CO46 for sales order no exploded view for specific material

Dear All,
When using CO46 for a sales order it does everything correct exept for a specific material. It is displayed above the sales order in the hierarchy, like if it is not contained in it and there is no exploded view possible.
When I look closer to the MRP for the material it has planned orders but the orders reducing quantity don't link to the sales order. The MRP element data is empty.
Anybody has a clue?
Thanks in advance,
Michaë

The material in the SOI created collective requirements. Change Material Master availability check to 02 and recreate SOI

Similar Messages

  • When sales order is created ,costing of a material cann't be created automa

    dear suppporter:
      when sales order is created ,costing of a material cann't be created automatically.if i cost the material in va02 ,the cost can be generated.please help me analyse it .
    best regards.

    There is Tick in Delivery block 01 Deliveries: Blocking Reasons/Criteria
    I have observed in testing Before you save a sales order, you look at the schedule line overview, you can see what the system would Proposed confirm date and confirmed qty, if the block were  not set. However, as soon as you save the sales order,(warring message Oldest open items over due will appear) the confirmed quantities are automatically reset to zero because sales order is Blocked. Here the goods remain available for other customers.
    Note : When you release the sales order the automatically in sales order confirmed qty and proposed date will come.
    Here the problem is  when they do MRP run after sales order saved with block Planned order is creating.

  • Sales order error - Only 0 EA of material 24 is available

    Hi friends,
    I got this message during sales order creation 'Only 0 EA of material 24 is available'.
    I checked for solutions for similar problem in this forum by search button. Could get hold of two unanswered question. I tried possibilities listed there but problem still persists.
    Any solutions to resolve this
    Thanks

    Dear Robert
    The reasons could be
    - non availability of stock of the material for which you are trying to create sale order
    - Already delivery is created and saved without doing PGI for the same material
    If the reason is first cited above, then you can create stock via MB1C with movement type 561.  If the reason is second cited above, then run VL21 where you can see if any delivery is created and saved without doing PGI.
    thanks
    G. Lakshmipathi

  • Run mrp for specific material

    i want to run mrp for specific material (not for all the plant materials) in background in scheduled intervals............what can i do?

    Dear,
    You need to go for enhancement M61X0001 with function al modules EXIT_SAPLM61C_001 and EXIT_SAPMM61X_001
    Please refer my reply from this link,
    [MRP run for Specific Material|Re: Excluding materials from mrp run]
    Regards,
    R.Brahmankar

  • Quality Deactivation for Specific Material

    Dear Gurus
    Is there any procedure to deactivate quality for specific material other than Material Master (MM02)
    Thanks & Regards
    Shoib

    Dear
    Go to QA08 and Select the deactivate the Inspection For particular Material and Before that Select Which Inspection Type u want to deactivate
    with regards
    pushpalas

  • How to make Delivery block at Sales Order Header level for specific materia

    Hi,
    My client want to create a delivery block EDI order at the Order Header level for specific materials
    How can we achieve this.

    Dear Varada rajan
    Go to material master, select "Sales: sales org.1" view and assign "01" against the field "DChain-spec. status" and save.  By assigning, for a particular sales area, you can block that material.
    Now go to OVSU select 01 and assign "B" against the field "Block delivery".
    Now create a sale order and post the outcome.
    thanks
    G. Lakshmipathi

  • Need actual production order operation details for specific material list.

    Hi all.
    I am looking to generate a report containing all of the FSTD and MSTD activity for a material list that I will prescribe, as well as within a specific date range that I will provide. Is there a T-Code to generate this report? Thank you in advance. -Steve

    Hi,
    Explore the standard report COOIS..
    Thanks
    Kumar

  • Sales order line item check based on material status

    Hi
    I have the following requirement
    There are Distribution chain specific material status maintained in the material master ( Sales Org1 View). Now for some of these statuses we need to reject these items in the sales order @ line item level. A reason for rejection needs to be assigned for these line items.
    Is there any standard setting or a user exit is required. I believe user exit save_document_prepare could be used to carry out these checks & assign a reason for rejection. Pls suggest asap
    Thanks
    Ramesh

    Dear Ankit,
    The difference between reason for rejection and delivery block is,
    Reason for rejection you can find this field at header level and line item level, the use of this is once you mention any reason for rejection the TOR or Schedule line not been confirmed for that material,so that the material can be confirmed to another customer.
    If you set delivery block the material for sale order in case if the material not available it will rise TOR or if available it will confirm the schedule line and block the material for that customer or sale order.
    This is the major difference between two.
    Regards
    Ram

