CK 11 N

Dear all..
Our client does not require product costing.
He just intrested to run Cost estimates with Qty. Structure i.e.CK11N.
I just want to know what settings are required for that..from start to end.... from controlling area settings to costing sheet if required..
It will be better if anybody will provide configuration links or guides..

HI Ranjeet,
Your client does not required prodict costing , but still he want CK11N means???
Which is your process either  REM, PP or PP-PI.
In REM - repetative manufacturing there is  be product costing  like
1. u have product cost collector
2.production version
3. do ck11n
4.ck24
then cost is updated in the materil master of costing view.
In CK11N  you are runing the cost for a materil for certain period with giving input prd version, costing lot, dates.
once Ck11N is complet then you are do  Ck24 i.e marking and relase the cost.
Because of product cost collector the cost is collectd here and this cost is called priliminary cost , which is  quanity structure of BOM component.
This is monthly activity and then settle the cost.
regarding to sheet, check OPN2, you are responsible to gve valuation varrient to CO consultant so that it assign into costing sheet.
CO consultant defines the REL stratyegy of costing, then over head cost parameter etc in costing sheet.
For more details plz check the SPRO settings of  PRODUCT COSTING
Regards
Siddhesh