Collective requirements of Planned orders
Hi All,
When i see the report of planned orders MD16, the planned orders of same material in the same date are not added as 1 planned order. Although i have used the value 2 in MRP view 4 for the field Ind/Collective requirements
Please advise
Dear,
If you want to use the collective requirement then use some other lot size according to your requirement but not lot for lot (EX). May be you can use daily lot size, weekly lot size or monthly lot size. So your requirement will be collected according to your lot size maintained. Revert back for more clarification.
Hope it will help you.
Regards,
Alok Tiwari
Similar Messages
-
Field setting when collective conversion from planned order to PR
Dear expert:
Is there any way(except ABAP enhancement) to add the field "tracking number" in MD15 when I conduct collective conversion from planned order to PR. Seems in standard config this field in not included in this screen. I have set this field as a mandatory field, but even though when I conduct the conversion, this field still can not be displayed in the MD15 conversion screen.Hi,
There are following T. Codes to convert Planned Order to PR;
MD14 - Individual Conversion
MD15 - Collective Conversion
MDUM - In Background
Also MD04
User Exit is LMDZU001 - User exits in additional planning -
List of dependent requirements of planned order for a component
Dear guru ,
I search a list of dependent requirements of planned order for a component
What do you suggest ?
Thanks.Hi Cristano,
Go to MD04 transaction, enter comopenet and plant. Then from the list select the Planned order and click on the Order Report from the bottom tool bar available below the list.
You can see the componets details for that planned order.
Thanks and regards
Murugesan -
Collective conversion of planned order to one production order
Dear all,
1. I have N number of pld ord for same material so i need to convert as production order with cumulative quantity.
Because to reduce Issing and confirming and receiving of number of production orders.
2. I need to create Number of production order with diffferent material numbers in one screen with different production order number.
Because per day i need to create more number of production order with different material number. If i create one by one it will consume more time as well as its not practical possible for our business scenario.
Pls let me know any standards are available in SAP.
Regards,
S.Suresh.Dear Suresh,
You can convert Planned Orders into Production order collectively as a mass maintanance in CO41 Tcode.
Revert if any doubt in case using above tcode.
Further if you wish to have one production order against multiple planned orders it is not possible as per Standard SAP.
You can convert to each planned order into individual production order not to single production order.
If you wish clubbed production order then better you use Individual / Collective Indicator as
2 Collective requirements only
Then you will get cumulative planned orders only against each material and you can convert all of them cumulatively to production orders in CO41 as a mass maintanance.
Hope your problem resolves.
Regards,
Tejas
Regards,
Tejas -
Dependent Requirements vs Planned Orders: how to retrieve?
Hello SAP Gurus,
I have noticed that in table PLAF, we can see which (simulative) requirement has been generated by MRP for a given planned order.
Also, in table MDSM, we can see what was the originating planned order for a given requirement.
My question is: is there a way to know what is the originating requirement for a given planned order? (most probably, in another table than MDSM and PLAF).
Thanks in advance for your light...
Regards,
RudyHi,
You can see the ordinal planned orders in MD05 and MD06 t-codes.
for tables search in SE93 by key in MD05 and MD06 where you can get all programs, Tables related to that T-codes.
revert me if any issue..
Regards,
Ravi -
Collective scheduling for planned order
Dear Gurus,
i create the planned order using the bapi standard whit the production version , but when create the new planned order the version don't is read in the order, ( BOM + ROUTING ) OF THE version.
For read the production version you must reschedulling the planned order.
Are there the methods for read the production version at the creation of the panned order ,
or the strument for rescheduling collctive?
Thanks a lot
Daniele Pistilli
PP TEAMDear Gurus,
thanks for indication of the material master, but we don't always manage the versions of productions.
For the production order there are the routing without the production versions, but when i create whit the bapi or whit the transaction MD11 the new planned order manually i need setting the production version , but when i setting the version for the find the version ( bom+routing) i must re-scheduling the planned order.
Are there the BAPI or alternative soluction for re-scheduling the planned order collective, or for read directly the version present in the BAPI ?
Thanks a lot
Daniele Pistilli
PP TEAM -
Collective conversion of planned order
hello experts,
i have some planned orders, while doing the collective converison in production order by CO41 i m unable to do so, the system is giving the error message "PLZ MAINTAIN SETTLEMENT RULE" and message number is "ZSD01000", but i can convert these planned orders individually in MDO4, there's no problem in individual conversion in MD04.
Regards,
Sarfaraz.Dear
Check ur configuratin settings
1. U must have maintained Plant Parameters for the Planned Order - Conversion
In that the profile u have selected, maintain that in the Settlement Profile Customization.
