CM23 - Capacity Levlling Production Orders

Hi ,
      When i try do the capacity levelling  for 2 orders in the T-Code CM23 , System has selected all the Production orders in the Eavaluation period .
My Requirement is i want to do capacity levelling for the entered Production Orders i have entered in the selection screen .
How to achive this one ... Please guide me ..
Thank You
kumar

Hi,
In order to achieve it, you have to enter same production orders in both selection and filter sets in capacity evaluation. In CM23, when you branch to filter options from the selection screen, you will not see production orders in the select options. For this reason what you want is not possible in CM23.
In CM25 you can call your own evaluation profiles that has been customized in SPRO. You have to assign filter and selection sets both containing prodcution order in a Z selection profile in customizing. Then assign this selection profile to an overall profile. When running capacity evaluatin by CM25 you must enter production orders in both selection and filter sets.
Regards.

Similar Messages

  • Individual Capacity in production order

    Hi all,
    In which table can we see the individual capapcities maintained in production order.
    Path >>> Production order > operation details > cap reqt assignment
    Regards,
    Yogesh

    Dear ,
    Bssically , it goes from KBEZ Add. data for table KBED -CRHD(Work Centre )-AUFK/AFVC(Operation details at Production Order ) .
    Refer this thread : PP Tables
    Individual Capcity comes from Work Center Addtional Capacity Tab and seats into Operation Overview of Production Order .
    Hope it clarifies
    Regards
    JH

  • Use of Planning Table (MF50) in Capacity Levelling with Production Order

    Hello Experts
    I wish to know that is it possible to perform Capacity Levelling in planning table (tcode MF50) with respect to a Production Order ? It is known that MF50 is used in Repetitive manufacuring to do the capacity levelling with respect to Planned orders. But in our discrete manufacturing scenario we want to use planning table to the capacity levelling with respect toa Production order.
    Any clue or help pertaining to this will be highly appreciated.
    Thanks in advance
    Regards
    Jayanta

    Dear ,
    MF50 is does the cacapcity leveling based on mateail -run schedule order (planned order ) where as in discrete manufacturing , when you run the MRP ,  MRP system assume Infinite Capacity  and schedule the order as per your selection in MD02(2,1,3,3,2)  and then you convert those planned order to Production order .Here you checkied the Capacity in Production Order level .
    In stanadrd SAP  , it is not possible to use MF50 for discrete production order.
    In discrete order or process order ,  do the caapcity leveling , there are seperate planning table available based on Over all Capacity Profile and Schedule type .This can be done  in following way :
    1.CM31-Production Order Wise -Tabular
    2.CM23-PO wise -Graphical
    3.MC88: Ruf Cut Planning
    Work Centre Wise : CM21 -Graphical , CM22-Tabular Planning Table .
    Make sure the below set up before  you carry on the Capacity leveling :
    .Define time profile in OPD2.
    Define the strategy profile in OPDB
    Define the Overall profiles in OPD0.
    In OPJK  maintained check capacity with SAPSFCG013 profile for your production order type
    In OPU3 , scheduleing parametre s: Generate Capacity , Scheduling Type , Automatic Log ,Start date in Past as per your req.
    In OPJU , chekc the contol tab of the scheduleing as per OPU3
    In OPKP- Production scheduling paranmeters assing the overall capacity profile -SAPSFCG013  with finte scheduling tick.
    Master Data :
    1.Materials Master define the Production scheduler and production scheduling profile
    2.Work Center - Define the capcity planner group,activate checkbox Relevant for Finite sceduling,on the capacity header define the shift timings,break timings and unit of measure,no of individual capaity, enter formula for scheduling in capacity view.
    3.Routing - enter the values for the standard values. Use control key with scheduling.
    Hope this will help you .
    Regards
    JH

  • Error while creating production order (capacity leveling)

    Hello Friends,
    For capacity Planning - Leveling, i am using overall profile  "SAPMPSG006 - MPS/MRP: Capacity availability check", in Production scheduling profile, which i have attached in the material master.
    In Availability check parameter, checking control for the combination of Plant,order type and business transaction 1, in capacity availability section also, i have maintained the overall profile "SAPMPSG006 - MPS/MRP: Capacity availability check'.
    Now i have created the production order for a particular period (start date 17.03.10 , finish date 20.03.10). In CM01, agaist the work center, i can see the load. Hence available capacity and required capacity is same for three days.
    Now again i have created one more production order for the same period (start date 17.03.10 , finish date 20.03.10), system is showing the window with the message work center with overload.On the same screen, when  i click on finite scheduling tab, than system showing the new latest start date and time the same as earlier date i.e 17.03.10.
    Here my question is , when i click on finite scheduling tab, than system should propose the date 21.03.10, as on and after this date capacity on this workcenter is available. But system is not proposing the dates, where capacity is available.
    When i checked the dispatching log, there i found two errors.
    continued..................

