I my company we have batch determination as well as batch derivation. Also on FG & SFG level different order type. Now we have scenario that A1, A2, A3 material having common bulk component. Where as A1, A2, A3 are vial packing strengh. Here is probelm that if all BOM component of A1,A2, A3 are available then bulk process order will get release & wise versa else error.
Now i wish to adopt the collective order scenario with phantom assembly. Here i will create one phantom material code with BOM component as A1,A2,A3... Will it work for me in collective order scenario with different order type?. IF yes then please guide me how i can configured this in SAP.

Hi Nivedita,
Question is not clear....A1,A2,A3 are FG products which have common SFG as a input material ?
map like this... bulk material SFG will have raw materials in it's BOM...Now FG material will have SFG material and other packing materials as input materials in the BOM....now make the setting in such a way that during process order release if components are not available system should not release the order...make settings in OPJK in configuration...
Thanks
Kumar

Similar Messages

  • Collective Orders with Phantom assembly

    HI experts,
    Required clarity on following scenario urgently.
    Material                                                Proc Type                             Special Proc
    A                                                                 E
    B(BOM item for A)                                       E                                             52
    C(BOM item for B)                                        E                                              50(phantom)
    C1(BOM item for c)                                        E                                             52
    When we are creating the production order for A,respective production orders for B and C1 is genrated.
    Now when we are confirming the production order for C1,GI of c1 to B is happening and also for C! production order it is giving the DLV status.Up to this the scenario working fine.
    But when we are confirming the production order for B,the GI for production order A and DLV status for production order B has to happen,BUt it is not happening.
    Can anyone throw some light on this. Expecting reply at the earliest.
    Thanks in advance.
    Regards
    LN

    Hi
    ritesh,
    It is not the question of control key.
    But the error is coming at the time of goods movement,we can see the description of it in "cogi".
    "ERROR IN DEPENDENT GOODS MOVEMENT."
    Because For 'c1',After confirming the order for 'C1',it will do the GR for 'C1'and GI of 'C1'to 'B' production order.
    Up to this it is working fine.But the same when I am trying for 'B'production order,After confirmation the GR for'B'is not happning And the Issue of B to 'A' production order is not happening.
    And in COGI the above error is coming.
    I want to know weather this problem occuring because of phantom assembly with collective order.
    Hope this will clear the problem understanding.
    Regards
    LN

  • How do we Prevent Creation of Production Orders for Phantom materials.

    Dear Experts;
    We have some materials which are Phantoms.
    We have set "special procurement type" as 50 in MRP2 and "Strategy Group" as 59 in MRP3
    These are non stchable items, but have BOMS.
    We dont create orders for them, however at the mement the system allows order creation. How do we prevent creation of production orders for these items in the system.
    Thanks in Advance
    Richard.

    Dear Richard,
    Check using this BADI - WORKORDER_UPDATE using method IN_UPDATE or Release by including a check if MATNR and for
    WERKS combination if SOBSL = 50 from table MARC,then do not allow to save.
    Check whether this works or else you have to set a plant specific status using OMS4  for not allowing production order
    creation and assign this value in the material master of the phantom assemblies.
    Check and revert
    Regards
    Mangalraj.S

  • COOIS Capacity report for Collective Order

    Hello Expert,
    Need your help & assistance. I have an issue related to collective order, COOIS report display for list Capacity.
    For one collective order, when I check this COOIS>Capacity report it display only header order detail, not for dependent order.
    But for another collective order for same order type & Plant, it display for both header & dependent order.
    Please find the  attached word doc with screenshot for the steps I am following. Please point out the reason, that I can check so that for first order also it displays both header & dependent orders in the COOIS > Capacity list.

