Complications in the Product Allocation

Dear SAP Gurus,
I am facing lot of problems in configuring the Product Allocation.
Problem-01
I started creating new Info Structure S561 copying the existing Info Structure S140 as the Info Structure is to be assigned in OV3Z (Specify hierarchy).
The problem is that the Table MCVOBJECT is not appearing in the u201CCharacteristics for 0001 Incoming Orders Quantityu201D in the transaction code MC25. I tried to insert the Table name as MCVOBJECT and Field name as KONOB against the characteristics u201CProd Allocation obj.u201D but I got the error message as u201COnly source fields from MC Communication structures allowedu201D
Only few Table names are available after pressing F4.
Please help me how I can put the Table name MCVOBJECT and field name KONOB in the Characteristics for MC25.
Problem-02
In OVZ0  (Define Flow according to requirement category) I am not able to create new Requirement even in the change Mode. But I found some of them started with Z i.e. it has been created by somebody. I am in IDES system.
Problem-03
The same issue in OVZ8  (Process flow for each Schedule line Category) I am not able to create new Requirement even in the change Mode. But I found some of them started with Z i.e. it has been created by somebody.
Please guide me how to create a new requirement and assign it.
Problem-04
When I am checking in OV8Z (Check setting in Product Allocationu201D, the following comments appear. If anybody guide me on this basis I will be grateful to him.
u201CProd.alloc.detmtn prod: PRODUCT Description: Various Items
  Use for following materials:
    1478
  Method:
    Cumulative check
      Step: 01 Description: First step Info struct.: S561
        Info struct.
          Planning version 000 is defined for info structure S561 .
          Periodicity M ( ) is set for info structure S561 .
        Update
          Updating is not defined for S561 at schedule line level!
          The update date is not permitted for S561 (permitted; MBDAT , WADAT , EDATU )!
          The period settings for info structure S561 agree
          The info structure is updated synchronously.
          Formula 146 is used for the order incoming quantity
          Not every characteristic has a formula
        Plng
          No allocation quantities have been defined for product allocation object MCA1 !
          End of allocation validity is always end of a period (PRODUCT ,01 ).
          The product allocation objects are entered in the planning hierarchy.u201D
Problem-05
Where should I put the quantity because when I am creating Sales Order no Product Allocation function is working.
Problem-06
I have used Transaction code MC8A for creating Planning type but every time I put some value and save but after that in change mode I am not finding those values.
Regards,
Jans

Hi Lakshmpathi,
Please help me in solving these problems,
Thanks,
Jans

Similar Messages

  • Leading zeros in the Product allocation characteristic combinations.

    Hi All,
    I am copying Characteristic combination from planning area to product allocation group, after i complete the transaction system is automatically preceding the zeroes to the product number.
    I have one the following activities before copying CVC of planning area to product allocation group.
    against all the Product allocation settings.
    2.Created the MPOS with product (characteristic length of Product is 18), Customer and Allocation object.
    3.Created planning area and planning book.
    4.Copied cvc combination from planning are to product allocation group and also copied planning area values in to Product allocation group.
    5.Tried to check in the ATP simulation mode, while I was doing system has given no characteristic combination found, when I checked Product is preceding zeros as per the filed MATNR length 40 and this MATNR is selected from the Product allocation field catalog, But when I add zeros to product system is performing Product allocations in simulation mode.
    6.Tried triggering gATP Product allocations by creating Order in ECC, here also it has given same error No characteristic combination exists.
    When I did initial R&D on this. I found that material number in the product allocation characteristic combination is leading by zeros for ex:- 000000000000000002200325.
    Could any one please suggest me what to do on this.
    Thanks and Regards,
    T.Muthyalappa