    Dear,
    That's great production order system is proposing the future date automatically.
    Few check,
    1) Factory calendar for holidays?
    2)Any other production order on that days?
    3)Your capacity profile and its setting?
    Basic dates
    Check whether scheduling should be performed with a time being specified. For this, check the scheduling data of the scheduling type in Customizing. OPU3
    Do the basic dates change?
    Check whether the alternative "Adjust basic dates" has been selected for the scheduling parameters.
    Check whether the basic dates are set correctly on account of the operation dates. So check operation dates also?
    Regards,
    R.Brahmankar

  • Capacity check is not working while creation of Production order

    HI Gurus,
    I want to restict the system that in case of insufficient capacity at the work centers, sysstem should not create the production order. For that i did the setting
    1) Unchecked the tick for the Capacity check & enter the profile SAPSFCG013 in the OPJK for the business functions 1 & 2.& also make the setting for the Release order '3".
    2) Maintain the same profile in the production profile & maintain that profile in the Mat Master
    3) In the CR02, activate the tick for the finite scheduling & uncheck for the can used for several operations.
    But i have creted the production orders & at the time of capacity check system is giving the message " Capacity avaiolable at all the work centers. But i check in the CM50, all the work centers are overloaded at the respective date.
    But i can create & release the p[orduction order.
    Requesting all to give your comments & solutions.
    Regards
    ACP

    ACP,
    ....after confirming all the operations system is allowing me to save
    When you confirm an order, you are by definition saying that the capacity existed for that order (you have just declared to the system that all operatons have been performed, and therefore all capacity was available).  I can't imagine why you would not wish to save that order, since you must somehow post the physical work that has already been done.  Capacity availability check is really only useful when the order to be checked has not yet been executed.
    CM50 displays capacity requirements.  CM50 does not perform the same function as Capacity availability check.  To ensure that all of your orders fall within you capacity constraints, you must perform capacity levelling.  Capacity availability check does not work the same as a Material availability check - don't assume that what you know about a material ATP will be applicable for a capacity ATP.  Read the help on Capacity levelling.  It is not generally possible to stop a manually created production order from being saved, due to any capacity situation, without using an enhancement.
    http://help.sap.com/saphelp_erp60/helpdata/en/60/13e308133a11d3bf550000e83235ee/frameset.htm
    Naturally, you can use enhancements to have the system meet any business requirement that is not met with the standard Cap Availability check.
    Best regards,
    DB49

  • Capacity planning and schedulng production order based on availabe capacity

    Hi Gurus,
    I am trying to use capacity planning, when the production order is created it takes the order start date as the requirement date. Then when i do he capaity check it says capaity not available. After finite scheduling again it proposes to shift operations by certain days.
    I need the capity to be check in MRP and the palled orders to have start dates based on aviable capity, currenty all the palled orders are starting on the requirement date irresptive of avaiabe capaity. I tried using finite scheduling option in MD02 still it does not take in to account exsting production orders for giving dates of the planned orders.
    Regards
    Abhi

    Dear Abhishek,
    1) This is Std SAP of MRP, only material Av check will be carried out in MRP & create procurement
    Proposals
    2) Capacities will not Checked  ( consider ) in MRP in Std R/3
    3) Your Need can be only met through APO
    Regards
    Madhu