    Case:01: Wherin COOIS>Capacity list display only show for header order not dependent order
    Case 02:Wherin COOIS>Capacity list display show both for header order & dependent order
    Order type & Plant is same in both cases.
    For detail please check .xml attached
    Regards
    Piyush

  • MDVP for collective orders

    Hi Experts,
    I have a scenario that if i run material availabilty check for FG material then all level of BOMS planned orders should be check collectivily. I have set the process as Collective orders for that because client wanted to have a linkage between parent order and sub-order.
    But Now in MDVP I can not see any option to run the collective orders material check as in COHV where collective orders check box is present. Can anyone tell me how I can do the material availabilty check for collective planned orders too?
    OR any enhancement I have to use for that?
    Regards
    Deepak Sharma

    Dear,
    Solution for this also same use the function module MD_SET_ACTION_PLAF for action control.
    Transaction MDAC .
    Also in MDVP -
    > you put there as 000001-Standard profile
    and 000001- Planned order view and put plant and execute that so will also work as collective.
    Please try and come back.
    Regards,
    R.Brahmankar

  • Collective Order Actual Activity Pricing

    Hi Gurus
    We are using collective orders for production orders. As you know collective processes are used for costing shared processes.
    Let me explain the problem with an example: Say, we have product A and B to be produced. These two have shared operations and costs will be collected via collective orders by Tcode mill_oc.
    The process is as below:
    Production order 1 for product A. - Normal production order - CO01
    Production order 2 for product B. - Normal production order - CO01
    Production order 3 for product A - Collective production order - mill_oc
    Confirmations are done for Order 3 during period. At the end of the period Order 3 is settled to Order 1 and Order 2 with certain proportions.
    Actual activity price is calculated via Tcode:KSII. During CKMLCP the system valuates activities (posting price differences) for Order 3 product, Product A only. It must be the case that Product A and Product B have to be revaluated.
    NOTE: Actual activity price is valuated in material ledger, rather in orders (not with CON2)
    Is there any OSS notes or solution for this problem? If there is huge activity price differences, all the value is posted to just one product, which is collective orders product, rather than both lower level orders' products.
    Thanks in advance for your replies.
    Ahmet

    Hi Ahmet,
    This is rather a problem of material ledger multi-level settlement than of activity pricing. Material ledger will pick up the actual activity price correctly and will use the difference against the former activvity price as multi-level price difference on the production process. The problem is, if there are multiple outputs coming out of the process, as is resulting of the order combination process, material ledger will by default search for a apportionment structure (for joint production) in the material master of the main (or original) output material. As nothing will be maintained there, all the differences will go to this material.
    You can overcome the situation by a BADI implementation of BADI cost_split. There should be an example implementation in your system (if you have the Mill Products add-on active, as is indicated because you use Mill_oc) that enables to distribute the price differences by quantity of the outputs of a process. If you don't find the example implementation I could provide it to you.
    best regards,
               Udo

  • Collective orders issue

    Hi Gurus,
    There is an issue with the collective orders for our client. For the child orders the Plan and actual are coming same. And for these child orders GI and activity booking is done but GR is done at the Parent order level.
    Pls tell me at this point how the plan and actual are equal for the child orders.
    Regards
    Dinaker

    I want to explain this more clearly.
    we are using collective orders and planning strategy 10.
    Say we need 1 roh to produce 1 halb
    and need 1 halb to produce 1 fert.
    target qty =100 say
    MRP run
    Production order qty for fert 100
    production order qty for halb 100
    purchase req qty for roh 100
    say GR for roh qty 50
    we confirmed qty of halb = 50 i.e:partially confirmed
    Now went to fert order and will be able to confirm 50.But this is not happening.User is able to confirm 100.
    we should be able to confirm only 50 since we have halb=50.
    How to restrict this.he should be able to confirm fert qty 50 since confirmed  halb qty is 50.
    Could  you please tell me what config setting i should do and where.
    thanks

  • Collective deliveries for open sales orders

    Is there any process or transaction code  for creating the collective Picking  for open sales orders.
            In my company we are not using the Warehouse management, so we pick the goods manually.
           If there is any way plzpost the answer.

