CJ88 Settlement Processing Type

Hi,
I would like to know the correct "Processing Type" to specify in Actual Settlement run (CJ88) for settling to Asset Under Construction (AUC) and Final Asset.  Please confirm if it is correct to use "By Period" for settling to AUC and use "Full Settlement" to settle to Final Assets.
Thanks!
Vivian

we enter processing type in the intial screen of project settlement which controlls the settlement process.
With processing type By period : only distribution rules with settlement types to PER ( Periodic Settlement ), PRE( preliminary settlement ) & AUC ( Asset under settlement ) are taken in to account.
How ever settlement to AUC will happens at last.  So, if  with this sequence if you have maintained any settlement type PRE( Preliminary ) , it will consider it first & therefoe settle cost portions that are not to be capitalised.
If  I  say in the context of your question,
With the first settlement of WBs sys automaticallty generates a distribution rules for the settlement type AUC.  If you don't want to settle all the cost of  WBS to AUC, you must enter additional distribution rule for the debit to other receivers that are not to be capitalised. Use settlement type PRE ( Preliminary ) to ensure that these distribution rules are taken into account before the settlement to AUC.
Once the Assset under construction Phase is completed,  create a completed asset. We does the same in Cj20n. next, define the distribution rules in the WBS element with settlement type FUL for the cost portion  to be capitalised and enter the completed asset as receiver.
Not that distribution rule with settlement type FUL is only taken in to account in the project settlement if you ahve used Partial Capitalisation / automatic as the processing type
So, in short
when you want to settle to AUC use the distribution rules with settlement type AUC (generated by sys) & processing type periodic
when  you want to settle to FXA you should use the settlement type Full  &  processing type partail capitalisation / automatic.
However the processing type Full settlement is used for the settlement rules with distribution rules of settlement type PER ( Periodic ) only, in to check weather the balance still exists in the object after the settlement due to debits to previous periods.
So, don't get confued with settlement type FUL (full settlement )   & processing type Full settlement.  ( processing type full settlement has nothing to do with AUC )
Regards
Nitin
Edited by: Nitin  Patoliya on Dec 12, 2008 9:43 AM

Similar Messages

  • Authorization in CJ88 by Processing type

    Hello,
    Our customer requires to split authorization roles for settlement processing by Processing type in CJ88. So, one group of users should be able to use only periodical settlement (automatic and by period), and another one only final (partly and final capitalization).
    Does anybody know how to do it?
    Thanks in advance!
    DD

    HI
    One option is you can havetwo  test user ids and test those requirements. Let you basis team starts the trace and find what are all objects it passes throgh during performing settlement run.
    Hope that will work and discuss with your basis team.
    Regards,
    PSR

  • Processing Type in Settlement

    Dear All,
    Is there any idea about Processing Type in Settlement, Can u give some help on it.
    Regards

    Hi Raj,
    The processing type in settlement is relevant for the type of processing you are going to do.
    Typically they are Automatic, Partial capitlization, by period and Full settlement.
    For Manufacturing orders you normally keep it as Automatic. When you keep "Automatic", system will automatically pick whether the periodic settlement or full settlement depending on the Order Type and the settlement profile settings.
    In case of Internal Orders being used as investment orders where the capital expenditure is captured to Internal Orders and then settled to a fixed asset, in such case we need to specifically choose the settlement type whether it is partial capitalization or full.
    Hope this gives a good understanding about the settlement type.
    Please do let me know if you need futher details in this regard
    Best Regards
    Surya

  • CJ8G Settlement Reverse Processing Type (CO forum)

    Hi Gurus,
    The following issue had been posted in the PS section without luck, maybe here can be answered.
    When I reverse a settlement with a given selection variant I noticed that not only automatic settlements were reversed but partial capitalization as well, regardless whether during the reversal the "automatic" processing type was set. Is this normal? Can I set somewhere in the system that reversal will keep the settings in the processing type field?
    Thanks in advance
    g

