There is a issue regarding budgeting.
we have some option that we are considering. pls give some views on it
option 1  whenever  we put a  cost center while making any posting ,system picks up a commitment code and then budget gets allocated. but here same commitment code gets selected for same cost center but different expenses in same cost center.
cost center is a/c              commitment code is       cc1    (g/l 1 repairs)
cost center is a/c              commitment ocde is       cc2    (g/l 2 salary )
option 2.  we have a GL bank charges and cost center  then based on this combination of gl and cost center a specific commitment code    a/c-b.charges get filled in commitment field.
if we have another cost center (IT) and same GL bank charges then based on this second combination another commitment code gets selected     IT-b.charges
so    for  cost center 1              if there are 30 commitment codes
then for  cost center 2              there will be another 30 commitment codes
so we have 60 cost centers then in all we will have 1800 commitment codes.
we want a way in which less commitment codes are opened yet we are able to achieve what we are getting in second option.

Hi
U r using Fund management , In Fund Manageemnt there are derivation rule. u create a GL account in FS00 , suppose Stationry expenses.the Same Account u created in fund management called commitemtn item.Suppose statioanry expenses.
in fund management u are also create fun center
u crerate aderivation rule, in derivation rule u assign :-
Cost center = GL Accounts
Cost Center=Comitment item=GL accounts
Fund center= Asset account
if any query feel free ask me
Regards
Roobal

Similar Messages

  • How to write a validaton rule for Cost Center and plant in PO

    Hi,
    I need to write a Validation Rule for Cost center and Plant in Purchase Order to get the error message if the Plant and cost center combination didnot match.
    But i am not sure in which transaction code do we need to write this validation. Kindly help me by giving T.Code or path to do validation at PO level.
    Thanks
    Sunil

    >
    Sunil Pal Raj wrote:
    > Hi,
    >
    > I need to write a Validation Rule for Cost center and Plant in Purchase Order to get the error message if the Plant and cost center combination didnot match.
    >
    > But i am not sure in which transaction code do we need to write this validation. Kindly help me by giving T.Code or path to do validation at PO level.
    >
    > Thanks
    > Sunil
    Check OKC7
    Regards,
    Indranil

  • COPA derivation for thecombination of Cost center and Cost element/GL accou

    Hi Gurus,
    In COPA derivation using KEDR i am trying to make a derivation for the
    combination of Cost center and Cost element. Here i got following problems
    • While posting FI document using t.code FB50 system not automatically
    updating the fields Cost center and cost element in Profitability
    segment. Hence system not posting COPA document. How can i make this
    derivation? Is there any note should i apply regarding these.
    • How can i create cost element as characteristic.
    • If i configure derivation for the combination of Cost center and cost
    element will it be posted with copa document for postings or automatic
    postings from MM,HR and FI
    Pls provide me solution at the earliest.
    Thanks and Best regards,
    Dhanumjaya.Ranga
    Mobile: - 919940093579
    Mail : [email protected]

    Hi Murali
    Thanks for update
    I explain my req clearly
    For me segment is Distribution channel field (EXPORT and DOMESTIC)
    If GL account is 1000-2000     always                      Export
    If GL account is 2001-3000    and Cost center is     X then Export.
    If GL account is 2001-3000    and Cost center is     Y then Domestic.
    Based on above REQ i am making derivation using KEDR T.code.
    These postings should work for all modules postings such as MM, HR also.
    Actually this should work automatically and after saving the transaction we should have copa document also.
    But problem is in source fields of derivation we have GL account (HKONT) and Cost element (KSTAR). I am making derivation using either of these.
    But after posting document system not giving COPA document.
    I found the reason is  at GL postings we are giving input to GL account (HKONT) but we took in KEDR source field as GL account (SAKNR). GL account (HKONT) is not updating GL account (SAKNR) field in PSEG screen in Fb50. Even i try with cost element (KSTAR), GL account (HKONT) is not updating this in PSEG screen in fb50.
    If GL account (HKONT) updates either GL account (SAKNR) or cost element (KSTAR) at the time of posting FB50
    Or
    If we have the field GL account (HKONT) as source field in KEDR i hope my problem
    Get solved.
    If you want further info pls give me your mobile number then i ll call you