    Hi Muthyalappa ,
    If i have understood your question properly , then my guess is you should be facing this problem only for numeric material codes. Try out the following things
    1. Execute the same test condition for a non numeric material. I believe it will work perfectly .
    2. For numeric material codes it is not working because of the difference in MATNR length between ECC and APO. In ECC the maximum possible MATNR length is 18 char whereas it is 40 chars in APO. So as per std SAP functionality the numeric materials get concatenated with leading zeros when you try to transfer it (or carry out any kind of processing ) from ECC to APO.
    ex consider material 12345. In ECC it will be stored internally as 13 leading zero's followed by12345 . But in APO it will be stored as 35 leading zero's followed by 12345.  Your issue is the system does not recognize the CVC that has this material as characteristic. At the time of cvc creation / change make sure your material characteristic ( especially for numeric material codes) totally has 40 chars . Pack it with leading zeros and make the material length 40.
    Try this out and update me .
    Thanks
    Saradha

  • Check the Product Allocation Settings - /SAPAPO/ATPCQ_CHECK

    Hello,
    I have an issue when I use the Check the Product Allocation Settings (TCODE: /SAPAPO/ATPCQ_CHECK), the system returns ''SYST: Period 000 is not valid in financial year variant J1''. J1 is my calendar and I using this calendar for all another Product Allocation Groups whitout erros. I just have this information by system report.
    I sincerely don't no why some groups have this issue because all groups are using the same setup.
    Anybody have any ideia?
    Thanks,
    -Ralph

    Hi Santosh,
    First thank you for help me, following your instructions I have made a investigation and now I know thatu2019s
    another team doing a test with this calendar in R/3, for FI, and really have differences between systems. Your direction are correctly.
    Thank you very much!
    Ralph Veiga

  • How is the product allocation  work?

    How is the product allocation  works? (material master: Basic Data 1,) where is the place to maintain the parameters?
    point will given

    Product Allocation
    Configuration Overview; Allocation Specific Usage
    1.Allocation Procedure (OV1Z) The product allocation procedure is the parent of the entire allocation process. All materials that are to be included in the allocation scheme are required to have an allocation procedure assigned to it in the material master. In addition, as of release 4.0, it is in the procedure that the method of allocation is defined. The user has the opportunity to set an indicator to identify their choice of two different methods (discrete and cumulative allocation) to evaluate the quantities to be considered for product allocation.
    2.Allocation Object (OV2Z) The allocation object is the root level of the allocation process where actual data is entered and planned in LIS. The object allows the user to further break down a procedure into smaller parts for future validation of components comprising a specific material
    3.Allocation Hierarchy Mapping (OV3Z) Primarily, this transaction permits the assignment of an allocation procedure to an LIS information structure. Secondly, a character is assigned to the information structure to permit collective planning. Finally, the user can assign a step level to the procedure and information structure to sequence the order in which allocation quantities are checked. This functionality allows the user the opportunity to check product allocation against several product allocation scenarios, before the required quantity is confirmed
    4.Define Consumption Periods (OV5Z) The allocation consumption periods functionality is only valid if the allocation method flag has been set (OV1Z). If you have de-selected the method field, this functionality is not available. The consumption window indicates the number of past and future periods to be used in the allocation check.
    5.Control Product Allocation (OV4Z) In order for the allocation process to function properly, allocation control records are created primarily to map allocation procedure steps to their corresponding objects so that the allocation data records can be located for validation. Secondly, validity periods must be established to indicate when the allocation control records are active. Finally, the user has the option of establishing a conversion factor per allocation control record to accommodate BOM listings of constrained materials
    6.Activate Allocation for Requirement Class (OVZ0) In order to turn on allocation in the standard order processing functionality, the requirements class must have a flag indicating that allocation is relevant.
    7.Activate Allocation for Schedule Line Category (OVZ8) In order to turn on allocation in the standard order processing functionality, the schedule line must have a flag indicating that allocation is relevant
    8.Create Planning Hierarchy (MC61) In order to adequately establish allocation quantities, the user must initially determine the level at which the allocation is to take place and the aggregation factor of the allocation quantities. In this step, the levels for the collective allocation search procedure are also identified.
    9.Generate Masking Character (OV7Z) Upon completion of the level determination for the planning hierarchy, the collective allocation masking character must be generated to allow aggregation indicators to be established. This transaction simply reads the hierarchy established in the planning table and then generates a collective mask character for each level of the hierarchy
    10.Modify Planning Hierarchy (MC62) This step is a repeat of MC61 where the initial hierarchy was established. In order to complete the hierarchical set up, the collective allocation (mask character) hierarchy must now be maintained with the appropriate aggregation factors
    11.Allocation Procedure Assignment to Material Master (MM02) At the root level of the allocation process are the materials. Each material that is to be considered in allocation scenario must be mapped to an allocation procedure. In order entry, then, when a material is entered with a valid allocation procedure in the material master, the allocation data is verified prior to confirming the line item ordered
    12.List of Suitable Structures (OV9Z) This report is used to identify potential LIS information structures that can be used in the product allocation process. This report simply reads through the data dictionary and selects all the active information structures that contain the field product allocation object (KONOB) as the first field. This data can then be utilized in the mapping transaction (OV3Z) to link the allocation procedure step to an information structure (previous step).
    Regards
    Jitesh

