COFC - Actual cost calculation error

Hi Friends,
I am a PP consultant and i have a issue with cost calculation at the time of confirmation.
There are production orders that were confirmed in year 2010 and year 2011. For year 2010 costing documents were created but not no costing docuemnts for confirmations in year 2011.
I checked tcode COFC and found error log as : A master record for 1111/ABCD exists only in 2010.(where 1111 is cost center and ABCD is activity type.)
I have checked the validaty of both cost center and activity type & both are valid.
can anyone please suggest what has to be maintained for year 2011 from controlling side.
Thanks In Advance.
Rohit

Hi Rohit,
The similar error i have faced  just couple of hours back.
I have checked up the plan prices in KP26 for the activity type and could see that they were not maintained for 2011.
I have maintained the same for the current year and the error got resolved.
Pls see that you are choosing the correct cost centre and activity type combination alongwith the costing version for 2011.
Regards
Sachin

Similar Messages

  • Errors arose during actual cost calculation

    Errors arose during actual cost calculation
    No prices could be determinedfor object activitytype company code xxxx , cost center XXXX, activity type XXXX
    Pls let me know immediately friends deperate,
    regards,
    sri

    Hi
    when you gone to the transaction code Kp26 Activity typ price/ planning after give the input press period screen or F6 function key and check what price was maintained for your period 12.
    And even you do one thing go to the transaction code KS02 or 03. Give the cost center and press enter . Then from the meny bar select Environment -> whereused list->.
    And let me confirm how you run the cost estimate for the material
    bye

  • Actual cost calculation process

    Hi, All!
    I run the Actual Cost Calculation Process and created IPV is effecting PMAC, but no lines are created in gmf_invoice_distributions.

    Hi,
    Check the unit price of the PO and the Price for the line during AP Invoice matching. If there is a difference then it automatically goes into IPV. Also check the values for profile GMF: Include Invoices in Actual Cost.
    Regards,
    Malcolm

  • CORUPROC is not doing "Actual-Cost Calculation" - still in CO1P.

    Hello friends,
    As per SAP documentation, and many SCN posts I went through - all of them said CORUPROC is the program to run as batch job, and CO1P is its equivalent online transaction.  In my quality system, I see CORUPROC is not doing the "Actual-Cost Calculation" - and even if I execute CORUPROC online (through SE38), it is not clearing them. (It is clearing the goods movement entries).  CO1P still shows all the order/operation awaiting actual cost calculations.  If I select them in CO1P, and click <save>, they are cleared.
    So can someone guide me how can I make CORUPROC to do the actual cost calculation please.
    Thanks,
    - Chetan

    Hi
    I would expect to have this record processed by report CORUPROC.
    It's quite easy to analyze this program in debug. Set a break-point on the line below:
    IF NOT g_costs IS INITIAL
    Now follow the program execution until function module CO_RB_POST_ACTUAL_COSTS is called. If the function module is called, check if it was executed correctly reading the value of variable SY-SUBRC.
    BR
    Caetano

  • Actual cost splitting error (Equivalence numbers)

    Hi
    I am facing an error during actual cost splitting (KSS2) . The situation is working fine in the case of Plan cost splitting (KSS4)
    I want to split costs in a cost centre based on equivalence numbers. But, i dont see any option of maintaining equivalence numbers for actual cost splititng. The option is available ONLY in KP26..
    Hence, I have maintained equi no.s only in KP26. This gives me error in KSS2 Quoting some divergence error. The message reads that activity price calculation did not converge
    It shows me a picture on screen which displays a loop between activity types. I am unable to understand it
    Can any one guide me on this??
    Any help wud be promptly rewarded
    Regards
    Ajay

    Hi Mahe,
      Here Kss4 Before cost centers are assigned Splliting Structure to cost center r not Plz check.Then Only it Work.Actuval cost Splliting is Working  Based On the Production Order Conformation and U r Fi entry Poistings Related to cost Planning.
    Best Regards
    Nagaraju Sami

  • Actual Cost Calculation in Process Order

    Hi All,
    I updated Standard cost of a raw material through a cost estimate and also ran cost estimate of the FIN that is using this raw material but when I am creating a Process order, it is taking the cost of this particular raw material from the previous estimate not the recent one to calculate the target cost. Can any body help me with this.
    Thanks
    MKR

    Hi Ashok,
    My Valuation variants for the Costing Variant of Cost Estimate and Production order (Actual/Plan) cost calculation are in Sync to get the prices according to the price indicator in material master. But when it calculates cost for a production order, it is picking up cost from the previous period for that particular raw material. I have updated the standard cost by running the cost estimate but still its not working.
    Any lead on this. This will be really appreciated.
    Thanks
    MKR

  • Actual Cost worker Error

    Hi all,
    When launching cost manager, Actual cost worker completed with warning message at a transaction_id and it erred out as below.
    CSTPACIN.COST_INV_TXN: (190): User-Defined Exception
    Pls help to sort out this issue..
    Thanks
    Dinesh

    Please see these docs.
    Cstpacin.Cost_inv_txn: (190): User-Defined Exception (Doc ID 1311958.1)
    How to resolve Costing Errors & Problems (Doc ID 865438.1)
    Thanks,
    Hussein

  • Actual cost calculation

    Dear All
    How can i find the actual cost in subcontrating cycle for my consumed materials
    Regards

    Hi,
    if you use the sub con cycle for your procurement ( external procurement) , the components costs will be taken from the material master for account postings,Hence normally the cost of that material multiplied by the qty will be your cost of consumption.The respective GL account data which has been posted out during the GR of the finshed product ( componets will be posted for consumption)  will give the neccessary info.
    If it is a internal procurement respective order will tell the story of costs.
    Regards,

