Hi experts,
for ETL tests, can i connect an ECC Produktiv system mandant copy to BW development system or shold it be a system copy.
Thanks.

Hi,
Don't connect Production ECC for Development BW. you can copy the client then you can use it.
The better landscape is
BWD -->BWQ-->BWP
  |       |           |
EWD -->EWQ-->EWP
Thanks
Reddy
Edited by: Surendra Reddy on Jan 30, 2009 12:55 PM

Similar Messages

  • Accounting document not copied after system copy.

    Hi,
    We copied the production system into our test system using backup/restore.  In the post copy verification, our CO team complained because they could not see the "accounting documents".
    What do you think happened why the accounting document was not copied?
    thanks
    krbas

    Hi Krbas,
    Make sure you did all the post processing activities after system copy. I doubt you missed some post processing activities related to CO after your system copy.
    regards,
    VInodh.

  • Formulas not copied during system copy

    Hi All ,
    Recently we copied non-prod quality system to create new Dev system. In the process we have realised that in transformations ,formulas havent been copied to the new system .This is resulting in Processs chains failing with error "Assertion failed"
    Has anybody faced such an issue before . Would appreciate all your help.
    Thanks

    Hi Krbas,
    Make sure you did all the post processing activities after system copy. I doubt you missed some post processing activities related to CO after your system copy.
    regards,
    VInodh.

  • System Copy from ABAP Stack to ABAP+Java Stack

    Hi,
    Is it possible to system copy (homogeneous or heterogeneous) from a system based on ABAP Stack to a system based on ABAP+Java Stack? Is it the normal system copy procedure or something aditional is required to do. Pl. advise. Thanks
    regards
    Edited by: Abdus Samad on Oct 24, 2008 8:13 AM

    It depends on what you want to copy, a system copy will always wipe out the existing target. But if you want to only copy data, you might be able to do a client copy. You can start with this SAP note: [552711 - FAQ: Client copy|https://service.sap.com/sap/bc/bsp/spn/sapnotes/index2.htm?numm=552711]
    Regards Michael

  • Homogeneous System Copy - Help me

    Hi,
    I need to refresh the Training environment with the QAS environment data then I did the client copy from QRP(QAS environment) to TRN (training environment). This copy was made successfully, but with some data inconsistences.
    And then a decided to do a Homogeneous System Copy.
    I did the HSC selecting the option "Standard System Copy/Migration (R3Load-Based) " but exist the another option "System Copy / Oracle Backup/Restore".
    And my doubt is: the process that I need to do is the Standard System Copy / Migration (R3Load-Based) or System Copy / Oracle Backup/Restore?
    And the inverse process (import), can I to install just a Database Instance, once that a Central Instance already exists?!
    Thanks and Regards,
    Dany Anderson

    Hii the process you need to do is system copy . In system copy there are two ways one by using R3load tool and other is backup method. Generally the backup method is faster where all your database will be backedup and copied to the target system. R3load and oracle backup are just two methods of doing system copy.
    homogeneous system copy if your target system is on the same operating system and database system as your source system. The database contents are copied from the source system to the target system.
        You perform a heterogeneous system copy if you want to change the operating system or database system. Migration is another term for a heterogeneous system copy.
    Please reward points if useful

  • System Copy - Homogenous and Heterogeneous

    Hi All Experts,
    Could one of you, please explain me the steps how to performed Homogenous,
    Heterogeneous, Client copy and System copy. Please help.
    Thanks,
    Frank.

    Hi Frank,
    For client copy there are two types one is Local client copy which is with the system and Remote client copy which is copy of client from one system to another system.
    Local client copy :
         1. scc4 .. entry for new client
         2. logon to the new entered client with SAP* password: pass
         3. sccl ..select source client and target would the one u logged in currently.
         4. Set the parallel processes ( depends on u r cpu) normally 6 -16
         5. Start in dialog
         6. check the logs in SCC3 .
    Remote client copy:
    1. Scc4 entry for the client.
      2. SCC8 RFC maintain .. folow the screens
      3. Scc3
    System Copy:
    1. Take the offline backup of the source system and the control file.
    2. Restore the backup on the target system.
    3. change the control file path.
    4. change in the control file where this RESET to SET
    5. Startup database in mount state.
    6. Run the control file.
    7. open the database with command : alter database open resetlogs;
    8.All Done !!!
    I hope its helpfull ..

  • Error in "Run Java migration toolkit", doing a SAP system copy.