    Check if VG01 helps you if you enter "K" as Group Type
    Cheers

  • DOCUMENTED  GOODS MOVEMENT  FOR COLLECTIVE ORDER

    Hi Guru's
    In  the  4.6C version 
    If i got to Production order from transaction code CO03 , Read the collective order , highlight the toplevel item and ''GOTO'' in the menu bar and select Documented goods movement , the display shows the Top level order AND the Sub-Assemblies.
    ( sub-assemblies goods movement with main assembly  can be seen in the single screen)
    In the ECC 6.0 Version
    If i got to Production order from transaction code CO03 , Read the collective order , highlight the toplevel item and ''GOTO'' in the menu bar and select Documented goods movement , the display shows the Top level order only.
    To see the Goods Movement in the Sub-Assemblies  you have to go to each production order individually.
    can this be changed in ECC 6.0  exactly to that seen in 4.6c version .
    pls give me your valuable inputs at the earliest .
    Thanks for your help.
    Regards
    satish k

    Hi satish,
    In collective order struture ,Automatic goods movement will be happened between toplevel & lower level.
    Please check with "coll order goods mvt" settings for order type at OPJH For ECC 6.0 version.
    Please also check with cost analysis for Goods movement.
    Regards
    Pradeep

  • MRP for collective order

    Dear experts:
           I met a problem of Collective order.
           My scenario is :   Fert (A) -- Halb (a) -- ROH ( b) .  Set special procurment 52 in mrp2 of material a.
           suppose material "a" has stock 30pcs,  now when i creat a Plan order for "A" 100pcs,
           and then run MRP,system generate a plan order "a" 100pcs directly,
           not consider the stock of a (30pcs). 
            my question is how to setting, then i can get the result :  Plan order "a"  is 70pcs.
            And also how to setting when scenario is creating Production order.
            Thanks in advance.

    Dear R.Brahmankar:
          Fert A :        M0      Individual/coll.  "blank"
            Halb a:       M0  ,  special procurement:  52  , idual/coll.  "blank",     stock 30pcs
               ROH b:   PD.
      Now , I creat a Plan order for "A" :100pcs, and Run MD41,  
      result is:    material  "a",   plan order :  100 pcs.
      but what I expectation result is :   material  "a",   plan order :  70 pcs.  for I already have 30pcs stock  of material "a".
      how should i do. Thanks

  • Collective PO - Generating Delivery Orders for STO using VL10B?

    Dear Folks,
    I have created a collective PO from various STO. After goods receipt for the PO, I need to generate delivery orders for the STO. Is it possible to create the delivery orders using transaction VL10B/VL10Batch instead of WF30/WF50?
    The issue is because we would like to generate the delivery orders in the background by batch job.
    Best Regards
    Junwen

    Hi,
    With merchandise distribution you can configure the system to automatically create the deliveries when you perform the GR.
    Look at the configuration for the Site Distribution Profile.
    Logistics general->Merchandise Distribution->Site Profiles for Merchandise Distribution
    If you are using different data for the 'Pull' Business Process ensure that the Point of CD/FT/PA Delivery gen fiels is set to 1 - 'Goods receipt'. Else just do above config for the 'Default' settings (Blank in Business Process).
    This will result in creation of Delivery at the time of GR.
    Regards,
    Naveen

  • Collective scheduling for planned order

    Dear Gurus,
    i create the planned order using the bapi standard whit the production version , but when create the new planned order the version don't is read in the order, ( BOM + ROUTING ) OF THE version.
    For read the production version you must reschedulling the planned order.
    Are there the methods for read the production version at the creation of the panned order ,
    or the strument for rescheduling collctive?
    Thanks a lot
    Daniele Pistilli
    PP TEAM

    Dear Gurus,
    thanks for indication of the material master, but we don't  always manage the versions of productions.
    For the production order there are the routing without the production versions, but when i create whit the bapi or whit the transaction MD11 the new planned order manually i need setting the production version , but when i setting the version for the find the version ( bom+routing) i must re-scheduling the planned order.
    Are there the BAPI or alternative soluction for re-scheduling the planned order collective, or for read directly the version present in the BAPI ?
    Thanks a lot
    Daniele Pistilli
    PP TEAM