    Hi,
       Please refer note 336557.
    regards
    Waman

  • CJ8G Settlement Reverse Processing Type

    Hi Gurus,
    When I reverse a settlement with a given selection variant I noticed that not only automatic settlements were reversed but partial capitalization as well, regardless that when during the reversal the "automatic" processing type was set. Is this normal? Can I set somewhere in the system that reversal will keep the settings in the processing type field?
    Thanks in advance
    g

    Hi,
       Please refer note 336557.
    regards
    Waman

  • Order Settlement Process in Discrete/Project

    Hi,
    a)I would like to know the Production Order Settlement Process in Discrete Industries and for a Production Order with respect to a Project.
    B) What configuration steps are required to do the Production Order Settlement?
    c) I have completed Confirmation of the Production Order and "Delivery Completed" indicator is marked in Goods Receipt Tab of the PRoduction Order.
    Can anyone tell me the steps to be followed one by one to do the Production Order Settlement.
    d) From where we can check whether Production ORder Settlement Rule is created or not?. What configuration steps are required to create this rule for a Production order and what steps are to be performed after this rule is created.
    Appreciate if someone provide me inputs to my above queries.
    Thanks in advance for your support.

    Hi,
    Find the answers for your questions..
    a)I would like to know the Production Order Settlement Process in Discrete Industries and for a Production Order with respect to a Project.
    After all PP activities are done production order techo is done... then controlling people will do following activities..
    Variance calculation - KKS2
    Settlement - KO88
    B) What configuration steps are required to do the Production Order Settlement?
    For this lot  of configuration is required from controlling module..check with FI/CO consultant on this..from PP side they will give settlement profile..you need to maintain this in order type configuration on OPJH
    c) I have completed Confirmation of the Production Order and "Delivery Completed" indicator is marked in Goods Receipt Tab of the PRoduction Order.
    Can anyone tell me the steps to be followed one by one to do the Production Order Settlement.
    you need to change the status of the order to TECO then inform controlling they will do following activities...
    Variance calculation - KKS2
    Settlement - KO88
    d) From where we can check whether Production ORder Settlement Rule is created or not?. What configuration steps are required to create this rule for a Production order and what steps are to be performed after this rule is created.
    in the order header status you can see settlement rule is created or not. It will have the status SETC. Settlement rule is created during order creation stage only..no separate configuration required for this..
    Hope this helps...
    Thanks
    Kumar

  • Processing type in ko88

    Hi Expert,
    is there any standard setting to configure processing type in t-code KO88. e.g. disable one of options
    Thanks
    Rgds,

    Hello Stephanie,
    You can not change the processing type options. They are provided to cater to various requirements.
    1. In  Automatic all distribution rules for a sender are selected. If a sender only has distribution rules with the PER settlement type, then only the settlement period costs are selected and settled.If a sender has distribution rules with the the PER settlement type (PER rules), and distrubution rules with the FUL settlement type (FUL rules), then the PER rules are used first for the costs in the settlement period. If there are still costs left over, then the FUL rules are used.
    A production order with a FUL rule to Material is only settled once it is technically completed, or completely delivered. Until then, however, "work in progress" can be transferred to financial accounting, if the WIP was calculated.
    2. In  Periodic all distribution rules with the settlement type PRE, PER and AUC are selected. The PER rules are applied first (except for investment measures).The PRE rules are applied first for investment measures, and then the remaining amount is settled with the automatically generated AUC rules to the asset under construction.
    3. You use Partial Capitalization  processing type to partially capitalize an investment measure that is not technically completed, so that a part of the total cost to complete assets is settled.
    4. Full Settlement : use this type of processing if a sender only contains distribution rules with the PER settlement type, and if a balance check is to be made after settlement
    Kind Regards // Shaubhik

  • Settlement process

    Hi experts
    I would like to go for brief about the settlement Process.
    Please explain
    1. How to settle 60% to other cost objects?
    2. What the industries need to follow the procedure for right periodic settlement
    3. Incase in mtc order 70% work is completed in that period ? HOw to settle? balance how to settle?
    4. any one tell me what procedure u r following ?
    5. how to inform the users?what we can do for the orders which is created on last week of month?
    6. Which run is better ? KO88 or ko8g
    i am waiting for your valuable inputs ..
    Regards
    Thenna