  • CO11N:ERROR AROSE DURING ACTUAL COST CALCULATION DO YOU WANT TO SEE THE ERR

    Dear Colleagues,
    Users are getting this error on CO11N when trying to post a confirmation for certain materials/orders.I searched this error on a few forums and can not find a lot of info...could you please point me to the right direction as to how I need to start troubleshootig this?
    I checked OPK4 configuration and can't see anything regarding cost over there...
    All help is appreciated,
    PAPJ1

    Hi Vivek,thanks for your reply.I got the details of the error as this:
    A master record for 360_221/LABOUR exists only in 2011
    Message no. KL002
    Diagnosis
    You want to use cost center 360_221 together with activity type LABOUR. For this combination, however, only one master data record was created in fiscal year 2011. The master record is defined in CCA during activity type planning.
    Procedure
    1. Create the master data record.
    Activity type planning
    2. Or, check your entries.
    Is it the within the cost centre master data that i need to do anything?
    I checked KS02/03 but can't see any activity such as LABOUR?is this for my Finance department I take it?

  • Cost calculation error while saving the activity in network

    Hi Experts,
    We have created internal activty in the network at the time of saving it is giving an error.
    "Error while calcualting Cost,log is deleted when saving do you want to save?".
    When I checked the log through extraslogscost calculation in CJ20N,it is showing following reasons
    1) Missing formula in work center
    2) Operation 0020/suboperation(or cost comp):activity type not entered.
    3) No control record for activity type in version 000/2009 activity planning/qty planning.
    could you please help me in this?
    Regards,
    Abdul Rehman

    In your work center, use "SAP008" formula in the costing tab.
    Copy the activity type you have used in the work center (again in costing tab) & use this activity type in your project internal activity. Use the same unit of measure in your project internal activity, that you have defined in the activity type.
    Define correct rates in KP26 for your activity type.
    It should work now.
    Good luck.

  • Cost calculation error while creating production order

    Hi, "version 0 is not defined in controlling area xxxx for the fiscal year 2008, maintain the fiscal area dependent version parameters for the version o".the above error message appears at the time of saving my production order with co01 t-code. i have tried to rectify this by okez t-code, but it gives message that "activation of the indicator is notallowed". the same message appears while releasing the order, while doing the GI . Pls suggest.

    Hi,
    Please refer the below thread.
    https://forums.sdn.sap.com/watches!add.jspa?forumID=144&threadID=484386
    Regards,
    Senthilkumar

  • Confirmation with errors in calc. actual costs for PM-order

    Hi,
    We have a PM-order with notifications and good movements that has tecnical completion status and is already settled. So we want to set it with bussines completion status, but an error arises: "Unprocessed future change recs for order 5009385 prevent del. flag/completion"
    We already checked for automatic goods receipt pending, backflushes, etc. and the only found is an error record in actual costs calculation (trn. COFC). Looking at this record the message says: "No prices could be determined for object Activity type CONA/900097/PM-100" (message KW 407).
    We checked price set for the activity type and cost center and is set for all the periods of actual fiscal year. Then looking at the details for above message, we found the following: "No price could be found for object Activity type CONA/900097/PM-100 with price indicator 7 and value type 4"
    The question is: why system is trying to get price for activity type PM-100 with price indicator 7 instead of 3 as usual for our PM-orders? How price indicator is defined from actual PM-order parameters? Any idea?
    Regards,
    mr.

    Hi
    Whats your activity type category? I believe it should be 1
    Your point is right, price indicator shud be 3 because while confirmation system uses the planned rate.. And price indicator pertains to actual activity price..
    Check whether you have calculated or maintaned actual activity price or not in KBK6
    Ajay M

  • Error arose during actula Cost Calculation

    SAP PP Experts,
                             I have a Problem in <u><b>CO11N</b></u>, While Click <b><u>Goods  Movements</b></u> the follwing Dialog Box was Appeared.
                             <i><b><b>Error arose during actual Cost Calculation</b></b></i>
                             Can You help me how to Reclaim It?

    Hi,
          In COFC you will find the error message. Read error and correct it

  • How to avoid actual cost error log while confirm production order activity

    Hi
    I dont want to post actual activity cost via production order activity confirmation. But i want standard value keys for my production duration purpose. So,i defined activites(strd value key) in work center without assigning cost center to that work center. While i confirm in CO11N, system throws erro log as Actual cost calculation contain errors and allows me to confirm the activities. I am doing MB31 and all CO settlement activities also. But when i try to close the order it says error log exists,so closing of order is not possible. How to overcome this problem as i dont want to capture any cost of activites via production order,but i want confirmation only for production analysis.

    Hi
    Issue is resolved thru PP forum. Thanks for ur reply.
    Solution lies in Control key of routing and BOM costing relevancy.

  • Actual Cost Process request run terminated with Error Signal 11

    Hi All
    Could not run Actual Cost Process as it is terminated with error signal 11. Please tell me the reason/cause if any one has come across this error before in your cost running process. Thanks in advance for your valuable suggestions.
    I am using PPAC cost method and on Release 11. I search in metalink and Apply Patch 5208603, 5475347 but But failed
    Pls Help me???

    Hi,
    Were you able to relink the executable file via adadmin successfully?
    Please see if these documents help.
    Note: 402805.1 - Actual Cost Process Fails With Error Message 'Signal 11'
    Note: 402829.1 - GMCACOST Actual Cost Process Completes In Signal 11 Error After Applying Patch 5386789
    Note: 375764.1 - Actual Cost Process terminated with Signal 11
    Note: 389970.1 - Actual Cost Process erroring out with Signal 11
    Note: 338230.1 - Actual Cost Process Failing With Signal 11 Error while processing inventory transfers
    Regards,
    Hussein