Coding mask problem

Hi All,
I am facing the problem in coding mask.
I have existing project coding  mask let say abcd :000/0/0/00 like this. here i am using project id of 4 char and remaing 20 for coding.
i will like to use project id as abc and remain 21char for coding but
system is not allowing me to create new error says abc already present.
then i tried with different char like xyz but still it is restricting me to use 20 digit only in coding mask
what is  problem ? how can we solve it
regards
shiv

Hi Martina,
I have one doubt.Suppose we configure Length of coding key= 1, define a coding mask A-0000 and create a operative project A-0001. Then sytem doesnot allow us to change the length as operative project exists. Now if we have had length 2 earlier (instead of 1) then system will allow us to change the length to 1,3,4 or 5. If we change the length to 3,4,5 we can go back to length 2/1 later. But if we change length to 1 then our existing project will get assigned to existing coding mask and system will not allow to change the length later on.
Does this mean that, though we have 1 to 5 options for coding key length, once we have selected a particular length and have coding mask of that particular length, create a operative project with that mask, then we cant change the length of coding key? In short we need to decide the length only for once, at the start of implementation and cant change it once we have operative projects. Or you know any method to go back to earlier key length in case opeartive projects exist?
Request you to please comment.
Regards

Similar Messages

  • Project coding mask problem

    Hi friends,
    My coding mask is: 00/XXXX.X.XX.XX.XX.XX.XX
    The First six characters are for the Project definition.
    First I created the Project definition, eg: 13/0000.
    Then I created the top level WBS element which will be the same as the Project definition, 13/0000.
    Then I created the 9 second level WBS elements (limit is 9 as per the coding mask) eg: 13/0000.1, 13/0000.2 and upto 13/0000.9
    Then I want to create some 20 WBS elements under the first WBS element (13/0000.1). At this time the system is allowing me to create the first 9 WBS elements, i.e, 13/0000.1.1, 13/0000.1.2 and so on upto 13/0000.1.9. According to the coding mask the system should allow me to create upto 99 WBS elements at this level. But this is not happening. I am surprised. I want to know why this is happening. Please help me out.
    regards
    Pratap

    Sorry for the delay in reply. There was some problem in SDN website here as a result of which I was not able to post my reply.
    In the meanwhile I found out the reason for this problem.
    My coding mask was 11/XXXX.X.XX.XX.XX.XX.XX
    Since it is 'X', the project creation was not being allowed to create more than 9 WBS elements.
    I then tried changing to 11/XXXX.0.00.00.00.00.00
    Now it is working fine.
    Thanks for your support guys.
    But I have one more doubt now.
    I have the old Coding (11/XXXX.X.XX.XX.XX.XX.XX) in my quality server. How do I make changes and transport it now? I may face problem since I have already created projects in the quality server with the old coding mask. Please sugget.
    regards
    Pratap

  • How to add new coding mask into productional system

    Hi,
    A new division is entering our system and has a business requirement for a project coding mask C-00000.00.00.00.00 to handle capital investment projects. We would like this proces to make the good example for rolling out project models to the rest of the organisation (and for making new coding masks in the future)
    However, we are facing a problem. Until now only the IT department has been using the project system and they have not had the need for mulitlevel projects or project models.
    IT projects today is entered as free texts like:
    Definition ITINTCOM001-S1003
    WBS       ITINTCOM001-S1003
    with no regard to the coding. Logistics integration is used via networks and MM-SRV.
    I have read in another issue in the forum that I was supposed to be able to enter additional coding masks as long as they did not interfear with existing coding masks. So I tried to transport a new coding mask into the system but it created an error message CJ 610 "Entry length is incorrect B-00000.00.00.00" with a reference to the coding (there are no existing projects using B- or any other coding mask). It also made a system dump when a wbs was searched via F4.
    So I removed the coding again and the system went back to normal.
    Since go-live is closing in I would be highly appreciative if  anybody had a suggestion on how to solve this issue?
    BR
    Allan Albrecht

    In the Node SPRO (T code OPSK) ie., Define Special Characters for Projects, mention '1' in PL field- Length of key for coding (as in your case the key is 'B') and don't check the check box SL. Also don't check the check box 'Edit'.
    For reasons, refer the F1 help on these fields.
    Save this and new coding mask in same request and transport it. Try this and let me us know if it solves the problem.
    You can also refer to note 520944
    Regards
    Sreenivas

  • Auto project creation and coding mask

    hi to all,
    i dont understand how system determines name of project definition during automatic project creation based on sales order.
    if the standard project definition does not have a coding mask then the project created is simply the sales order number. (no problem with that)
    however if the standard project definition has a coding mask, then in my case the newly created project just contains a certain number of 000000 and includes the last part of the standard project.
    hope someone could enlighten me on this..