  • Unable to confirm quantity on the sales order --- Product allocation issue

    The following configuration steps were completed in the APO system.
    1.     Maintain Product allocation object
    2.     Maintain Product allocation group
    3.     Maintain Product allocation procedure
    4.     Create planning object structure with the necessary characteristics
    5.     Maintain characteristic combination
    6.     Create Planning area with necessary key figures
    7.     Create Planning book and data view
    8.     Maintain connection to planning area
    9.     Generate Product allocation group objects
    10.     Generate characteristic combination from planning area
    11.     Allocate the stock for the CVC combination
    12.                 Assigned the product allocation group to the APO product
    Regardless of quantity in the planning book, it is confirming all the quantity on the ECC sales order. This is due to the material availability date being pushed out to 12/31/2011 which seems to be the last date of the planning area time series. The values on the planning book were maintained online (manual step).
    Also when I run the simulation of product allocation under GATP>Reporting>Product allocation,
    For the product allocation group and the combinations that I have, I get the message "No allocations defined for the current characteristic combination"
    Any help would be greatly appreciated.
    Thanks
    Ashwin

    Dear Ashwin,
    I would recommend to use the transaction /SAPAPO/ATPQ_CHKUSG. Enter the PAL group and do the following:
    First: run the transaction with the 3rd option. Select all assignments found by the report then press the button delete with incoming order qty -> this deletes all assignments without any order number                                                                               
    Second: run the transaction again with the 1st option. Select all entries. press the button "merge PAL assignments", press button execute, choose on the first popup "yes" and on the second popup "no"  -> this should correct the shortages.                                                                               
    Check the note 676128 to get further information about the //ATPQ_CHKUSG and the options.                                             
    I hope this helps.
    Regards,
    Tibor

  • Restrict Product Allocation if Planned order is not getting created

    Hello All,
    We have a scenario that when ever a Sales Order is getting created, Product allocation assignment will be done automatically and planned orders will be created for that requirement in APO.
    There are some cases where in because of wrong Variant Configuration, Planned orders wont be created. Our requirement is to delete the Product Allocation automatically or to stop the product allocation assignment if the planned orders are not created.
    Do we have any standard setting for doing so or Kindly suggest me some BADI's which can be used for it.
    Thanks in advance.
    Best Regards,
    Srinivas.D

    Srinivas,
    A rather odd requirement.
    Have you tried in SCM APO 'Maintain check instructions' to perform the product check first, then allocation?  I would think that if the product check failed, then allocation would not be consulted, and no allocation therefore assigned.
    IMG > APO > GATP > General Settings > Maintain check instructions
    Best Regards,
    DB49

  • Adding new field to product allocation catalog?

    We are configuring product allocations in SCM 7.0 and have a requirement to add a new field to the standard field catalog for the allocations check.  We have followed the procedure outlined by SAP to add our new field to the structure /SAPAPO/KOMGOZ, add the field to the field catalog, and copied the source code to ERP.
    The issue that we are having is that new custom field that we added to the field catalog is not being populated when we execute /SAPAPO/ATPQ_PAREA_K - Characteristics Combinations from Planning Area.  The product allocations group that is being used in /SAPAPO/ATPQ_PAREA_K has three characteristics. The first two which are SAP provided fields are being populated correctly, but the last custom field we added to the field catalog is not. It is just blank.
    Is there a step that we missed during the configuation.  We are only using this field for the product allocations check (we do not use Rules Based ATP).