    Hi
         There are 2 type of settlements 1) Periodic 2) Full settlement
    1)For 60% enter the settlement percentage rate 60% in the settlement rule
    3)Enter the partial amount as settlement %(say 30%,50%) in settlement rule. & run the settlement (K088)
    5)FI/CO will take care of settlement activities.just u have to follow up with them.
       we can see in cost overview of order (planned value/actual value/settled value)
    6)KO88 is single order settlement
       KO8G is for group of orders
    Thanks
    Seenu
    Reward points if it useful

  • How to find the original CO document after the settlement process

    Does is posible to know the original CO document (from MM, FI or RH...) after the settlement process?
    We need to find a table or just a report in order to mapple the original CO document with his new CO document after the settlement.
    Kind regards.

    If you are talking about project settlement then you can look in report CJI3, the transaction type for settlement transaction is KOAO. You may run a filter and double click the relevant line item to drill down and see the original settlement document.
    Regards,
    Ammar

  • Custom Process Types not working in SAP BPC 10.0

    Hi Experts,
    We have migrated from SAP BPC 7.5 NW to SAP BPC 10.0 NW.
    We have three Custom Process Types created in BPC 7.5NW using the super class CL_UJD_SIMPLE_ACTOR as super class.
    It has been made Obsolete and Final class in BPC 10.0NW and the Custom Process types are not running as expected.
    Can you please suggest if there is any alternative for using the existing custom process types? Or do we have any alternative for creating custom process types?
    *Note: We have tried replacing the superclass with CL_UJD_ACTOR instead of CL_UJD_SIMPLE_ACTOR but of no use.
    Regards,
    Balraj.

    Hi Inl,
    The statement looks fine, just confirm:
    Your CATEGORY dimension is named CATEGORY? Is it really has property COMPARISOIN?
    Can you show the screenshot of UJKT run of script?
    What is your core BPC SP?
    Vadim

  • BI custom process type (ABAP OO Class): how to create a variant screen?

    I created a custom process type in Netweaver 2004s (business intelligence) which in essence is nothing but an Abap class that implements certain interfaces. What I am now struggling with is how to write the code for the "new variant" input screen.
    My understanding is that the logic has to be implemented in the method IF_RSPC_MAINTAIN~MAINTAIN, but I am lacking detailed information.
    Can someone give me an example with a variant screen that displays two radio buttons?
    Thank you,
    D.

    It is a custom class that implements the following interfaces:
    IF_RSPC_GET_VARIANT
    IF_RSPC_MAINTAIN
    IF_RSPC_EXECUTE
    The interface I am struggling with is the first one (get variant). Any more insight on how this should be used would be highly appreciated.
    Thanks!

  • How to capture the process type for a particular application

    In my application CRMD_BUS2000120 there are 3 process types namely incidents, zcomplaints and zrepair order. But all the 3 display the same description as New: Incidents . Since this is attached with the application name. How can i change the description according to the process type i select. If I select incidents the description should be Incident , if i select zcomplaints it should be zcomplaints. Can anyone guide me how to do this.
    Thanks in Advance,
    Anu

    Hi Fred,
    If you open any activities or opportunities, you can see the description if you select new button and click on the process type. It will be display Activities and below that New: Activity. Instead of always displaying the same description I want to override the description according to the process type. For me the application is not activity but Incident. Hope I am clear with the question.
    Thanks,
    Anu

  • Charateristic variable with Processing type "replacement path"

    Hi all
    I am using BI 7.0;
    I have a characteristic ZPL_CNT in one dimensions of a Cube;
    now i want to use the value of  the ZPL_CNT as column in Query.
    So i created a formula and a formula variable with replacement path of processing type:
    setting:
    i created a new formula "Calculated MBZ"
    the formula variables is "ZMBZ" and inserted the variables into "Calculated MBZ"
    Reference characteristic: ZPL_CNT
    Processing type : Replacement path
    Replace variable with: Attribute value
    Attribute: characteristic Reference (constant 1)
    But i find the value in Query incorrect
    Can anyone help me solve this problem?
    Thanks!