    Hi,
    This scenario is very well explained in PS under title "Assembly processing".
    An assemble to order environment is one in which the product or service is assembled on receipt of the sales order. Key components are planned in anticipation of the sales order. Receipt of the order initiates assembly of the customized product. This business process is called assembly processing. It creates a link between sales document and project. It is an indirect method of generating a network or a WBS from a sales order. It is used throughout SAP R/3 logistics applications to automatically generate the order types like Planned order, Production order, Process order, Service order, Network (project).
    You will find the "SD/PS assignment" indicator in the control data for the project definition of the standard project. This indicator determines whether, during assembly processing, a hierarchy is created in the operative WBS for each sales document item, or whether a hierarchy is created for the entire
    sales document in the operative WBS.
    If we use SD/PS assignment indicator, do not flag "Only one Root" option in the project profile ( t code OPSA).
    Regards
    Tushar

  • Error in Project Coding Mask "Edit screen is "1" too long" Message no. CJ62

    Hi Friend's
    In sandbox already i have Define Special Characters for Projects is as "2"  (Length of key for coding)
    Now when i go for defining Project Coding Mask by making following new entry in the spro
    example "PR     .0000000000.00.00.00.00     Dairy Process Project
    after entering above details system gives following error
    Edit screen is "1" too long
    Message no. CJ627
    How i can resolve this issue.
    Thanks & Regards,
    Sandeep

    Your coding mask is exceeding the limit of 24 characters(including special characters). Reduce some characters to make it 24 or less then 24.
    Edited by: Kuldeep Bidalia on Sep 9, 2010 4:42 PM
    Edited by: Kuldeep Bidalia on Sep 9, 2010 4:43 PM

  • How to create a validation for the project coding mask

    Hi,
    Would just like to ask how to create a validation for the project coding mask wherein the WBS elements hierarchy will be checked against the template saved. For example,
    project coding mask is XXXX-XXXXX-XX-X-X-X-00-X
    mother WBS should be XXXX-XXXXX-X and lower level WBS would be XXXX-XXXXX-XX.
    The validation should not allow a mother WBS to be XXXX-XXXXX-XX.
    How can we go about this?

    Hi Jacquiline Bersamin,
    You can use validation with the combination of the level and the coding mask.
    In the validation:
    Pre requisite: WBS level = 1
    Validation: Prps-posid = prps-posid :1-12:
    Message : Error
    If required you can give the parameters for your detail error message.
    Please let me know if this does not work.
    Thanks
    Regards
    Srinivasan Desingh

  • Project code mask problem

    Dear All,
    Presently we use project codes as " H.00.HXX.000.00.00.00.00 "
    Now we have created project upto series H.08.HXX.999.
    We are unable to create H.08.CXX.1000 or further.
    Now I tried to change the coding mask in the config by changing H.08.HXX.000 to H.08.HXX.0000 , but the system is not allowing the same.
    Please suggest me on this matter.
    Regards,
    Vishal

    Hi,
    Thanks for the reply.
    I think  what u have suggested is  right.
    But still I am  looking for possibility of the same.
    May be OSS note could of some help.
    Thanks again.
    Regards,
    Vishal

  • Can I create a Coding Mask without special characters?

    Good morning,
    Our client wants a project code with the following masks:
    XX0000-0000.
    Please advise how to proceed with it.
    Best regards,
    Nat

    Hi Nat,
    u cant have both numeric and alphanumeric in single word "XX0000". U can make the same as "XXXXXX"
    and there should be a specific project ID and Project ID and coding mask should be separated by a special character.
    u can make the coding mask as explained below
       Project ID     CODING MASK
    1)  A               :XX-0000-0000
    2) A               :XXXXXX-0000
    REGARDS
    Avinash

  • Project coding mask in PS

    Dear Sap gurus,
                          Can anyone explain what is project coding mask in project system.please very urgent
    Thanks&Regards
    p.srinivasan

    With the project coding you will going to idntify the project definition and WBS elements in SAP.
    In Customizing for "Project Number Coding Mask", you define the appearance of the coding masks.
    Also in Customizing for "Special Characters" table, you specify the special characters for WBSs, and you also specify the following for the project coding: whether coding must be used, how long the key should be, and whether this length is compulsory. Also a temporary placeholder for determining a project number automatically.
    So based on the organizational requirement you will identify how the project coding should look like.
    Say for Eg. for company code NLY0, I want start all the project naming should start with NLY0-XX-XXXX.
    you specify how a project number in customization for editing. You can maintain the following parameters for editing the project number:
    The length of the key for project coding 4
    and many special characters, specifying whether the key must have this exact length or whether it can also be shorter. Special characters to enter WBS elements faster. An indicator specifying whether only coded project numbers can be used to create projects....so on.
    Like that based on the organization requirement you can maintain you own project coding.
    If you satisfy with the answer, reward the points accordingly.
    regards,
    Harisha

  • Use of Project Coding Mask

    Hi,
    Could you please tell the usage of Project coding mask. Is it useful for creating for WBS elements with specific hierarchy or to search the WBS elements?