    Hi Arnel,
    I was expecting with examples but anyway.
    consider the examples of your CVC
    Country Region brand SO DV DC mat plant  etc...
    now you want to first get confirmation on SO and DV  , Prd allo group with these 2 characteristics
    same goes for all other combinations.
    now if you want to go with Either Or   /And.. decides if you need to go with one product allocation procedure with many prod allocation group  /or/ a sequence product allocation procedure.
    Its very straight forward as such... if you come up with examples, i can give better details.
    Looking at point 3 it looks like you want to go with 'OR' so you will have to go with sequence.
    (tcode: /SAPAPO/ATPCQ_GENER)-  is to check the customizing,  sometime you might move the Prod allocation from dev system and just to make sure there is no issue in transport /missing config.. it will check with transaction code.  I don't think you have to run this every time. After every transport..may be you have too as a caution check.
    Imp:  just to check @ different levels i dont think you will have to create different planning area.  If all the characteristics on which you want to (combinations) is available in one planning area , you should be good with one planning area only.
    Hope this is helpful.  I would suggest to follow what we have discussed so far and then you can create another message after the configuration/approach you finalized  with new issues/concerns you will be facing.
    If issue are really bothering you much, you can reach out to me directly. Let me know
    Pravin M

  • Product allocation is not working after setting all required config!

    Hello SD gurus,  Would you please help me to resolve this issue?
    I followed and configured all the required steps for product allocation  in ECC 6.0 Version still  the product allocation is not working as expected.
    Here are the steps performed
    1. Created procedure through OV1Z
    Maintained Product allocation procedureT.code OV1Z
    2.  Maintain product allocation object Transaction code: OV2Z
    3.   Create required info structure as per requirement T.code MC21
    4. Specify Hierarchy and Define the “Product allocation planning structure”
    Transaction code: OV3Z
    5.Define Consumption periods
    6. Control product allocation
    T. code: OV4Z
    Selected the product allocation procedure and given the required criteria and assigned to Info. Structure S991. Activated ‘Requirement category’ for product allocation
    8. T.code OVZ0
    Activate schedule line category for product allocation
    S991 Info structure Planning parameters updated
    Mc7F
    Create update
    T.code MC24
    Activate the update
    T.code OMO1
    Create planning Hierarchy
    T.code: MC61/62
    Maintain planning type
    . T.Code: MC8A/B
    Created the product allocation plan for required quantity  through MC94 IN spite of reserving stock as shown against the product allocation material specific and customer specific product allocation is not  worked and the regular Atp check allocated stock to some other customer when created  SO.
    Thanks for your help in advance
    Srini

    Hi Sumitra,
    Thanks a lot for your quick response!
    Actually to say availability check is working but not product allocation.
    I checked the settings in Material master MRP 3 view for strategy group  and it is 40.
    Availability check is 02 assigned. OVZ9 settings are assigned correctly 02-A- SD Order.
    Not knowing what is preventing to reserve the stock against product allocation!
    Do you or any one know where to see the product allocation stock?
    Best Regards& Thanks a lot for your help!
    Srini

  • Product allocation error while creating a sales order

    Hi Gurus,
    My client is using the availability check against  product allocation functionality in sales order.while I am creating the sales order and entering the material system is throwing the error message product allocation XXX is invalid,after pressing the enter button system has thrown another error "incorrect index structure for table XMVERF_POS/000010" and unable to save the order.
    I have checked the material master and the product allocation is assigned in basic data 1 view,I have also checked the IMG settings it has maintained and assigned to infostructure.Please let me know is there any config settings are missing related to product allocation.
    Regards,
    hari challa.

