We have an issue while creating an shipment cost document for the shipments created with respect to Project/Networks.
Scenario: Our client has various project site where construction is going on and material is being sent to these site. A outbound delivery (delivery type LP) is created with respect to Project/Networks and send it out via third party carriers. A shipment document is created for these deliveries in order to fetch the shipment cost.
I am using account assignment category as "P = Project" in Item category assigned to Shipment Cost Type I am using and Account Modifier has been taken as VBR. My G/L account is deteremined fine but Cost Object (WBS element) beside G/L is coming blank in account assignement field in Shipment cost document.
Please suggest what I am missing here in configuration from Transportation or Financial side.
Thanks,

>
Rana Debgupta wrote:
> Dear All,
>        I have configured shipment cost through VI01 successfully and it is showing net value.But,when I am clicking "Freight Cost Estimate' button in shipment document through VT01N,it showing Net Value "0.00".so,Why Net Value is showing "0.00" although I have maintained it in VI01.Can anybody tell me the solution...??                                                                                with regards,
>                                                                                RANA
I am a bit confused with this, VT01N is first, then you do VI01.
in VI01 you create a shipment cost document to a shipment which must exist.
when you execute VT01N, then you create a new shipment.

Similar Messages

  • Shipment Cost Calculation

    Dear All,
    I know that tariffzone plays a role in determining the price for the freight/Service Agent condition in case of outbound shipment cost calculation
    I have the following query in Shipment Pricing.
    Can anyone please explain whats the role of the 2 postal code columns in the tariff zone assignment?
    Also how & where I have to maintain the data for determining the tariff zone which I have assigned to the above combination.
    Please help.
    Regards,

    HI Dave,
    Thanks for the response.
    Please note that I have maintained postal codes in my Shipping point also in my customer master.
    For the combination of TP Point, Service agent, Shipping type & Country I have made the following assignment.
    I have given my shipping point Postal code in both the Postal code columns of Tarff zone assignment (say Tariff) & my customer master Postal code in both the Postal code columns of Tariff zone assignment (say Tariff1).
    Now I have maintained the condition records in TK11 for the combination of Depart. Tariff zone/Destn.Tariff zone/Service Agent i.e. Tariff/Tariff1/Service Agent
    But my condition record value is not getting determined & when I simulate my shipment cost I am getting the following error message.
    Shipment costs not yet calculated
    Shipment costs item 000001 w/ ref. to doc. $0001 item 0001
       Message no. VY104
    Goods types directory could not be determined
        Message no. VW803
    Please help to reolve this issue.
    Regards,

  • Required BAPI for Shipment Cost Document (VI01)

    Dear All,
       I required BAPI for Shipment Cost Document (VI01), pls help on this.
    Regards
    Ranjit

    Dear MM
      Thanx for replying, but the BAPI which you have provided will only show me the Cost with correct Tax calculation,
    But its not getting created, which system should show the Shipment Cost Document number.
    Regards
    Ranjit

  • Step by Step configuration for Shipment cost Calculation

    Hi Gurus,
    Does anybody have the step by step configuration guide for Shipping, Transportation & Shipment Cost Calculation. I am new to this functionality. My email id [email protected]
    Thanks in advance
    Regards
    Mahendra

    Hi MAhendra,
    Create Delivery:
    T.code: Vl01n
    Create TO:
    T.code: LT03
    Create  Shipment Document
    Use
    After the status of the delivery is open for transportation planning, it is possible to create a shipment document to schedule the transportation.
    Logistics  Logistic Execution  Transportation Transportation Planning  Create  Single document
    T.code: VT01n
    Enter your transportation planning point and shipment type. Press enter.
    Creating the shipment cost document
    Use
    After the deliveries are scheduled by shipment and the shipment is executed, now it is time to maintain and close the shipment document in order to record all relative information and ready for the shipment cost settlement.
    Logistics  Logistic Execution  Transportation Shipment cost  Create  Single document
    T.code: VI01.
    After creation of shipment cost doc. You settle the Shipment cost.
    Go to VI02, enter shipment cost no.and press enter.
    Then go to Overview -- Fright cost items, Select hte line item and double click it.
    Go as main menu: Itme --> Acc. assignment, You enter G/L acc. and cost center to which the transportation cost will be posted.
    On the Standard change, details – Freight cost items screen, then check the check box “Transfer”, which means you will transfer the relative transportation cost to FI/CO, in this case, the system should determined which Purchase Order will used to settle the cost, so after you check the “Transfer” check box.
    Press save button on the current screen.
    Shipment cost settlement and documents:
    Use
    After the shipment cost settled in shipment cost document, it has the following affects:
    It creates a service entry sheet that refers to the purchase order determined.
    It posts acceptance of services performed.
    It creates an accounting document for the accruals.
    Further subsequent documents are created in FI.
    Reward points if it helpful
    Regards
    Govind.