  • Cost Center and GL account in Sales Order / Delivery

    I have a requirement where we want user to specify what cost center and GL account should be used while posting goods issue.
    Currently GL account and Cost Center is automatically determined based on OBYC configuration.
    Is there a way  user can populate Cost center and GL account at Sales order or Delivery document level and what ever they have specified will be used for Posting Goods Issue.
    If user doesnt specify anything then standard OBYC determination should take place.
    I looked at OVF3 transaction which can default cost center (though no GL account) but its not useful in our requirement.
    I also looked at OKB9 transaction but not sure if we can use it either.
    Again we want user to enter Cost center and GL account at either SO or Delivery document level and then that should be used for Post goods issue.
    Thanks in advance.

    Hi,
    In delivery under tab GOODS MOVEMENT DATA
    After valuation type column COST CENTER & G/L Account column available
    Now with the help of FI consultant make it change mode so user can maintain  also I observe that if delivery created without reference to order then that fields are in change mode means user cn maintain data for this but if with reference to order it is disable mode
    Check in t-code OMJJ FIELD SELECTION FOR MOVEMENT TYPE
    Put movement 601
    Then select movement type and double click on filed selection (from 201)
    Then go to additional account assignment and for cost centre make it optional or requirement
    or Else under field selection enjoy for movement type 602 indsert field KONT0 and KOSTL and check
    If this can not work there is option field selection for G/L account check that with FI
    Kapil

  • Report showing total costs pr. cost center and internal order..

    Hi FI Gurus,
    Do any of you know a standard report, which can display G/L, Company code, Period, total cost in local currency, cost center and internal order. The report should be at summarizational levet (not line items) and we should be able to sum costs at cost center and internal order.
    Finally we should also be able to transfer the report to BI via an extractor etc.
    Thanks for you help
    Pernille

    Hi,
    Cost Centre vise Report you can take from KSB1
    Internal Order Vise Report you can take fro KOB1
    Regards,
    Sridhar Sha

  • Cost Center and Internal Order report

    Hi,
    We are trying to design an account structure using Cost centers and statistical Internal orders. So any invoice would be booked on REAL Cost Center and a STATISTICAL Internal Order. Can I pull up a report based on the cost center and also the internal order?
    Our other requirement is to report the values on the statistical internal order along with the values on a profit center ( can be any profit center belonging to the company). Is there any way to develop a report using special purpose ledger or ABAP that can achieve this requirement.
    Any help on this issue will be greatly appreciated.
    Thanks and Regards,
    Venkat

    In t code KOB1 - Order line items, you will get details of cost center as well. For this you need to display field Aux. acct assignment_1.
    Regards
    Rakesh Pawaskar

  • Cost Center and Plant

    Hi Guys,
    Is there any R/3 table that gives relations between Cost Center and Plants?
    Thanks

    The plant is an <b>operating area or branch</b> within a company and  is assigned to a single company code. A company code can have several plants.
    The plant plays an important role in the following areas: <b>a) Material valuation
    b) Inventory management c) MRP d) Production  e) Costing (material prices valuation)</b>
    A <b>Cost center</b> is an organizational unit within a <b>Controlling area</b> that represents a defined location to identify where a cost is being incurred. or an area of Responsibility for costs
    If you happen to run transaction KSB1 for a cost center, where plant field is not blank, you may find some material transaction. These are trasnactions which could involve both plant and a cost center.

  • Cost center and cost center group

    hi,
    how can i create cost center and cost center group?

    hi,
    after u enter in to sap easy access
    goto Extras menu-settings->select display technical names
    you can see the T.codes for each transaction
    for example:create cost center
    accounting>controling->cost center>master data>cost center>individual processing-->KS01-create

  • Link for Cost Center And Work Center.