    Please check if storage location is populated for the material. Also may be this material is a non-stock material and not relevant for storage location check.. If you have any non-stock items in your order and if you are populating the storage location in the order automatically, then this happens. Please check your code and bypass the check for non stock items.
    Hope this helps
    Regards
    Sai

  • Product Allocation in OM17

    Hi Experts
    I am new to APO GATP.We have implemented GATP Basic methods product availabilty check and allocation check in our project.
    When i run OM17 for product allocations we are getting following inconsistencies:
    000     Shortage of incoming orders quantity     @5F\QNo long text exists@     ZCS_S999     32oyIy8a043X0000meaTaW     12.04.2010     18.04.2010     0     0     1,222     1,222
    When i run correct inconsistencies , inconsistencies are not getting removed.following message is prompting:
    Message Number: /SAPAPO/OM_SYNC082
    Diagnosis
    The incoming orders quantity in liveCache could not be adjusted using product allocation assignment. This can have a number of causes. Check the following causes and try again:
    Procedure
    Check:
    If the planning area to be adjusted is locked
    If the time series are initialized (after liveCache has been initialized)
    If all characteristics combinations exist in the planning area
    1)What is the problem and why i am getting this error message?
    2) How to remove or resolve the above inconsistency?
    Regards
    Vicky

    Hi Senthil
    Thanks for your reply.
    When i run OM17 for product allocations we are getting following inconsistencies:
    000 Shortage of incoming orders quantity @5F\QNo long text exists@ ZCS_S999 32oyIy8a043X0000meaTaW 12.04.2010 18.04.2010 0 0 1,222 1,222
    1) Based on the planning object number(32oyIy8a043X0000meaTaW) from om17, i went to the transaction /SAPAPO/ATPQ_CHKCHAR - Characteristic Combinations  and i dont find the characteristic value combination of the Planning Object Number.
    2) I ran the transaction /SAPAPO/ATPQ_CHKUSG - Product Allocation Assignment Check  based on the product allocation group and planning object number (32oyIy8a043X0000meaTaW ) with Assignment w/o order quantity i found it with red lght.
    1) Check whether if the allocation group is used in several product allocation steps. (We are using only single product allocation step )
    2) Check the product allocation procedure is maintained correctly( Yes its maintained correctly)
    3) Check whether any lock created in planning area(How and where to check this )
    4) Check whether the planning area is initialised(yes Planning area is intialized )
    5) Run /SAPAPO/TSCONS and check for any errors(No errors)
    6) Run /SAPAPO/ATPQ_CHKUSG and look for any errors
    (I ran the transaction /SAPAPO/ATPQ_CHKUSG - Product Allocation Assignment Check  based on the product allocation group and planning object number (32oyIy8a043X0000meaTaW ) with Assignment w/o order quantity i found planning object number with red colour.I dont understand what need to done in this transaction. I tried to delete but Delete option is greyed Out)
    What would be the reason for this error?
    How to resolve this inconsistency?
    Regards
    Vicky
    Edited by: vicky999 on Jun 24, 2010 4:17 PM

  • Issue with Product Allocation Scenario

    I am Trying out Product Allocation in APO (SCM 5.0).
    Relevant setup in SPRO - Product Allocation Object, Group, Procedure, Sequence etc., Planning Object Structure, Planning Area, CVC generation, Connection between Planning Area and Product Allocation object in GATP, assignment in Location Product Master (at Customer Location) Product Allocation Procedure, Check mode, ATP Group has been done in APO.
    After entering data in appropriate keyfigures (Allocated Qty) it shows up under GATP>> Reporting >> Product Allocations >> Time Series per CVC
    Have carried out ATP Simulation to check that for a given product at Customer the Product Allocation against a Required Quantity takes place correctly.
    Now trying to carry out the Product Allocation check by creating a Sales Order in ECC. In that case during the material availability check screen in APO, the product allocation does not show up.
    I believe it is related to master data settings for the product in ECC. My questions are as follows:
    1. In ECC the product exists at the manufacturing plant only (and not at customer as in APO). There in MRP3 tab Strategy Group is maintained. Is this along with Availability Check field responsible for determining the check instruction (combination of check mode + business event) in APO for the Product Allocation check.
    2. If so (which I guess it is) I can see the check instruction picked up in APO while creation of sales order in ECC is different from the check instruction I ran simulation with. How can I ensure the same check instruction is chosen (in which case I believe the availability check result will be same as the ATP Simulation carried out in APO).
    3. In APO I ran simulation for the product at customer location (and maintained the required ATP settings in the product master). In case of Sales Order creation in ECC how does system pick up the Check Mode and Business Event for the product (having Sold-to as customer and Supply Plant as the plant code) and use it in APO.
    4. Any other setting/configuration that is missed causing this behaviour.
    I guess some of the questions is a bit hazy but I would appreciate if someone can outline the Product Allocation Scenario. I am trying out based on Building Block S59 Demand Planning for Product Allocation but of course it does not detail out enough.
    Disclaimer: My knowledge of GATP is almost nil but am exploring.
    Thanks,
    Somnath