  • How to change operation dates in Production Order /Capacity Leveling

    Dear Experts ,
    We are using ECC 5.0 .In production order , scheduling happing as Backward  based on the Sales Order Delivery Date .I am doing the following :
    1.Demand as Sales Order with Delievery date : 20.03.2010
    2.Running MRP with Lead Time Scheduling -2  in md02 and converting the Planned Order to Production Order .
    4.Production Order have following dates :
             Basic Finsish Date : 21.03.2010
             Basic Start : the day Pl.Or--Pr.Ord
             Schedule Start : 15.03.2010
             Schedule Finsish : 17.03.2010
            Schedule Release : 13.03.2010
    5.In schedueling margin key :  Float Before Production : 3    , FAP : 3 , Release Period : 2
    6.In material master : Work Scheduling View : Setup : 3 days , Processing : 4 ,Interoperation : 2 for one Base Qty 1
    7.In operation : Op1  : Start Date  : 15.03.2010    Finish Date: 15.03.2010
                             Op2 : Start Date : 16.03.2010      Finish Date : 17.03.2010
                             Op2 : Start Date : 17.03.2010      FD : 17.03.2010
    Question :
    1.How to change the Operation dates  in Production Order Operation over view screen ? Today,  operation over view screen , Start date and Finsih Date  of individual operation are not changable with in Production Basic Start /BF date  or beyond .It is only changing based on the Standard Value : Labor
    2.How to change/re-schedule operation dates d in CM21 (Graphical view -Work Center Capacity load as per   Production Order and Operation combination ) based on capacity availale in advance dates? I am using  Time Profile : SAPSFCZ002 -SFC Graph midterm-3 motnhs and Planning  ,
    How to solve this above issue in scheduling operation and capacity distribution .
    Regards
    JH

    Closing the thread

  • Function module to calculate capacity requirements of production order

    HI
    Hav a requirement to calculate capacity requirement  for production orders like we see in cm50... does anyone know a function module to calculate capacity requirement?

    Hi All,
    Just to reopen this issue, even I am looking for a similar functionality.
    To reinstate the requirement:
    I want to find shifts and corresponding capacities for a work center. These details are obtained from CR03 and CR13 transaction.
    If possible do let me know Function module or tables for the same.
    Debs

  • Capacity problem in production order

    Hi Friends
    I am facing a serious problem in capacity evaluation. After MRP run with scedulling as 2. After this I am able to see the capacity in respective work centers for the planned orders. But when converted to production order I am not able to see. When I checked the order it is showing as "Order 60003310 has no requirements in the eval.period, so there is no display".
    I dont have any clue as whats happening since the capacity is there till it is a planned order. Any suggestion?
    Thanks & regds

    Hi,
    Your problem is with Evaluation period as system not displaying the capacity so first check whther is nay capacity requirement is there in this period you can check with CM01 also.
    In OPD2.
    Assuming you want to create a time profile for 2 months.
                                            Entry Type    Start Date     End Date
    Database Read Period            J                -3                   3
    The database read period specifies the period in which capacity requirements are read  from the database. All requirements are accessed which are partially or completely 
    within the database read period.
    Evaluation Period          G              -1           60
    The evaluation period specifies the period over which data is formatted and displayed. 
    The evaluation period must lie within the database read period.
    Planning Period            G              -1           60
    The planning period defines the period in which the SAP system can carry out planning. 
    The planning period is smaller than or equal to the evaluation period. You cannot move  operations outside the planning period. Equally, when automatic finite scheduling is 
    carried out for an operation the system only searches for a new date .
    Please check and come back.
    Regards,
    R.Brahmankar

  • Capacity check during Planned order to production order conversion

    Hello Gurus,
    I have a strange situation during capacity check.
    While Converting the planned order to Production order, I release the order and I don't get any warning. All work centers are available
    But for the same material/quantity/dates, if I create the Production order manually, release it, system check the capacity and I got the message the Capacity Over loaded (which is correct also as there are overload on the work centers).
    My question is why I am not getting this message while converting the planned order to production order.
    There are overload on the work centers and manual creation of Production order is working fine, but problem is during planned order to production order conversion.
    For information, I have maintained Finite scheduling indicator in OPKP, capacity availability indicator "NO CHECK" is also blank in OPJK.
    It will be grateful if you can please help me here.
    Thanks in advance,
    Sandeep Kumar

    Hi KK,
    Thanks for your feedback.
    I have checked all these settings but still no success.
    I am surprised but it is not a customizing issue I believe, because capacity is checked in Dev client while converting planned order to production order. I am facing this issue only in Staging client.
    Master Data is same. In CM01, in Quality(Staging) client, it is showing overload. while creating production order, it shows overload but only when convert from planned order to production order, it does not show overload .
    Please suggest what else I need to check.
    thanks in advance.
    Br,
    Sandeep Kumar

  • Putting a production order on hold, removing capacity requirement

    Hi,
    I have a need to temporarily remove capacity requirements from production order because there is situation on the shop floor that caused the particular order unable to move ahead.
    Capacity requirement shall be re-instated when the order specific production issue is cleared.
    Is there a way to update a production order to release capacity requirement yet allowing changes to production order routing? I tried "LOCK" production orders but that will not allow me to change anything in the order.
    Can I set up a user status + user exit to remove the capacity requirement? If so, how to?
    Thanks all in advance!!!
    Regards.

