Commitment cost of Purchase requisitions for Project

Dear All,
My requirement is like , I don't want Purchase requisitions  cost to come under commitment cost for Project.
Is it possible to do so.?
If yes, then how.
Regards,
Vishal

>
mforman wrote:
> How did you finally solve this issue?
>
> Thanks
Question
>
Vishal Murmoo wrote:
> Dear All,
>
> My requirement is like , I don't want Purchase requisitions  cost to come under commitment cost for Project.
>
> Is it possible to do so.?
>
> If yes, then how.
>
> Regards,
> Vishal
Answer
>
Nitin  Patoliya wrote:
> As suggested by Virendra,
> you can deactivate the commitment menagment in OKKP txn ( Maintain Controlling area ) --> slect your CoAr --> (Double click ) Activate component /control indicator -->   Commitmment management --> select drop down componenet not active.
>
> Make not that by doing this your are going to make inactive commitment management  to entire controlling area. with referenct ot PS.  i.e. all the project belongs to that controllling area.
>
> The SPRO node for the same is PS-->Cost --> Activate Project Management in Controlling Area.
>
> Please refer this post.
> http://help.sap.com/saphelp_470/helpdata/en/a9/ab7868414111d182b10000e829fbfe/frameset.htm
>
> Regards
> Nitin Patoliya
Correct answer already given by Virendra &  Nitin, Please try the solution before posting further queries.

Similar Messages

  • How to create a Purchase Requisition for a material component in WBS or NW?

    Hello All,
    I have created a project with the following structure:
    Project Defination (Construction of Sub station)
          Main WBS
                   Level 1 WBS
                             Level 2 WBS
                                       Network for level 2 WBS
                                                      Activity  (Procuring Material)
                                                                 Material Component - MATXXX (Stock Item)
    Now in the above structure i have a activity where in i am procuring all the materails required to construct a Substation.
    So under this activity i have assigned all the materials which are needed to build Substaion.
    After i change the status of the project to release, there  a reservation created for the quantity of the material which i have mentioned in the material component under the activity.
    Now my querey is, how should i create a Purchase requisition for the reserved materail quantity in order to bring in the stock against the WBS / network / Project ?
    Awaiting your reply.
    Thanks and Regards,
    Sudarshan.

    Hi Sudarshan,
    In your case you can run Me5J to check the list of PR created against your project.
    Then Create PO and similarly you can check list of PO in Me2J.
    Then followed by GR and check if any GR release exist in MIGO. Then once after doing GR you can check the Material in Stock which will move material from Unrestricted stock to Project Stock which you can check it in MMBE.
    Then you can do the Good Issue in MIGO itself and run MIRO to complete the cycle.
    Regards'
    syed

  • Stock transfer purchase requisition through project builder

    Hi Friend's,
    For transfering material from one plant to another plant we have to create stock transfer purchase requisition through project builder.
    Can is it possible to create stock transfer purchase requisition through project builder which will have account assignment category as Q & item category U.
    Thanks & Regards,
    Sandeep

    Hi Sam,
    Thanx for your input.
    We are dealing with project specific stocks & customer project scenario.
    My requirement is that we having 2 plants. Projects are created in 1001 plant, same plant does the mfg. of FG items required for projects & 1002 plant manufactures MTS items which are required to mfg. project FG items as well as same items will bring into 1001 plant and then delivered to customer.
    Here my clients want to create stock transfer pr through project builder to bring MTS items from 1002 plant to 1001 plant & then delivered to customer.
    I think as you said this is not possible in std. sap to create stock transfer pr through project builder.
    Thanx & Regards,
    Sandeep
    Edited by: Sandeep Theurkar on Mar 23, 2011 7:11 PM