  • Hi whenever I trfr  shipment cost in VI01 to FI system is directly posting

    Hi
    Expertese
    whenever I trfr  shipment cost in VI01 to FI, system is directly creating a PO and a service entry sheet
    and is there any control for service entry sheet through release strategy with the relation of shipment cost please let me know
    Thanks
    SRI

    Hi,
    If you want achieve this through Rel.Strategy then Just check following structure.
    CESSR through SE11.
    Regards

  • Shipment cost calculation  - configuration problem

    hello all
    we are implementing the shipment cost calculation system and so far configured only 1 service agent  .
    the problem regarding scenarios that the shipment executed by service agents that is not configured in
    the system but the invoicing party is the one ( SA) that we configured .
    ( the SA that is configured in the system is charging us for the shipments of the
       SA that is not configured. )
    how can i get the shipment cost document to open for the invoicing party ( the one that we configured )
    but still leave the shipment under the origin service agent ( the one that isn't configured )  ?
    Regards ,
    ASA .

    Hi ,
    sorry,  i wasn't precise :
    i need to open a service entry whose based on po in order to forward to financial accounting .
    ( its a separate po that isn't part of the inbound or outbound process and i open it for  SA x  )
    Y and X are differnt transportation companys but i have some cases that SA x is charging me
    for the shipment of SA y.
    the transportaion agent in VT01N is SA y and there for the shipment cost document opens for SA y and
    looks for po for SA y .
    i have to direct the system (  by some user exit / badi  ) to seek for the po of SA x ( the one whose
    charging me for the shipment ) .
    hope this help explain my problem ,
    Regards ,
    ASA
    Edited by: ASA MOKED on Apr 12, 2009 5:47 AM

  • Shipment cost Trx Vi01

    Hy,
    in shipping cost calculation, transaction vi01, there is the feature to create a purchase order. I try to create the purchase order from Vi01 but I get an error that the system  require purchase order type.
    Can you tell me where to fix the purchase order type for transaction VI01 to create the purchase order.
    Thank.
    Bye.
    Edited by: Josy wells on Sep 11, 2010 8:18 PM

    Hi Josy,
    It is in shipment cost configuration. SPROLOGISTICS EXECUTIONSHIPMENT COSTS--
    You have to explore here in settlement area. As I am not in the system, I am not able to give you the correct path. But the solution lies somewhere here in the settlement area only.

  • Error in Shipment cost Transfer in VI02

    Hi,
    When i am selecting the transfer tick in my VI02 in procurement is shows the PO is assigned but when i am saving it its giving be the leg.
    When i am checking the leg it gives the following message
    Forward shipment cost is incorrect
    General error in acceptance posting
    Can anybody help to solve the issue.
    Manish

    Hi Sachin,
    I am also facing similar kind of issue as Manish is facing.
    Issue is : while clicking on Transfer button & saving. System throws a message "
    While saving the shipment cost using vi02 , message"Forward shipment cost Incorrect-No service items selected" is coming.
    In my Case status is as follows:
    Shipment Cost Fully Calculated - C
    Account assignment fully completed - C
    Forwarding status Fully Transferred - A
    Please suggest.
    Kamal Batra

  • Shipment cost calculation based on HU's allowed packaging weight

    Hi all,
    I need to calculate a shipment cost based on the Means of Transport's Allowed Packaging Weight (MARA-ERGEW). After condition record determination of cost per ton in each case, the system must multiply this value times the allowed packaging weight.
    I know that through customizing I can create a Condition Type with Calculation Base = 'C' (Handling Unit) and Calculation Type = 'D' or 'E' (Gross or Net Weight). This is almost what I need except for the Calculation Type, because Allowed Packaging Weight is not an option in the field's matchcode (Percentage, Fixed Amount, Quantity, Gross Weight, Net Weight, Volume, etc...).
    Is there any way through customizing I can achieve this? Or how can I program a routine in the Pricing Procedure for the Condition Type in order to make the calculation based on the HU's Allowed Packaging Weight.
    I appreciate your help!!

    Freight carriers charges weight on the basis of Weight / volume of the items.SAP shipment works on the same principle.
    Cost of transporting ton of Potataoes  is same as transporting 10 ton of aluminium between two known destinations.
    Hence it is illogical to distributes cost on the basis of item value. However if still you want to distribute the same on value basis then maintain freight condition(%) in PO as per your prefined logic of distribution of freight cost.
    It is well known fact that cost of freight % is always higher in  Low value items & iis low in case of High value items.
    Regards,
    Sanjay Kohli

  • Error in Shipment Cost document(Delivery date is in past)

    Dear All,
    While iam trying to save the shipment cost document, i am getting error like Delivery Date is in past. Due to this error iam unable to generate the P.O in back ground. We are creating the shipment Cost for the S.T.O process.
      I want to know system is considering which delivery date in shipment cost.
    Regards
    Sunil