    Hi
    Capacity requirement can be deleted when the following functions are carried out.
    1.The production order is set to Technically Complete.
    2. The deletion flag is set for the production order
    3.The production order is locked
    4.The indicator capacity  requirement in the procdution order is reset  and order is rescheduled
    5.The capacity requirement is reset with fucntions -----Availability check---reset cap stock
    Regards,
    Sadan

  • Capacity Requirement From Released Production Order

    Hi PP Gurus,
    Can i limit capacity requirement only from released production order ? I don't want to count requirement from production order that just created but not yet release.
    Regards,
    Arman Lie

    Dear Arman,
    As a standard practice the system creates the capacityrequirements once the production order is created.
    Check this,
    When a production order is created the following actions are carried out:
    ·        A routing is selected, its operations and sequences are transferred to the order
    ·        The bill of materials is exploded and the items in the bill of material are transferred to the order
    ·        Reservations are generated for bill of material items held in stock
    ·        The planned costs for the order are generated
    ·        The capacity requirements are generated for the work centers
    ·        Purchase requisitions are generated for non-stock items and externally-processed operations
    Regards
    Mangalraj.S

  • Auto Material & Capacity Availability check when releasing Production Order

    Dear Experts,
    Is there any configuration in Production Planning that will automatically check material availability and capacity availability automatically when a Production Order is released?
    Meaning to say, users will not need to manually click on the Check Material Availability and Check Capacity Availability button.
    Please advise.
    Thanks in advance.

    Hi,
    I've solved the problem. Just maintain the config in transaction OPJK.
    Thanks

  • Capacity for only Production orders only.

    Hi
    I am checking capacity loads in CM01.
    In this t-code its considering my Planned orers also.
    I want to capacity load for production orders only.
    we dont want during planned orders stage.
    where can i check.. what are the settings i have to do for checking capacity for only production orders.
    Regards,
    srihari.M

    Srihari,
    This is a standard requirement.
    Planned orders in a non-repetitive environment typically are not dispatched nor confirmed.  They do not, therefore, become part of the 'Basic Load'.  The capacity requirements of planned orders are there mostly so you can view the capacity requirements in sum with the production order capacity requirements (CM01 and similar).  They do not 'consume' from total available capacity.  When performing a capacity check of a production order, it will not 'see' the capacity requirements of the undispatched planned orders.
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/60/13e30b133a11d3bf550000e83235ee/frameset.htm
    Best Regards,
    DB49

  • Machines with different Capacities in a production order

    i am have the  Machines of Different Capacities( Ex Machine A :2pcs/hr &  Machine B:4 Pcs Hr).
    i have Maintained the Work centers as Same Name.
    In actaual Production i want to use both the Machines.
    How to maintain in the  Routing .This is only one Operation and i want to use both the Machine.
    Ex :Prod Order Qty :100
    I want to use Machine A to manufacture the 60 Qty and use the Machine B for 40 Qty.
    Please give me the Solution

    Dear laks,
    I think this will help.  If you have maintained individual capacity as 2 for eg, for machine oriented capacity category then pl maintain the individual capacity details for  those 2 nos. You can give the individual capacities what ever name u like for eg Punch press 10ton, Punch Press 20 ton etc. 
    Note: you can access the individual capacities in the menu bar "goto - Individual capacities" of the relevant capacity category.
    Once you have maintained this, you can assign these individual capacities  in your production order.  You have to enter into the production order operations, double clik on the operation number which has got this WC, then enter into Cap. req assignement tab.  There u can enter the individual capacities detail and assign the quantities for the individual capacities as well.  Also, the capacites will be split and despatched as well.
    During the confirmation process, in CO11n, you have to mention the split number as well other than your confirmation / order number.  The system will validate this quantities with the production order capacities split qty.
    Regarding parallel routing, i think this will only work if you have two different work centers. 
    If the scenarios  is always like this, i think it would be preferable to create two diff work centres and like the other members of the forum have suggested, a parallel routing would be ideal.
    reg
    kiki
    Award points if this info is useful and solves ur problem