    Dear Experts,
    Can you Provide me the Link for Cost Center And Work Center.
    Regads,
    Jyoshna

    Dear Experts,
    I got the answer for the Link Between Cost Center And Work Center.
    By using CR03   T Code we can see the Display Work Center : Cost Center Assignment Screen will appear.
    we need to select the costing tab, We can find Cost Center .
    Thanks & Regards
    Jyoshna

  • Cost Center and Profit Center Planning

    Hi,
    I have one  Co issue.  Pls Suggest me the wiseful solution.
    Cost Center and Profit Center Planning.
    For F-2008 Planning  data they have updated in the month of Aug, 07 for Profit and Loss Items and they have revised the plan data of some cost elements in the month of oct, 2007 (say 5% Increas).  when comparing the cost center report to profit center report, both are not matching.  the reason when i see and reconcile the document nos and values in between cost center and profit center reports  i found out that there are some documents are missing in the profit center report. 
    wherever plan data had revised e.g for cost element Salaries they have updated 100000 Planning cost in the month of Aug, 07.  In the month of Oct, 07 increased 5% i.e.5000. In cost center line items details i found 2 documents for Rs.100000/- and Rs.5000/-  But in Profit Center Line Items i am getting only Rs.5000/- Value Document.
    Note.  As and when KP06 Plan data has been updated Profit Center line items are generating.  It is not necessary to run any programme inorder to transfer Plan Data from cost center to profit center.
    Observations From My Side:-
    I tried to run the transaction code 1ke0. i have selected the cost object is Cost Center, version and had given Cost Center Parameter in development and quality clients and executed the same.By this time already existing data either deleting/ riversing and creating new documents fully except manually changed data in profit center through 7ke1.
    My Question is
    1.Upto what extent it will work.
    2.will it be possible to transfer data from cost center to profit center only missing documents which are available in cost center, without disturbing of existing data in profit center.
    3.suppose if i done this activity, there are some data which was already transferred from other cost objects like internatl orders & wbs elements to Profit Center. will the data get disturbed (deleted/riversed).
    Pls suggest me the wiseful way to solve the

    Hi
    Try This
    BAPI_COSTCENTER_CREATEMULTIPLE
    BAPI_COSTCENTERGROUP_CREATE
    BAPI_PROFITCENTER_CREATE
    BAPI_PROFITCENTERGRP_CREATE.
    Regards,
    V.balaji
    Reward if usefull

  • Transporting Master data - New GLs,Cost Center and profit Center.

    Dear Friends,
    1. I have to create new GLs in Dev, Now i have to transport the new GL to Quality and Production. As per my knowledge, Master data has to created in DEV,Quality and Production.
    please suggest, is there any t.code where i can transport GL from Dev to quality and production.
    2. when Creation of the site, New Cost center,Profit center, Changes to standard hierarchy both in cost center and profit center hierarchy has to done in dev,quality and production manually.
    Any suggestions where i can do only in dev and transport to quality and production.
    3. After creating new cost center and profit center, i have to go to okb9, select the co.code,cost element and insert the new cost center and profit center in every cost element. This takes almost one hour.
    Please suggest how to reduce this manually process.
    All the help will be greatly appreciated.
    Regards
    Sridhar Reddy

    Hi ,
    Master data is to be created in diffrent clients as it is a non transportable object .
    So in case of GL , cost centers you will have to again re run the LSMW which you had created for DEV .
    Secondly OKB9 is a transportable object , so i dont feel there should be an issue in adding it to a transportable object .
    In case of adding the values of tables in a request what you can do is create  a request , go to SE01 open the request in change mode in the objects enter TABU and enter on the relevant entries that you want to transport .
    But again one has to be very clear on what all table entries are to be transported , like SKA1 , SKB1 , SKAT etc. looking at the complexities and moving ahead with the standard way it is advisable to re run the LSMW in QUA and PRD .
    Hope this helps .
    Regards ,
    Dewang T.