    Hi all,
    Migration to new hardware with system copy, get an error in CI installation on "Run Java Migration Toolkit".
    From the sapinst.log:
    ERROR 2009-05-13 12:46:47.188
    FJS-00003  TypeError: ci.getInstanceDir() has no properties (in script NW_Doublestack_CI|ind|ind|ind|ind, line 120276: ???)
    ERROR 2009-05-13 12:46:48.318
    FCO-00011  The step InitPrivateContext with step key |NW_Doublestack_CI|ind|ind|ind|ind|0|0|NW_CI_Instance|ind|ind|ind|ind|12|0|NW_CI_Instance_Configure_Java|ind|ind|ind|ind|4|0|NW_RUN_MIGRATION_CONTROLLER|ind|ind|ind|ind|2|0|InitPrivateContext was executed with status ERROR .
    From the sapinst_dev.log:
    ERROR      2009-05-13 12:46:47.188 [iaxxejsbas.cpp:204]
    FJS-00003  TypeError: ci.getInstanceDir() has no properties (in script NW_Doublestack_CI|ind|ind|ind|ind, line 120276: ???)
    TRACE      2009-05-13 12:46:48.038 [syuxctask.cpp:1382]
               CSyTaskImpl::start(bool)
    A child process has been started. Pid = 23620
    ERROR      2009-05-13 12:46:48.318 [sixxcstepexecute.cpp:951]
    FCO-00011  The step InitPrivateContext with step key |NW_Doublestack_CI|ind|ind|ind|ind|0|0|NW_CI_Instance|ind|ind|ind|ind|12|0|NW_CI_Instance_Configure_Java|ind|ind|ind|ind|4|0|NW_RUN_MIGRATION_CONTROLLER|ind|ind|ind|ind|2|0|InitPrivateContext was executed with status ERROR .
    TRACE      2009-05-13 12:46:48.368 [iaxxgenimp.cpp:752]
                CGuiEngineImp::showMessageBox
    <html> <head> </head> <body> <p> An error occurred while processing service SAP NetWeaver 7.0 Support Release 3 > Software Life-Cycle Options > System Copy > Oracle > Target System Installation > High-Availability System > Based on AS ABAP and AS Java > Central Instance . You may now </p> <ul> <li> choose <i>Retry</i> to repeat the current step. </li> <li> choose <i>View Log</i> to get more information about the error. </li> <li> stop the task and continue with it later. </li> </ul> <p> Log files are written to /tmp/sapinst_instdir/NW04S/LM/COPY/ORA/SYSTEM/HA/AS/CI. </p> </body></html>
    TRACE      2009-05-13 12:46:48.368 [iaxxgenimp.cpp:1255]
               CGuiEngineImp::acceptAnswerForBlockingRequest
    Waiting for an answer from GUI
    I had checked the INSTANCE_NAME parameter, in every profile, and is ok.
    I tried a new instalation, after importing the profiles, and checking the INSTANCE_NAME, but got the same error.
    Please, advice.
    Thanks in advance.
    Best Regards.
    Jorge

    Thanks Manoj for your advice.
    We had already checked the procedures, we are working based on the System Copy Guide: "System Copy for SAP Systems Based on SAP NetWeaver 7.0 SR3 ABAP+Java".
    I had to mention that source and target systems are HP-UX, 11.23, Itanium and the DataBase is Oracle 10.2.02.
    The copy was made from a Central System (ABAP + Java) to a High-Availability System (ABAP + Java), and the problem appeared when copying the Central Instance.
    Thanks in adavance.
    Regards.
    Jorge

  • How to rename global_name to NEW_DBSID after System Copy

    Hello,
    I changed SID D22 to S11 during system copy.The System Copy guide recommends to rename global_name on Oracle.
    I have some questions.
    1) Is the following procedure correct?
         SQL>alter database rename global_name to S11;
    2) If I do not rename global_name, what happens?
    I refer to the guide "Homogeneous and Heterogeneous
    System Copy for SAP Systems Based
    on SAP Web Application Server
    ABAP 6.40 SR1".
    6.2 Performing Follow-On Actions in the
    Target System
    Oracle: If you changed the <DBSID> during the system copy, it is recommended to adapt the global_name parameter with the following SQL command:
    alter database rename global_name to <NEW_DBSID>;
    If the parameter is not existing on your system, ignore this step.
    thanks,
    Keishi

    Hello Keishi,
    just for information.. the official oracle documentation about that topic:
    http://download.oracle.com/docs/cd/B19306_01/server.102/b14231/ds_admin.htm
    > 1) Is the following procedure correct?
    Here is a test in my MDD test database:
    SQL> SELECT * FROM GLOBAL_NAME;
    GLOBAL_NAME
    MDD.WORLD
    SQL> ALTER DATABASE RENAME GLOBAL_NAME TO MDD2.WORLD;
    Database altered.
    SQL> SELECT * FROM GLOBAL_NAME;
    GLOBAL_NAME
    MDD2.WORLD
    SQL> ALTER DATABASE RENAME GLOBAL_NAME TO MDD.WORLD;
    Database altered.
    SQL> SELECT * FROM GLOBAL_NAME;
    GLOBAL_NAME
    MDD.WORLD
    > 2) If I do not rename global_name, what happens?
    If you use a distributed database system, you need to identify each database by a unique identifier (the global name).
    For more information, take a look at the oracle documentation:
    http://download.oracle.com/docs/cd/B19306_01/server.102/b14231/ds_concepts.htm#i1007500
    Regards
    Stefan