    It would be good practice to use coding mask to standardize the Project ID and helps in building WBS hierarchy.
    If the client is having different projects for example customer as well as capital projects then u can define coding mask such way that u can identify whether the project is customer or capital project. Later it helps in reporting if client wanted to analyze all the capital projects.
    But in SAP it is not mandatory.
    Hope this help.
    Venkat

  • Campaign Element generation using coding mask

    Hi Friends,
    Iam working on the automatic number generation for marketing/campaign plan generation. I have implemented the Note provided by SAP and everything is fine.
    The issue is with the campaign elements. I have used the coding mask to generate the campaign elements. Whenever i delete a campaign element and create a new one, the same number is used again. I mean the previously deleted campaign element numbers are generated again.
    Is there any standard way to create a new campaign element every time from the coding mask without re-using the deleted campaign elements.
    Thanks
    Raju

    Hello Narayan,
    Be more specific? Which version are you in? Is default badi activated? do you have any active custom implementation of  Badi CRM_MKTPL_OL_OBJ with code in method "external id generation".
    Are you using code masking along with the Badi activation. if you custom implementation of badi CRM_MKTPL_OL_OBJ, make sure you deactivate the default implementation.
    Some time this issue might be caused by conflict of multiple implementations active.
    Thanks & Regards
    Raja Pamireddy
    Moderator

  • Dedicated coding mask for standard template.

    Hi Experts
    I wish to maintain coding mask for: various varities of projects like:
    1) PP/00000-00-00-00
    2) PS/00000-00-00-00
    3) PA/00000-00-00-00
    To have the template functionality also in place, please suggest which of the following is best?
    1) The above coding masks are allowed for both operative and standard. It means, the number series contains mix of both std and operative projects.
    2) To have a dedicated coding mask ST/00000-00-00-00 which will be a common standard template for creating Operative projects using the above masks. I am still having doubt since i could not test this as the existing system coding masks not allowed for modication.
    I request the experts, to suggest a best practice in this regard.
    warm regards
    ramSiva

    The number series will not contain the mix of both operative and standard structures as you have mentioned in point 1. Please check.
    As for point 2, Kabir is right. Create a new mask for standard structures and lock it for operative projects.
    Regards,
    Ajinkya
    Edited by: Ajinkya Vaidya on Oct 30, 2009 6:08 AM

  • Coding Mask errors CJ610 and CJ627

    dear experts:
    i have 2 questions regarding Coding Mask:
    i have created the project coding mask: D-XXX-00.00.00.00.00.0
    in fact i tried to make it aliitle bit longer by ading extra 4 charecters 0.00 to be this way: D-XXX-00.00.00.00.00.00.00
    but the system didnt accept this and issued the error message no: CJ627 (Edit screen is "4" too long)

    Hi,
    You cannot create coding mask that is more than 24 characters long. Read SAP Help and find out more about this.
    Regards,
    Gokul

  • Coding mask error

    hello,
    I am using ECC 6
    I have configured the coding mask as follows
      :000/0/xxx/000/000
    my project id is 4 char long
    when i created the project with id abcd:001
    my first wbs element abcd:001/1
    my first wbs element under the first wbs element is : abcd:001/1/1
    my second wbs element is : abcd:001/1/2
    this way well right upto 9th wbs element abcd:001/1/1/9
    10th element is coded as %00000001
    can anybody pls explain why so? and what will be the solution
    hope i clarified query..
    Thanks
    shiv
    Message was edited by:
            shivshankar mule

    Dear Shiv
    The coding mask should be enough to cater ur requirement. But in your case coding mask is allowing only one digit in the first level of the WBS Element, i.e. u can create only nine coded WBS Elements in the first level. If u want more then change your code to something like "000/00/xxx".
    Regards
    Murali

  • Error in Coding mask

    Dear Experts,
                     I have a one issue in Coding mask.My mask is "PSXP-XXX-00-00-00-00-00",For this mask im going to create wbs elements like CJ20nproject Definationwbs overviewCreate Wbs element,for this im not getting any error.But Im going to create Cj20nproject DefinationRight click on project definationcreate wbs.. In this scnerio the wbs element is not picking up the running number [Example:When im going to create level 1 wbs element through overview screen it will pick up "PSXP-001-01" and working fine,When im going to create WBS element through right click it is picking up like this "PSXP-001-1"].May i know the reasons please..It will very helpful for me..
    By
    Suma

    Dear Pradeep,
                   Thanks for your quick response...
       But my question is Project defination>wbs overview>create Wbs.Here it will pickup automatically running number(means 01).As you said numaric system it will not consider the zeroes,I agree..But it should not take When im going to create WBS through Overview screen right..In my case it is taking  automatically running number automatically..
    Second,In your version we will not create not morethan 9 wbs elements in that level right,then what is the use of taking "00"?.
    If im wrong please correct me...
    Regards,
    Suma