    Hi Dragon,
    Can you not drag and drop this characteristic directly in the columns...have I misunderstood something?
    I think when you use replacement path in the formula variable , the fromula variable tries to find the reference characteristic value at each record level in the report and then replaces it with attribute value as defined and may be in your case as the characteristice is not defined in the row , it has problems to identify which value of the characteristic it has to replace.
    Regards,
    Sunmit.

  • Email Alert for Process Chain for ABAP Process Type

    Hi BW Experts,
                             I created a process chain based on ABAP Process Type ( for Broadcasting rsrd_broadcast_starter). I want to add alert message for each ABAP process if it is failed. But I cant see any option showing Successfull or Error or Always when I select create message option on the process type. How ever I can see for other process chain which is loading data (Process Type is Info Package ) from SAP into BW.
                             Please some one tell me why it is not showing alert message for ABAP Process Type.
    Thanks
    Ganesh Reddy.
    Edited by: Ganesh Reddy on Jul 13, 2009 10:16 PM

    I dont have the exact answer for your question, But as a work around i can suggest you that.
    If these ABAP programs are included in a chain and this local chain is a part of meta chain then you can create a message on the local chain.By right clicking on the local chain >Create Message>Success
                                                                                    --->Failure
    >Always
    Hope this resolves the problem tempervorly.I will get back to you once i have
    Or the permanent solution is
    Its big and also easy method to perform, by this you will be able to get all the options for a ABAP Program also.If you have any questions please let me know.
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/business-intelligence/a-c/creating%20an%20abap%20process%20type%20for%20process%20chains%20in%20bi.pdf

  • What is the difference between  Process Type TRIGGER AND CHAIN

    What is the difference between these two process types.  When I am looking process types, I want to provide information only about process chains and not individual steps of process chain. Looks like one can do using either.
    Along the same line, I am looking  at  data from RSPCPROCESSLOG, no where this table has a column process chain id. So How od I find information about a process chain.
    Thanks a lot,

    A "Chain Process" can be a a step in a Process Chain as well.    For Example: So you could have the following Process Chain:
    Process Chain Example
    Step 1. TRIGGER (Execute Daily at 4am)
    Step 2. DTP_LOAD Execute DSO Load
    Step 3. DTP_LOAD Execute InfoCube Load
    Step 4. CHAIN Execute Master Data Process Chain
    I believe the "Master Chain" is called a "MetaChain" since it controls the start of another Process Chain.
    Hope that helps...

Maybe you are looking for

  • Bridge just wiped out scores of folders and hundreds of photo files

    Bridge CS3 (2.1.1.9) just did an absolutely terrible thing to me - so terrible that I fear ever to again use what I once thought was a great program. I keep a blog (http://wasillaalaskaby300.squarespace.com/) and I was working on my latest entry. The

  • Can get appletv to work with my Hitachi television.

    Can't get AppleTV to work with my Hitachi P42H401.  Any ideas? We replaced the AppleTV, replaced the HDMI cable, tried all three HDMI ports and inputs. I'm bumfuzzled.

  • Running Apple Hardware Test

    the manual says to disconnect everything except the mouse and keyboard, then reboot holding D to enter the hardware diagnostic program. When I follow those directions the computer displays a blank grey screen for a very long time and then boots up no

  • My ipod camera shutter wont open

    hey i know that there is alot of discussions about this already but i have tried reseting my ipod, that restarting thing where you hold down the home button and the off button, and restoring it which failed terribly because the back-up failed and i l

  • How does this UPDATE update multiple rows?

    For the UPDATE in the following script, what values are selected to update Table2? For example, for a row in Table2 (ie. 'NY') there are several rows in Table1 that can be used for the update. Thanks. create table Table1 Col1 varchar(10), Col2 varcha