  • Purchase requisition for service activity / element cannot be generated

    Dear SAP MM Experts,
    This is a service Creation from the PM order to Purchase Sercive Requisition.
    The Error Message Is Generated :Purchase requisition for service activity / element cannot be generated
    Diagnosis
         Due to the system settings, the system is trying to generate a purchase
         requisition for a service activity or a service activity element.
    No service package has been created for the activity/element.
    As a result, the system cannot generate a purchase requisition.
    The activity/element is created or released, but the indicator for
    generating a purchase requisition is not set.
    Create a service package for the activity/element and then generate a
    purchase requisition.
    regards,
    A S

    Solved From PM side

  • MRP creating additional purchase requisitions for the existing sales order

    Hi,
    We have scenario where we switch materials from POD material to ARP material. POD material is just like make to procurement which creates purchase requisition and purchase order upon saving the sales order. ARP (Auto replenishment) material creates purchase requisition based on sales order and re-order point while running MRP.
    When the material is POD title, it created purchase requisition and purchase order (example: 4500000110) while saving the sales order (example: 1000000010) for the quantity 10. After some time this material is switched to ARP and it has open sales order (1000000010) and purchase order (4500000110).
    We have special MRP run for ARP materials based on MRP type, which creates purchase requisition.. What is happening is when we run MRP; it is creating new purchase requisition for the old sales order (1000000010) for the quantity 10. But old sales order (1000000010) is already having purchase order (4500000110) to fulfill. So we donu2019t want to create new purchase requisition for the old sales orders. It should create purchase requisition only for new sales orders.
    Please advise
    Thanks in advance
    Srinivas

    Mangesh,
    If the components are Inhouse production then you can think of using collective orders by assigning special procurement key 52. If raw material exists then your requirement cannot be met..as i think your scenario is of assembly processing. The idea of assembly processing is that component materials will always be available and only assembly will be done based on Sale Order.
    Regards,
    Prasobh

  • Planned Order and Purchase Requisition for total Plan

    HI
    As per my client requirement whenever i am giving a plan in Demand Management in MD61 say for quantity 100. System should create purchase requisition for quantity 40 and Planned Order of 60.
    Please let me know if it is possible.
    Regards,
    Anand

    HI
    Thanks a lot. Its working with quota arrangement.
    Regards,
    Anand.

  • Purchase Requisition for Order BOM components ?

    Dear Members :
    Can I generate purchase requisition for Order BOM components from VA01 ? Mine is TAQ - the header itm cat and TAE for sub-items (finished prod) . While navigating within Sales Order and branching to a particular component's shced. line - the pruch req col is blank. The schedule line cat for the sub-item is CT.
    Could someone please explain the configuration steps I need to maintain for the above ? What I am expecting is when I save the Sales Order it should create Purch Req for the components which do not have enough stock.
    Thanks
    Atanu

    Hi :
    Thanks for your advice. Couple of things :
    1. In my system in auto acc assignment, I already have consumption acc under posting key GBB. Now I am getting error in VA01 - which states that "The system was not able to determn a consumption acc for purchase order item with acc assignment" and also suggesting to address "GBB posting key". I made the following changes for CT :
        movt : 101
        order type : NB
        item cat : 0
        acc assignment cat : F/C
    2. Obviously SAP is expecting a consumption GL acc, which though is there under GBB-AUF from my existing setup. For generating purch req this is strange becoz I haven't yet gone upto PO generation step nor released the supposed to be Purch Req.  for BOM component - and this is before I save the Sales Order .
    3. In spro->acc grouping for mov type; I don't see the following combination in SAP  ie,
    101(MvT) - B (MvT) - GBB (TEKey) - AUF. I need B instead of F which is already there and is for production order but the BOM comp has to be for PO but the combination is not there.
    Do you think this could be the reason that SAP couldn't find the GL acc ?
    4. Also my purpose was not just to raise a purch req every time the sales order is created for the BOM components - only if there is shortage in stock - but then again for CT once I assign the above, it doesn't allow to check the boxes like Availbility , Requrmnt etc. (??)
    Am I clear and could you please suggest me what I am missing or doing wrong ? What movement type do you siggest to enter in CT fields.
    Thanks so much for your time.
    Atanu