Use T code - OPPQ for Plant Parameters Settings
Use T Code - OPKT (Define Settlement)
Regards
Samunder Singh -
Dependant Requirements and Planned Orders
Hi,
For dependant requirement, question is whether once the planned orders (of independent requirements) are converted to production orders, then only will the dependant requirements be converted to planned orders or it is converted once independent requirements are converted to planned orders? I.e. independent requirements are blown down all the way in MRP.
Thanks.
Rgds,
SueHi,
Let us take some example so that it is easier to explain.
Material A - Finished Good
Material B - Raw material
PIR generated for A - 100 Nos , MRP is run and Planned order created for A - 100 Nos. Now
For Mtl B Dep reqt is generated for 100 Nos.
If No stock is available then a planned order for 100 nos generated.
IF Stock is availabel then no planned order is generated.
When production order is created for Mtl A then the "dep reqt" status of Mtl B changes to
"ordres"(order reservation)status.U can check this MD04.
Thanks and regards,
Rajesh -
Collective deletion of Planned Orders
Hi,
We want to delete MRP generated planned orders collectivily. However we are using MD16 for it, but it is very slow process to get rid of unwanted planned orders. Our limitation is we can't go for re-generative planning.
Please help with any BAPI, function module or transaction code.
Regards,
AmolDear Amol,
Check this BAPI BAPI_PLANNEDORDER_DELETE in SE37.
Regards
Mangalraj.S -
PP - creation of planned order
HI,
I have a finished product say F001
which has the semi finished product - say- a001
and a001 has another semi finished product - aa001
aa001 has another semi finished product - aaa001
Now When I run MRP for finished product F001 and after that i run MRP for
all the semi finished products individually.
3 planned orders and 3 dependent requirements were created for a001.
1 planned order & 3 dependent requirements were created for aa001.
1 planned order & 1 dependent requirement were created for aaa001.
My client requires 2 planned orders for aaa001( semi finished product)
can it be done. points assured
Thanks
RHussainDear Rashed,
Please check with this.
1.<b>Maintain Individual/Collective requirement's indicator as 1 for your finished
product in MRP4 view -</b> You can find this field under BOM xplosion/Dependent
Requirements.
Check this,if not modify and take the MRP run.
The following is the help taken from SAP.
Dependent requirements ind. for individual and coll. reqmts
Indicator determining whether the following requirements are allowed for the dependent requirements of the material:
<b>Individual requirements</b>
Requirement quantities of the dependent material are stated individually.
Collective requirements
Requirement quantities of the dependent material are grouped together.
<b>Use</b>
You can maintain this indicator in the following places:
In the material master record
For the explosion type of the BOM item (in Customizing for Basic Data in Define Explosion Types)
The setting for the explosion type overrides that in the material master record.
<b>Dependencies</b>
If the material is assigned to a material type that does not allow quantity-based inventory management in this plant, you can set the indicator to individual requirements only.
If the stock is to be managed in sales order stock or project stock, the indicator must be set to one of the following options:
<b>Individual and collective requirements</b>
Individual requirements only
If a material managed in project stock is to be procured from another plant using a cross-company-code stock transport order, the indicator must be set to 2 (collective requirements) in the issuing plant because, in this specific context, individual project stock management is not possible in both plants.
<u><b>Reward points if useful.</b></u>
Regards
Mangal -
After firming planned order, new planned order is generating in MRP run
Hi Experts,
I am using SAP AFS. Planning strategy is 21- MTO with Project settlement. MRP type is PD. Lte size is EX. Procurement type is X.
We are using the production versions. Individual / collective reqmts is 1. Planning time fence is not maintained.
In sap AFS T.Code for MRP run is /n/afs/md02. After receiving the Sales order, MD04 screen gets updated accordingly and I am running the MRP.Planned orders are generated accordingly. I am firming the planned order manually through MD04. The satr mark is also appearing.
My problem starts now. If I am running the MRP again for the same requirements another planned order of the same qty. is getting generated. That means after the second MRP run, I am having two planned orders (one firmed plnd order) and second is the new planned order. My requirement is that MRP should not generate any new Plnd. order / PR's if there is no new Sales order.
The parameters for MRP run are "1" for "Create PR's", '1" for "Plng Mode" and '"1" for "scheduling ".
I have tried in all the possible ways, but of no use. Still new plnd order is generated after firming the 1st plnd. order in MRP run.Thanks all for your feedback..
@ Vishal
1. Yes, Both Old firmed planned order and newly generated planned order have the same grid value
2. For both the planned orders :
Special Stock is E u2013 Orders on hand,
Consumption is V,
Sales order is the same (As we are using MTO , Strategy 21) and same WBS element.
3. First planned order is not in the assigned tab of MD04. This means that has been allocated to some object. u2013 I didu2019nt got this point. Can u please elaborate?