  • Unable to View low level items for Phantom Assembly - Order created in APO

    Hi All,
    I am unable to view the sub items when I create planned orders in APO and production orders in ECC. But when the order for the same material is created in ECC, I can see all the sub items. I see that this issue is only for Phantom Assemblies.
    And I cannot say that all the items in the Phantom do not appear, actually some of them do appear in BOM explosion.
    For example:
    Pld Ord is created for A in APO
    Prd Ord for A is created in ECC
    A has B, C and F as requirements
    and  B is phantom
    B has D and F as requirements
    Then my BOM explosion shows
    ..1 B
    ..2 D
    ..1 C
    ..2 D
    ..2 E
    ..1 F (This only gives the quantity required to make A)
    But it should also list how much of F (..2 F) is required to make B.
    Where as it comes up in ECC.
    Do I need to change the material settings for Phantom or is it just the UOM that is creating an issue?

    Hi All,
    I am unable to view the sub items when I create planned orders in APO and production orders in ECC. But when the order for the same material is created in ECC, I can see all the sub items. I see that this issue is only for Phantom Assemblies.
    And I cannot say that all the items in the Phantom do not appear, actually some of them do appear in BOM explosion.
    For example:
    Pld Ord is created for A in APO
    Prd Ord for A is created in ECC
    A has B, C and F as requirements
    and  B is phantom
    B has D and F as requirements
    Then my BOM explosion shows
    ..1 B
    ..2 D
    ..1 C
    ..2 D
    ..2 E
    ..1 F (This only gives the quantity required to make A)
    But it should also list how much of F (..2 F) is required to make B.
    Where as it comes up in ECC.
    Do I need to change the material settings for Phantom or is it just the UOM that is creating an issue?

  • Business scenario for collective orders

    Hello folks,
    Can somebody explain the business scenario associated with collective orders? why we need collective orders? what is the business requirement that calls for collective orders?
    Regards,
    Sravan Kumar

    You may create several production orders from several planned orders, provided that the planned orders exist in the same plant and belong to the same MRP controller. This is called collective order conversion.
    A collective order is a linking together of planned orders or production orders over several manufacturing levels.
    Every production order has its own routing and order number.
    When you are in the collective order structure, you can edit an individual order, a subtree, or the entire collective order.
    Goods movements are not required for sub-assemblies. The material is passed on directly to the next
    order up.
    The special procurement key determines whether direct production is involved.
    Since no goods movements are required for sub-assemblies, this means that you have less data to maintain. Goods movements are only required for the leading order and for components whose special procurement key does not stipulate that direct production should be used.
    Changes to dates and quantities affect all related orders.
    The actual costs of the production process are more realistic because they are not influenced by the
    predefined price in the material master.
    Master Data.
    Special procurement key "52" on MRP 2 view
    Individual Collective Flag MRP4 view
    Bills of material and routings at each assembly level
    Any structure possible

  • Collective Orders with GR & GI for sub-ordinate orders

    Hello,
    I am lookng for collective Orders where superior order and sub-ordinate ordes can be tagged together and at the sametime, I would like to GR for sub-ordinate Order which trigger Auto GI to superior Order. this feature is not available in collective orders.
    why I am looking for GR execution is that GR quantity changes for sub-ordinate order from one order to another order always. it needs to be actual.
    any work acound to satisfy this requirement?
    Thanks
    JK

    Hi JK,
    I have a doubt that whether this would be a business requirement. Say as per the BoM if there are 3 levels the last level was expected to be produced as 100 UoM but after production run the yield was 98 UoM or 105 UoM then how system will undertsand that it should post the GI of level 3 SFG2 as yield produced from the last Production/ Process order. But at the same time you need to do subsequent adjustment at SFG1 level also.
    This is highly dynamic situation thats why when you have multiple level of BoM and at each stage the chances of yield variation is high then its always better to create Production/ Process order of superordinate level of BoM when the lower level are produced, confirmed and available in the stock.
    Regards,
    Shoyeb