  • Multiple Document Types For Purchase Requisition For Different Order Types

    Dear SAP Gurus,
    I want to have different document types of Purchase Requisition for different Order types.
    For Example:
    for Order Type ZT01- Document Type used should be YR01
    for Order Type YA01- Document Type used should be ZR01
    How could this be achieved?
    Regards.

    hi
    Kindly check the user exit for the same
    COZF0001 or COZF0002
    regards
    thyagarajan

  • One Purchase Requisition for One Maintenance Order

    Dear Consultants,
    We have implemented mySAP ECC 6.0.   We have more than 20 line items in one Maintenance order for  Item category N. Curently system is generating Purchase requisitions by line itemwise for Item category N(Non-stock items). Our client requires only one purchase requisition for every Maintenance Order. Is it possible to generate one PR for one Maintenance Order? If possible please give us the solution.
    Thanks,
    Dev

    Dear Pete Atkin,
    With your help my issue has been resolved. Thank you very much.
    With Best Regards,
    Dev

  • MRP - Single Purchase requisition for multiple Items

    Hi
    We have recently introduced MRP module in SAP .In some specific scaeanrios , we want to create a single Purchase Requisition for multiple items .Standard SAP generate different Purchase requisition for each item
    Is there any way out

    Sandeep,
    This topic has been covered numerous times in this forum and in the MM forum.  You evidently have not used the search feature.  There are thousands of posts in these forums, and the search function will be very helpful for you in future questions.
    To answer your question, No, nothing is available to make standard SAP MRP create Purchase requisitions for multiple items.
    Most companies address this issue during the conversion of Purchase Requisitions to Purchase orders.  During this process, you can add many items to a single purchase order.
    Rgds,
    DB49

  • Purchase requisitions for  raw materials

    Iam having multilevel BOM and when I do Sales order MRP then Iam getting planned order for Semi finished items but not getting Purchase requisitions for  raw materials.

    Hi,
    Planing File Entry :-
    The planning file is used to limit the scope of the planning run for the
    total planning run. For this purpose, all materials that have been
    assigned a valid MRP type are automatically entered in the planning
    file.
    System will check the Planing file entry only in the case of Total MRP (MD01) or Total MPS (MD40).
    While there is no need in the case of MD02,MD03,MD41,MD42,MD50.
    Now how this Planing File entry activates,
    - Once MRP is activated at Plant level (T.code OMDU)system automatically maintains entry in Planning file for all those materials which contains the Active MRP type.
    - So if materials which are created before this activation of MRP in that case you have to maintain this planing file entry manual.You can do this either by MD20 or by using Back Ground Jon OMD0.
    Regards,
    Dhaval

  • BAPI to create Purchase Requisition for selective BOM Material

    Dear Experts,
    I need ur help, Actually I am developing a module Pool prg to create Purchase Requisition for selective Bom Material .
    Actually, standard T.Code (ME21N) create PR for a multiple BOM Materia lwhich are used to create a prepared material. But my requirement is PR should be generate for selective BOM material .
    Multiple BOM Material is used to prepared a complete Material .
    I have checked a particular BOM Material, for this matrial Purchase Requisition should be genrate.
    Please suggest me the related code and Bapi which helps me .
    Thanks & Regards,
    Swapnika

    Hi
    you can Use BAPI   BAPI_REQUISITION_CREATE
    Hope Its  help You.
    Regards
    Ajit

  • PURCHASE REQUISITION FOR SERVICE

    HELLO
    IN THE TRANSACTION ME21N FOR PURCHASE REQUISITION FOR SERVICE. IN THE SERVICE VIEW AT ITEM LEVEL, THERE IS A LIST DISPLAYED, SO I NEED TO ADD A FIELD WITH INFORMATION OF THE MATERIAL GROUP.
    ANYBODY KNOW HOW TO DO THAT?
    THANK YOU
    ELENA