  • Procurement tab in Sales order displays two line items per material

    Folks
    I am not a SD guy and i have a very basic question on how to read the details in the procurement tab for a sals order.
    In the Procurement tab of a Sales order, two line items per material are displayed as shown below. whats does this mean ?
    Further, I had observed the below differences in the below 2 lines
    1. Mat. Avail Date is 06/19/2007 for line 1 & 06/20/2007 in line 2.why r the dates different ?whats the significance?
    2. Confirmed qty is 0 line 1 & 1in line 2.( when does confirmation trigger or update ? Is it upon ATP check or upon delivery ?)
    3. Order qty is 1 line 1 & 0 in line 2.
    Item     Material     Plant     Confirmed Qty     SU     Mat. Avial Date     SL     Req. Type          Deliv. Date     ATP Qty     Loading dt     Route     Part. Deliv/ Item     Deliv priority     Desc                              
    10     NTE801NC     2400     0     EA     6/15/2007     CT          D     6/19/2007     0     6/15/2007     24GB03     C     98     Priority 98 (Normal)                              
                                    1     EA     6/15/2007     CT          D     6/20/2007                   6/15/2007                    Priority 98 (Normal)                              
    Thanks

    It means  2 schedule line for that materials ,
    06/19/2007  is the date on which material is requested by  customer  but there is not sufficient stock on that day so 0 quantity is confirmed for that day.
    On 06/20/2007 material is availabe and you can start delivery to customer on 06/20/2007 and system confirms the material for 20th and it is reserved for this sales order.
    Confirmation is based on your MAT ( Material availability date ), but you can revist these dates through by triggering availabilty check or Back order processing through GATP or ATP.
    Manish

  • Designing the consolidated and line item report for specific material

    Hi
    i have a R/3-report and it run only for 7-materials.That means we need to only those 7-materials in the selection screen of report.
    Then we will get each material corresponding line item details(material no, profit center, variable cost, quanity, price, financial loss(this is calculated based on quantity) , Utility Consumption(calculated based on price, variablecost)  ) in one report.
    Another report will give same for consolidated values of financial loss, utiliy consumption.
    <b>so how can i design the consolidated and lineitem details report for each material.</b> pls let me know
    kumar

    0VENDOR_ATTR - Vendor Master Data Attributes
    0FI_AP_51 - Check Register Line Items
    0FI_AP_4 - Accounts Payable Line Items
    It should be noted, however, that this won't get you everything that you need, so you may have to create enhance one or more of these DataSources and create User Exit ABAP code to get the required data. Also, the 0FI_AP_51 DataSource isn't available if your source system isn't ECC6 EHP3 or higher. If your source system is less than that, you're going to have to create a generic DataSource for the data from the PAYR table.

  • V_V2 for specific material/report lists other materials

    When we run V_V2 selecting a material, the report generated shows many more materials rescheduled on sales orders than just the selected materials.  Is this a bug in the program?

    I have met this problem also!
    Please someone comment on that?

  • Approve suppliers only for specific material groups

    Dear Experts,
    Current scenario: Our purchasers can buy products from all material groups from every boarded supplier. E.g. they can buy production materials from an office paper supplier.
    Target scenario: The moment a purchaser buys a material that's not part of the approved material group of that specific supplier, he get's an error.
    What is a practical way to achieve this?
    Thanks a lot,
    Steffen

    Normally we maintain Source lists,  which restrict the list of vendors from whom certain materials can be purchased. 
    Sometimes you can also create a Material group level contract, and then in the PO  specify the materials from that specific material group.
    but ideally you should go for source list, as it is the simplest and standard way to control approved suppliers for materials.  I know its not at material group level , but still its the best option.
    Last case, you can go for a development  , use the BADI ME PO PROCESS CUST i think it is.

  • PO Qty in SKU configuration for specific Material Group in PO

    Dear All,
    I face issue when I do MIGO, which is that unit measure KG can not covert to stockunitstock unit measure PC.
    After I checking, I found the following information in tab Qualities/Weights of PO:
    PO Quantity                     2 PC     Order Unit <-> Ord. Price Unit        PC  <->         KG
    PO Qty in SKU               0.000        Order Unit <-> SKU             0      PC  <-> 0
    What I can configure is "Order Unit <-> Ord. Price Unit        PC  <->         KG", but I can not conifgure "Order Unit <-> SKU" for PO to buy material group rather than sepcific material.
    Could anybody can tell me how to configure "PO Qty in SKU               0.000        Order Unit <-> SKU             0      PC  <-> 0" for PO to buy material group in ME21N?
    I am looking forward to your kind suggestion, which is really appreciated!
    Cheers!