    Hi
    Can you provide few details like.....
    what are all preceeding steps you completed before shipment cost Processing
    whether you restricted only backward scheduling?
    Generally backward scheduling checks whether the delivery date  is in past or not?
    Thanks & Regards
    Bhaskar

  • Report for Shipment cost calculation based on Delviery Line items

    Hi,
    What would be the Standard SAP report where I can find the shipment cost based on Delivery line item. Currently there is a report ME2S that gives the cost based on PO. But I want to find a report based on outbound delivery line item.
    Regards
    Gaurav

    I hope VI11 should help you

  • Automatically Shipment cost calculation by the system

    Dear Gurus,
                       My client has a requirement that there are three route and three forwarding agent (Vendor),Suppose routes are 100,150&200 km respectively and 12,15,18 are the transporter (Vendor).transporter 12 is charging Rs.400 including loading,unloading & freight charge of materials from supplying zone to receiving zone (customer) , 15 is charging Rs 600 & 18 is charging Rs 800 for same respectively. so how system will automatically pick which one will be convenient for customer from both aspects route & shipment cost.anybody suggest me the configuration.
      Regards
      Jibanjyoti

    To achieve this, you need to have a combination of Route and Transport Vendor which should be configured in T_07.  Meanwhile, you would already be having an existing condition type for freight.  Assign the above sequence in T_06
    Now in TK11, maintain the required charges
    thanks
    G. Lakshmipathi

  • Error during Overhead cost calculation (Tcode :KGI2) for Production Order

    Dear Gurus,
    I am facing problem while calculation of Actual overhaed for production orer through tcode KGI2.
    Error Desctiption
    No account is specified in item 0000000001
    Message no. F5670
    Diagnosis
    No account was specified for account type "S" in item "0000000001" of the FI/CO document.
    System Response
    The Financial Accounting program cannot process the document.
    Procedure
    A system error has probably occurred in the application you called up. Check the data transferred to item "0000000001" of the FI/CO document
    I am not able to understand where I mistaken.
    Pls suggest
    Regards,
    Rupesh

    Hi,
    You should check postings to production order vis-a-vis your configurations for overhead calculation to find out what is wrong.
    Thanks and regards,
    Sanjay

  • Replicate breakdown cost from the Shipment cost document (VI01) to the PO

    CASE:
    Currently we are creating the SCD with reference to the shipment number. This SCD creates a Service purchase order and a Service Entry sheet automatically.
    The SCD has several conditions types to store different types of costs: Freight, fuel, accessorial, package, etc.
    The purchase order has only one value, instead the several values in the SCD. We want to replicate all condition types from the SCD  to the PO.
    Example:
    SCD condition types:
    Freight           $80
    Fuel           $15
    Accessorial     $5
    Total          $100 USD
    Automatic service PO conditions
    Price(Limit)          $100
    We want to have the same breakdown cost in both documents. Do you know how to do this?
    CD

    No possible.
    OSS note 427944

  • Automatic picked up purchase order during shipment cost cal

    Hi,
    We have one issue system picked up automatically Purchase order which having account assignment category "U".We have config new account assignment category "I" for some specific reason.Now we want that during shipment cost calculation (VI01) system automatically picked up purchase order with having account assignment category "I" intead of u.
    Please guide.
    Regards'
    Kumar

    Dear Arif,
    Please check the shipment document is there any error log exists
    Check the shipment cost having the value and Transporter(Vendor) and it is getting transfer to FI.
    After checking the transfer chek sytem will create the PO while saving the shipment cost document.
    I hope it will help you,
    Regards,
    Murali.

Maybe you are looking for

  • Updated to Lion and now iTunes and Apple TV 2 no longer work

    I "upgraded" to Lion today and now iTunes won't work and neither will my Apple TV 2. I click on media in iTunes and nothing happens. More than that, though, there's something strange going on with the metadata because movie posters are vanishing and

  • IDOCs - Simple doubt in INBOUND DELVRY. IDOC-DELVRY03, Process code isDELV?

    Hello Experts, Our SAP system receives the Inbound IDOC for Delivery from Gentran. Further details are, Process code: DELV IDOC type: DELVRY03 Message type: SHPCON Message code: TOC Parther profile: Account # of Ship To party So, my requirement is th

  • Using Google Earth in Premiere Pro

    I am trying to make a video for a competition using premiere pro and i want to put google earth in it. how do i do that?

  • RE: Modifying a Saved Query

    Hi there I have saved a query and now I would like to make some changes to it. How can I have the "guts" on the query be shown as it was when it was being created using the Query Wizard. I do not understand all the query lingo, but I find when I used

  • Database contention report

    hello i'm running on my database 10g r2 with autotuning a database contention report with the following result CLASS TOTAL_WAITS TOTAL_TIME free list 0 0 extent map 0 0 system undo block 0 0 sort block 0 0 segment header 1 0 bitmap index block 0 0 un