    Hi,
    ME21N is the transaction for a PO creation.
    On the full screen services view you can enter either a service number (if you have maintained service masters in transaction AC01) or  you can enter just a short text to describe your service.
    There is also the column material group (ESLL-MATKL) available to fill in your material group (screen SAPLMLSP 0201). You can also enter your material group by selecting the service line and going to the detail view (popup "display service details", tab "basic data" (screen SAPLMLSP 0220).
    What do you mean by "list"? Have you switched on the outline view for your services? You can turn on and off this outline overview by hitting F6.
    Regards,
    Edit

  • Cost center not populated in Purchase requisition for a third party order

    Hello,
    We are currently testing the Third party order flow which includes :
    1. Creation of a sales order with item category TAS
    2. A purchasing contract is maintained for a sales order item at the schedule line level.
    (In the purchasing contract, account assignment is already maintained for each contract item, meaning a G/L Account and a cost center).
    3. Automatic creation of the Purchase requisition when the sales order is saved.
    >> The account assignment is not copied from the contract to the Purchase requisition. Do you know why and how I can do that ?
    Thanks
    Best regards
    Benjamin

    Hi Palani,
    if i am not wrong This WBS in location or additional tabs are used for settlement purpose. For PR creation by maintenance Orders can have Order number as account assignment.
    Please reply
    Thanks
    Sunil

  • Display purchase requisition for a material

    Hai...,
    can any one help me in developing a report to display purchase requisition based for perticular material number.
    tell me the tables and fields to  use..
    if possible sample code tooo....
    thanks in advance.

    Tables for Purchase Requsition.
    For Purchase Requisition
    EBAN Purchase Requisition
    EBKN Purchase Requisition Account Assignment
    EBUB - Index for Stock Transport Requisitions for Materi
    EINA - Purchasing Info Record: General Data
    EINE - Purchasing Info Record: Purchasing Organization D
    EIPA - Order Price History: Info Record
    EKAB - Release Documentation
    EKAN - Vendor Address: Purchasing Document
    EKBE - History per Purchasing Document
    EKBEH - Removed PO History Records
    EKBZ - History per Purchasing Document: Delivery Costs
    EKBZH - History per Purchasing Document: Delivery Costs
    EKEH - Scheduling Agreement Release Documentation
    EKEK - Header Data for Scheduling Agreement Releases
    EKES - Vendor Confirmations
    EKET - Scheduling Agreement Schedule Lines
    EKETH - Scheduling Agreement Schedules: History Tables
    EKKI - Purchasing Condition Index
    EKKN - Account Assignment in Purchasing Document
    EKKO - Purchasing Document Header
    EKPA - Partner Roles in Purchasing
    EKPB - "Material Provided" Item in Purchasing Document
    EKPO - Purchasing Document Item
    EKPV - Shipping-Specific Data on Stock Tfr. for Purch. D
    EKRS - ERS Procedure: Goods (Merchandise) Movements to b
    EKUB - Index for Stock Transport Orders for Material
    EORD - Purchasing Source List

Maybe you are looking for

  • How can I print a prn file on HP6500; I have windows xp

    How can I print a prn file on HP6500; I have windows xp

  • Ipod Video UK/US

    I have 1 ipod video which I bought here in the UK, and someone has just bought me a 2nd IPOD Video 80gb in the Apple store in New York as a present for a friend But I am worried when they get it home here I will not be able to transfer my DVD's to it

  • Merge Clips is greyed out

    I shot video on Canon 5D, converted to ProRes and imported into FCP 7. Audio was recorded separately on a JVC GY-HM100U (lens shut, so no video footage just sound) and imported into FCP. I've marked in on video and audio clips to merge them, but the

  • RE: Re: can't find libjava.so on solaris 8

    "No one answered the essential question of why the install program needs and can't find libjava.so. If it's a path or env setting I'd like to know about it so I can test this

  • Copying files ipad3 gives 'not enough memory'

    Hey folks, Very annoying and hard to find an answer to appearently. I am copying files to apps on my new Ipad 3 and I think I've run into some kind of limit. Itunes copies a few files and then throws an error message "File bla bla bla could not be co