  • Homogeneous system copy on the same hardware and OS

    Hi!
    When I installed our Q system I was given the wrong user, a local admin instead of a domain admin. Now we can not perform backup with our backup tool, HP dataprotector, because of authorization issues.
    My solution is to "move" the system to the domain and to do that I need to do a Homogeneous system copy.
    Our system is a 64-bit CRM 7.0 ABAP and J2EE on Windows 2008 with Oracle 10.2
    I've read note 676468, 1238351 and the System Copy Guide - System Copy for SAP Systems Based on SAP NetWeaver 7.0 and from this I can see the following ways to do it
    1. using SAPinst for export and import
    2. using an offline backup
    3. copy database files
    What are your experiences with the different methods and what would you recommend?
    rollo

    > that seems to me a bit overdosed for just a user mismatch...
    It is not "just" a user mismatch, the full environment is wrong (wrong user ID).
    Windows stores users not as usernames but as UIDs (see HKEY\USERS in the registry). All permissions and ACLs and registry access permissions are using that UID - including the enviornmental settings, DCOM configurations etc.
    Therefore I would go for system copy as stated in
    Note 1233320 - Domain migration for SAP system
    Technically it may work on the first look, problems may arise later. <sid>adm has to have some special permissions/policies that are not visible (like 'locking pages in memory' or 'act as part of the operating system' or 'run as batch') etc.
    Markus

  • System Copy Guide: Exporting the Source System Using SAPinst.

    Hi Gurus,
    I am trying to do Unicode conversion of ERP 2005 SR3 on Oracle/WS2003
    The preparation steps are OK
    When I execute the last Phase using Sapinst : "database instance export",
    it finishes within one minute with the message "Database instance export has been completed succesfully"
    but without exporting data.
    I have follow up Unicode Conversion Guide  and System Copy Guide System Copy for SAP Systems Based on SAP NetWeaver 7.0 SR3 ABAP+Java.
    What could be wrong here?
    Thansk for your help
    Martial

    So you need to set an environment variable
    SAPINST_USE_HOSTNAME = <your-virtual-hostname>
    for the user executing sapinst.
    Markus

  • System Copy using SAPINST on SRM 5.0 + DB MSSQL 2003 + OS Win 2003 Server

    Hi All,
    Im doing a System Copy using export and import method i.e using SAPINST. Export has been completed and now when im doing the import. it stops at Import Java dump and give me this error in
    Jload.java.log
    Apr 23, 2009 5:29:56 PM com.sap.inst.jload.Jload logStackTrace
    SEVERE: com.sap.dictionary.database.dbs.JddException: CREATE TABLE CAF_RT_MAPRLE failed
    17:29:56 2009-04-23 dbs-Info:  <<< Analyze table CAF_RT_MAPRLE >>>
    17:29:56 2009-04-23 dbs-Info:  predefined action is: >>>null<<<
    17:29:56 2009-04-23 mss-Info:  table CAF_RT_MAPRLE doesn't contain data
    17:29:56 2009-04-23 dbs-Info:  Action: DROP_CREATE
    17:29:56 2009-04-23 ope-Info:  Action: DROP_CREATE not possible
         at com.sap.inst.jload.db.DBTable.create(DBTable.java:109)
         at com.sap.inst.jload.Jload.dbImport(Jload.java:278)
         at com.sap.inst.jload.Jload.executeJob(Jload.java:397)
         at com.sap.inst.jload.Jload.main(Jload.java:621)
         at sun.reflect.NativeMethodAccessorImpl.invoke0(Native Method)
         at sun.reflect.NativeMethodAccessorImpl.invoke(NativeMethodAccessorImpl.java:39)
         at sun.reflect.DelegatingMethodAccessorImpl.invoke(DelegatingMethodAccessorImpl.java:25)
         at java.lang.reflect.Method.invoke(Method.java:324)
         at com.sap.engine.offline.OfflineToolStart.main(OfflineToolStart.java:81)
    Apr 23, 2009 5:29:56 PM com.sap.inst.jload.db.DBConnection disconnect
    INFO: disconnected
    Has any one seen this error ???
    Regards,
    Ershad Ahmed