    Does anyone face the same issue before? could you give me any tips if you have such problem? thanks in advance!

  • FREE check box in PO should be selected by default for specific material

    Hi All,
    We have a check box  FREE in PO creation - ME21N in the item row  which is selected when ever we want the vendor to supply those items as free.
    - I have a list ot items which are supplied freely by the vendor which I have to mention in the PO. My requirment is when ever the specific material is in the PO the FREE check box should be selected by default. Is it possible?
    Please advice.
    Thanks ,
    Vengal Rao.

    Hi Vengal Rao,
    I don't think there's such flag in the material master. As far as I know any material can be supplied either free or chargeable - the buyer has to choose the applicable option it in each specific PO.
    If however in your business case certain materials shall always be supplied as free, then you can use the BAdI that I mentioned above to analyse which material is being procured and set the FREE flag in the PO accordingly.
    BR
    Raf

  • For LUMF - BOM, Plant field in Sales Order should be editable for TAP

    Dear Gurus,
    I have the following requirement.
    Requirement...
    TheComponent level BOM (LUMF) should be exploded in sales order with one by default plant when iI enter the main component in Sales order but if I want to change the plant of main item manually system should allow me in order change mode. And this changed plant to be determined automatically for all the components of that BOM.
    As we know if we maintain the BOM at component level we will use the Itm Catg Grp "LUMF" so the pricing will be determined on the component level.
    In CS01 we maintain the BOM for a main item. I have followed the same process in CS01 by entering Main Item material, Plant and BOM usage (5). whenever i enter the main item in sales order it explodes correctly with components, quantity and Plant.
    The Plant field for main item (TAP itm Catg) becomes gray. But now my query is that if I want to change the plant of main item system is not allowing me as I have  created BOM for a specific Plant. Same Bom I have maintained with other plants also
    I know that We have one more option in CS01 like we can create a BOM without entering Plant also. But before I doing it for trial and error I want to know whether it will work for my latest requirement.
    And what is the Group BOM ? how to use it? will it be helpful me in this requirement?
    Please help me for the issue, I need to configure it as soon as possible.
    regards,
    Vojas

    Dear Kapil,
    Thanks for your suggestion i followed it also but yet I am facing the same problem.
    I did as follows
    I extended the Main item and components to the different plants.
    And also created the same BOM for different plants in CS01.
    After doing this if I create a Sales order and enter the Main Item with quantity system asks me for the Plant to explore the BOM, as i enter a plant BOM get explodes and the plant for main item becomes gray which i dont want. Any how I want the this plant field for main item in editable mode.
    Let me explain my requirement in short
    I maintain the LUMF BOM (Pricing at component level) .
    once I enter the BOM material with quantity system should explode the bom with one plant by default. and in change mode of sales order the Plant for main item should be editable instead of gray mode. Becoz decision can be changed later on the delivering plant location.
    Please suggest me. Its a high priority issue for me.
    regards,
    Vojas

Maybe you are looking for

  • Can't open Canon Cr2 file in Photoshop CS6

    I purscahed PShop CS6 Upgrade a few days ago as an upgrade for the full CS4 Extended (which was upgraded to CS5 last year).  I installed CS6 as an upgrade to the installed and registered CS5.  Neither Bridge CS6 nor Photoshop CS6 will read Canon Cr2

  • How do you in an easy way number the pages in a book your´e doing in LR4?

    How do you in an easy way number the pages in a book your´e doing in LR4? In Blurb´s BookSmart it´s quite easy to do it autoamtically.

  • Passing variables inside a url to call a query

    Hello, I have created a BSP-application with a restful webservice to transform a BW-query (BI7) into a XML-File for further development with XCelsius. https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.highlightedcontent?documenturi

  • Third party patches for XP

    Hi, we have a big amount of XP machines. From April we suppose to receive XP patches from forest level IT. So I have no choice, but connect to upstream server. I don't like this idea because of loosing full control of my clean WSUS. My intention is t

  • Fields "Used " upon Leave Request show carry forward instead of al

    Dear all, Staff  have apply 1 days annual leave. However when the staff submit leave request via ess, fields "used" in leave request show carry forward leave insteqad of annual leave . The staff have carry forward but have fully utilize it before his