedule it just after the completion of those previous Jobs.
    Check and revert
    Regards
    Anupam Sharma

  • CJ88 - Settlement values are not appearing in CJ88

    Hi,
    I am not able to see any settlement values when i run CJ88. I have followed below steps.
    1.     Create Sales Order (TC: VA01)
    2.     Post Outbound delivery and PGI for the sales order (TC: VL01N)
    3.     Set the Order (Project) status to REL (TC: CJ20N)
    4.     Create Rework WBS/Network and Activity element at the project (TC: CJ20N)
    5.     Post one direct labor cost and rework entry to the order (CN25) (Use Activity type TECHXX for direct labor cost and RWRKXX for rework labor cost)
    6.     Post overhead (CJ44)
    7.     Post RA (KKA2)
    8.     Post Settlement (CJ88)
    9.     Change the order status from REL to TECO
    10.     Post RA (KKA2)
    11.     Post Settlement (CJ88) (Here you should see the costs posted to rework order should get settled to GL account 600724000)
    I am stucked at step 8, when i ran CJ88, i am not able to see any values. I have checked allocation structure and it is correct. Please help to resolve issue a.s.a.p.

    Hi,
    After step 5 verify CJI3 report. This is to show actuals against a project. Ensure the costs are posted correctly to the project. Next before OH calculation, do CJ88 for netowork so that it settles the cost to WBS Element. Then run the CJ44. During KKA2 verify the values make sure system calculated the PoC correctly. If everything till here is fine then run CJ88 for the WBS. System should picke up the RA values and post the settlement entries.
    PS: all the above assuming RA / Settlement configs are in place.
    Regards
    Sreekanth

  • WBS Settlement error

    Hi,
    We have a negative balance in area 02 of AuC. We cannot settle that to asset as no negative values are allowed to fixed assets and we cannot change that setting too. Now we posted a manual correction entry to WBS and settled it to AuC to nullify the balance in area 02. The balance got nullified in AuC but we are getting the error " Acq value -ve in area 02" for the fixed asset. Is there any way by which we can get rid of this so that we can make further postings to WBS and settle the same to fixed asset?
    Regards,
    DP

    HI DP,
    The cleanest procedure is to allow the negative posting, either at the asset or change configuration.
    SPRO > Financial Accounting > Asset Accounting > Valuation > Depreciation Areas > Define Depreciation Areas
    and
    SPRO > Financial Accounting > Asset Accounting > Valuation > Depreciation Areas > Determine Depreciation Areas in the Asset Class (OAYZ)
    You state you cannot change the negative value setting...it can be changed technically, so are you stating there is a procedural reason you cannot change?
    Regards,
    Kent Bettisworth

  • OPEX settlement error

    Hi Guys,
    I have a problem when trying to settle the opex project. I get error message "For document type SA, an entry is required in field Doc. Hdr Text". There was a journal created against the project and the document header field was filled. The settlement rule is cost center.
    Thanks
    Koko

    Hi,
    Please refer SAP Note 770285.
    Hope it will be helpful.
    Tnx.
    abdul.

  • Consignment and pipeline settlement error

    Hi Expert!
    I have error when processing consignment and pipeline settlement for company code 4424. The error is "No message was found for partner 146073/company code 4424". Can anyone tell me what has going wrong and how to solve it?
    Thanks.

    HI,
    The MRKO Transaction only for settling the Pipe line and Consigmnet pscenarions.
    No effect if u maintain as like that.
    If u have doubt do one in Devlopmet.
    Regards,
    Andra

  • MRIS- invoice plan settlement error

    I have created invoice plan using the standard SAP supplied periodic invoicing plan. When I go to tx MRIS and enter  Co code, plant, vendor, purch doc and then in document selection 3( I have tried 1, 2 and 3) but I get an error " no document selected" I also have created output for Invoice with co code combination
    What am I missing? Need help
    Thanks
    Raj

    Hi,
    If you are not going to send the payments automaticaly via ERS, then you must post the invoices normally via MIRO with reference to that PO. the system will then check the value and the dates on the invoice plan to see if the invoice should be cleared for payment or blocked.
    MRIS is only used if you want to settle the payments without entering an invoice (i.e. automatically as the oayment dates fall due)
    Steve B

  • ERS Settlement Error message Reg

    Dear All,
                      Im doing the ERS settlement configuration first time i have configured the Messages and outputs but at the time of settlement run it is showing error message as "ERS Settlement No message was found for partner 305469 company code 1000"
    how to resolve this issue...
    REgards
    Anand.

    hi,
    have you configured the condition record for the output  type ERS with that particular vendor what you are using.
    check and revert back.
    Regards,'
    velu

Maybe you are looking for

  • Bonjour printer not showing up in Printer List

    I am having trouble adding a bonjour printer (HP PSC 1610). The printer is not showing up in the list of printers under System Preferences > Print & Fax. I was able to add the printer by clicking on the "+" sign. It found the bonjour printer and I cl

  • Time machine: Can I target specific folders for back up

    As a default time machine backs up your entire drive. Along with my mac I want to back up a +specific folder+ on my Drobo: an external drive. (it's where I keep my large working files) I don't want to, don't need to and can't back up the entire Drobo

  • RE:WebDynpro for Java (Model)

    Hi all, I have created a model using Depricated webservice in WebDynpro DC  it is working fine.But after that i have modified that webservice the changes are not reflected to my model and the error iam getting method not found so how to update my mod

  • Populating the email address (SMTP_ADDR) in Vendor Master using PRAA

    Hi, experts! We would like to start using transaction PRAA (program RPRAPA00) to create and update Vendor Master Data based on HR employee data.  As part of this process, we would like to populate the "E-Mail" field with data from infotype 105.  (We

  • Good apps to get for ipod touch

    hi, i was wondering if anyone could suggest any worth-while games (free and paid) that i should get? thanks!