  • Change the Accounting document fields cost center and profit center

    Dear Experts,
    User has posted document with wrong profit center
    For that we subjected that he can go to the profit center actual posting T.Code 9ke0 but with that he can only change the Profit center document with that there is no accounting side updating
    I have tried with Document Change Rules, Line Item for fields cost center and profit center  in that while configuring I did not get any error message,
    But in the document I am unable to changing the same fields cost center and profit center  
    Can any body please guide me to resolve the issue?
    Essentially I want to change the Accounting document fields cost center and profit center   
    Thanks in Advance,
    Wiswanath

    Hello,
    Once the documents are posted in FI module, the system doesn't allow anybody to change the cost objects (cost center, profit center, internal order). The only fields you can change through FB02 transaction are the Line item text (BSEG-SGTXT) and the assignment (BSEG-ZUONR).
    If you want to get a change to the cost object to be reflected from FI to CO, you should reverse the FI documents with wrong cost objects and post new documents with correct cost center, profit center.
    Hope it helps you.
    Cheers,
    Daniel.

  • Standalone Scenario -  Company Code, Cost center table

    Hi,
       Can any one please let me know the company code, cost center table used in standalone scenario.
    Regards,
    SAP Guy.

    Hi,
    The account assignment, Product category and Logical system combination is maintained in SPRO.
    SPRO > IMG > SRM > SRM Server > Cross Application Basic settings > Account Assignment
    There are three settings which you maintain there :
    1. Account assignment categories
    2. Define G/L account for product category , Logical system and Account assignment category
    3. Maintain local accounting data.
    These are the three settings which you maintain for account assignment determination.
    Hope this makes you more clear and helps in resolving your issue. Clarifications are welcome.
    Award points for helpful answers.
    Rgds,
    Teja

  • Display descriptions of cost center and G/L account in ME51N/ME52N/ME53N

    Hi Experts,
    Can any one suggest that how to display descriptions of cost center and G/L account in account assignment subscreen- ME51N / ME52N / ME53N.
    Thanks in Advance...
    Siva

    hi
    if the field is required then u have to enter them manually
    so if this are not required then goto OKB9 here give the default cost center for the Gl acct

  • Report Painter Request - Cost Center and WBS Element

    Hi Everyone,
    Currently, my company settles all project related expenses through to a cost center by way of an internal settlement cost element (category 21).  The issue with this is that when the expense gets to the cost center, they lose all visability as to where the expense originated, such as salaries or travel expense (category 1 cost elements).  We can't switch the settlements to the originating cost element from wbs to cost center just because of the additional data/volume that will cause.  My thought was to create a report painter that can run by cost center but also show the wbs's that settle to that cost center and group the expenses by primary cost element (cat 1).  I'm assuming that there is a way to marry a cost center and wbs element by way of the wbs settlement rule but how would that be done for reporting purposes?  I've seen it done before by way of a nightly job that created sets based on the combination of cost center and wbs but I'm not sure how that was done.  Any advise and examples?
    Example:
    Cost Center:  IT
    WBS: A.0017.01.01 (settles to cost center IT)
    Postings made:
    1.  CC IT and CE 552000 "salaries"..............................$20,000
    2.  WBS A.0017.01.01 and CE 552000 "salaries"........... $5,000
    3.  Settlement of WBS to CC (expenses flow through to CC IT by way of CE 985000)
    I want to run CC IT and see that the account 552000 really shows $25,000 and can be broken down by cost object (CC and WBS by the amounts above)
    Thanks,
    Pete

    Hi Peter,
    I had a similar requirement and used report painter report group 1SHK-002 (in library 1VK).
    I took a copy of the standard and ameneded it slightly, I switched the explode so it occured on the cost center not cost element.
    The report runs so that direct costs on the cost center are shown at primary cost level. And values settled to the cost center are shown on the partner object. In your case i guess WBS Elements (Partner ObjType WBS).
    Now in my case I didnt need cost element breakdown on partner level, just on cost center so effectively I have(sorry for text alignment but I hope you get the idea):
    GL1   .............  100
    GL2   .............  250
    + Cost center1 total ....350
    GL3 .............   50
    GL4 ............. 100
    + Cost center2 total.... 150
    Primary Cost Total ..... 500
    X-YZ-1.200 .............   50
    X-YZ-1.400 ............. 100
    + WBS total ............. 150
    IO 1............. 100
    IO 2  ............. 100
    +IO total  ............. 200
    Partner Total............. 350
    Overall total .............  850.
    Its not exactly like your requirement but it might be a good report for you to work with to get what you need.