@ Nikhil
1. Quantity of sales order is not reducing after firming the sales order
2. Account assignment category for both the planned orders is u201CZu201D - Indiv.cust./project
I have made some more observations and found the following differences between the two planned orders
From MD04 , keep the cursor on corresponding planned order
& click on upward arrow ( available on bottom side of the report).
It will show what will be the originating requirements i e. for which requirements this planned order generated.
For Firmed planned order it is taking me to screen u201CPegged Requirements
u201D*And the following data is present:
Planned dates: 04.07.2010
MRP element No. 3100001185 (Sales Order No.)
MRP element item 100
Scheduling No. is 1
MRP element indicator - VC u2013 Order
MRP element data- 3100001185/000100/0001
Plng segment u2013 3100001185000100000
P.O / Order Type u2013 ZX
Rec/reqd Quantity 10
MRP element u2013 Order
For new planned order generated, I am going to Screen *u201CProcurement without Requirementsu201D
*The following data is present
Planned date 03.07.2010
MRP element No. 0000123522 (Planned order No. of the newly generated after MRP Run)
MRP element Ind. u2013 PA
MRP element data 0000123522/SO
MRP element item 1
Scheduling No. 1
MRP segment 20
Plng segment u2013 3100001185000100000
Rec/reqd Quantity 10
P.O/Order type- KD
MRP element u2013 Plnd Order -
Planned order deletion in mass
Hi,
I want to delete all palnned orders in the plant.
Planned order can be deleted using MD16. In MD16, MRP controller is the mandatory field. We can't delete all the planned orders in one stretch in a plant. We can delete the planned orders in a plant MRP controller by MRP controller only. My requirement is without giving MRP controller, the system has to delete all the planned orders in the given plant.
Is there anyother way to delete all the planned orders in a plant.
Regards,
V. SureshDear Suresh,
Check whether T code MDBA,can help you.
Also refer this thread.
Re: Collective deletion of Planned Orders
Regards
Mangalraj.S -
How to view the planned orders in mass and how to delete in mass
Hi gurus,
How to view the planned orders in mass and how to delete in mass.
Regards
R.RajakarthikHi,
Use the collective display of planned orders, transaction code MD16.
You can select the data by different options and choose which ones or all that you need to delete.
Click the Delete button to trash them.
This will delete planned orders without deleting the planned independent requirements and sales orders.
Hope it helps -
Can we combine many plan order to 1 PR?
Dear Guru,
I have got the requirement to merge many plan order to 1 PR.
Is it possible to merge them?
I try to use MD15 but I don't know how to merge them.
Please kindly advice.
Thank you very much.
SaiyamanDear Sai,
Suggetion would be
If the scenario is MTO
Then in MRP - 4 view make indi/coll indicator to collective
If required one plan order weekly then use lot size as WB in MRP - 1 view
If required one plan order monthly then use lot size as MB in MRP - 1 view
Regards
Madhu -
APO: RRP3 automate Production order creation from planned order ?
Hi everyone ,
I have got a business requirement in APO where in Open sale orders uploaded in R/3, needs to be converted to Planned order and subsequently to Production order in APO-PPDS tcode RRP3 at all stages. They want to automate this process rather than doing it
manually.
Can anyone tell how is this possible . Any BAPI or function module available to do this . Please help.
Regards,
SyedHi,
1.You need to run the heuristics Planning of standard lots SAP_PP_002 in /SAPAPO/CDPSB0 by specifying the time profile
and strategy profile, planning version and propagation range, product and location.
2. Convert PPDS Planned Orders created to process orders thru /SAPAPO/RRP7 by specifying the product location start date of the order for production order creation.
Out put of step 1- For sales order requirement, PPDS Planned orders gets created.
Out put of step 2- PPDS Planned orders are converted to production orders.
Thanks,
nandha
Maybe you are looking for
-
I've seen similar questions, but no answers. Most commonly, I've seen people wanting to know how to code a link on their website to make it open in the sidebar. That would be handy too. My own goal here is to make all the pages I need open for work o
-
Learning how to sing/play a song
I would like to know if I can type the notes to a song into garage band and play it back so that I can hear how it sounds.
-
We moved in to the house in early March. At that time and for a month or two afterwards, Broadband (via WiFi) speeds seemed ok. Web pages would load in a reasonable time etc. However, initially over the last month or so, pages stopped loading at cert
-
9iAS Reporting Services Vs 6i Reports..urgent
Hi All, what is the difference in using the 6i reports and 9iAS Reporting services, as i know that invoking 6i report takes more system resources, will this problem can be resolved by 9iAS Reprot servvices or not, if so how and if not what i have to
-
Input XML having multiple values in the same tag
Hi, In my scenario, my input XML is in the following format... <Product> <Site_ID>A1, A2, A3</Site_ID> <SIte_Name>ABC, XYZ, PQR</Site_Name> </Product> A1 corresponds to ABC A2 corresponds to XYZ and so on... Is there some way to retrieve values from