    Hi,
    I would refer the concerned System copy guide "[System Copy for SAP Systems Based on NW 7.0 SR2 ABAP+Java|https://websmp108.sap-ag.de/~sapdownload/011000358700006457662006E/SYSCOPY_2004sSR2_ABAPJava.pdf] " along with this [SAP Note 151603 - Copying an SQL Server database|https://service.sap.com/sap/support/notes/151603] for getting all answers.
    All prerequisites / steps are well mentioned in that documents. Please read them carefully.
    Regards,
    Bhavik G. Shroff

  • System copy tool

    Hi friends,
    I want to know from where i can download system copy tool for BW 3.5 640_REL HPUX 640 itinuim.
    Please help  and let us know.
    thanks.

    Hi:
    Pls chk this document , might be useful
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/bff13df2-0c01-0010-6ba7-bc50346a6fd8
    Check following OSS notes.
    Note 543715 - Projects for BW Migrations and System Copies
    Note 886102 - System Landscape Copy for SAP BW 2.X, 3.X and NW2004s BI
    Note 325525 - Copying and renaming systems in a BW environment
    Note 184754 - Procedure after BW database copy
    BW system Copy :
    System Copy BW
    Re: bw system copy
    BDLS :
    Re: After R/3 Refresh
    BDLS on BW Q/A
    Regards
    CSM Reddy
    *pls assign points if links are useful**

  • System Copy vs Client copy

    Hi,
    I have to choose between a copy with or whitout data from PRD system to DEV.
    I'm little confused about the difference between System Copy and Client Copy.
    Which is that includes a copy of data also?
    Then, System copy = Refresh system?
    Please, reply me directly, without post link.....
    Many thanks.
    Claudia

    Hi,
    Please do an SDN search of these terms.
    Also read SAP Note 886102 for all system copies scenarios.
    Rgds,
    Colum

  • Client Copy and System Restore query

    Dear All,
    I have few major doubt regarding client copy and system restor.
    1. In my Quality system there are 2 clients: 100 and 200.In my PRD there is only 1 client 300(other than the standard default clients). My doubt is during remote client copy with SAP_ALL profile from PRD to QUA why the space increases only in MB.
    I have been asked the same question by my management. They are saying PRD is 300GB and QUA is 220GB then why the space increases in MB though all data is copied in client 200(QUA) from client300(PRD)
    2. If I delete client why the space is released in MB. Because according to them it should be in GBs.
    3. Now my third query is I have to restore PRD backup in QUA.So I said that this requires same <SID> and Same sapce in the sapdatafiles(OS is HP-UX 11.31 and DB is Oracle 10g).So I have to explain them why these two things are contradary to each other. In case of client copy space required is only in MB and in case of System restore of PRD in QUA sapce require is in GBs.
    Your suggestions will be highly obliged.
    Regards,
    PG

    1. In my Quality system there are 2 clients: 100 and 200.In my PRD there is only 1 client 300(other than the standard default clients). My doubt is during remote client copy with SAP_ALL profile from PRD to QUA why the space increases only in MB.
    Response > Because during client copy your customizing and other objects are copied.
                        The database structures,tables etc are already present.
    2. If I delete client why the space is released in MB. Because according to them it should be in GBs.
    Response > Since client deletion is not same as deleting database /customizing tables .If you delete complete dataspaces/tables then there will be sizeable difference.Similar logic as Response 1
    3. Now my third query is I have to restore PRD backup in QUA.So I said that this requires same <SID> and Same sapce in the sapdatafiles(OS is HP-UX 11.31 and DB is Oracle 10g).So I have to explain them why these two things are contradary to each other. In case of client copy space required is only in MB and in case of System restore of PRD in QUA sapce require is in GBs.
    Response > Since in a system copy you will copy data files (which includes tables,and all otehr strucutres ) hence the size required will be similar to PRD.

  • Homogeneous system copy OR Remote client copy

    Dear all,
    We have SAP ECC 6.0 system running on HP Unix and Oracle 10g. This is a production system.
    We would like make an exact replica of this system into a test system for several tests.
    To achieve this, I think there are two ways.
    Procedure 1.
    a. Install ECC 6.0 in similar platform and creat a new client.
    b. Perform remote client copy from production system to new test system.
    Procedure 2.
    a. Perform homogeneous system copy.
    Could you please tell me which procedure would be the best one? and also we would like to know SAP Guide on how to perform this procedure.
    Thank you.
    Regards,
    Prashanth.R.G.

    Hi Prashanth,
    Perform homogeneous system copy is the best solution for your requirment.
    For Procedure for homogeneous system copy look below link.
    https://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/6945da7d-0c01-0010-1792-dd7b5d87235c
    Regards,
    Krishna Reddy