    Hi Somnath,
    It will be a pleasure to help you out.
    Firstly I will list out all the steps which I can think of:
    (1) R3-You have moved all the ATP customizing from R3 to APO via ATP integration model.
    (2) APO- goto SPRO>APO>GATP>General Settings>Maintain Check Instructions
    Here go to Check Mode- 041 and Business Event- A and maintain the following settings manually in development and migrate it all the way to Production
    I am assuming here that you want to first do an allocation check and then availability check**
    Product Allocation: Change from NO CHECK to First Check
    Product Check: Change from First Check to Second Check
    This check mode and business event is the most common one which is triggered while placing a sales order
    See the following blog for DETERMINATION OF CHECK MODE
    http://solution-timezone-issue.blogspot.com/
    There might be other check modes( 030, 050) which might also require this change. However you can judge that while placing a sales order and when you go to the availability screen, You have the tab - SCOPE OF CHECK CONTROL where you can see the Check Mode + Business Event
    Following guidelines can be used to modify Check Instrctions after Customizing Import from R/3 –
    1.     Business Event A*  is Sales Order Entry (The main scope of GATP) so define check instructions for all check modes since it is not possible to identify the requirement class that may come over on an order. For Business Event A* if availability check was being done in R3, then define check instructions with Allocation as first step, then Availability check as second step. Else if no availablity check in R3 then define check instructions with no availability and no allocation checks.
    2.     Business Event B* is  normally for deliveries but is also required for Rush Sales Orders. An R/3 configuration showed that 041 is the only requirement class that will come across for this business event. Hence defined only for 041 check mode. For Business Event B* if availability check was being done in R3, then define check instructions with Allocation as first step, then Availability check as second step. Else if no availablity check in R3 then define check instructions with no availability and no allocation checks.
    3.     Business Event 03 required for Inventory Transaction availability check such as MB1C. For such transactions, the APO Product Master Check Mode is used. Hence check instructions for all Check Modes are maintained. For Business Event 03 if availability check was being done in R3, then define check instructions with Availability check as first step. Else if no availablity check in R3 then define check instructions with no availability checks.
    (3) Maintain the Product Alllocation Procedure:
    <b>a-</b> Create a Product Alloc Object -- Example: PAO-001
    In this step, we define the product allocations objects - product allocations are saved per object for a characteristics combination in the product allocation group.
      Product Allocation Procedures can be used to maintain different Product Allocation Objects for different time validity periods.
      Generally Product Allocation Objects are used to model the different ‘reasons’ for the need for allocation – material shortage, capacity constraint, etc.
    <b>b-</b> Product Alloc Group--PAO-1234
    A product allocation group defines a group of characteristics against which allocation checking is done.
       Creating a Product Allocation Group creates a characteristics directory in the APO database and an area in Live Cache where the key figures are maintained.
       If ‘Check Planning Area’ is set to No then allocation and incoming order quantitiy data can be seen in table /SAPAPO/QTTAB. If the ‘Check Planning Area’ is set to Yes then no data is stored in this table and the allocation check is done directly against the data in the Planning area.
       Detials of allocationconsumption by sales orders are maintained in table /SAPAPO/QTVB in APO and in QTVB in R/3.
      If ‘Check Planning Area’ is set to ‘Yes’ and if there are users are in the change mode in the Planning Book, Sales Order Entry can get locked out.
      If ‘Check Planning Area’ is initially set to yes and then deactivated later you will no longer see data in /SAPAPO/AC42.
    Settings:
    Check Planning Area – Yes. The reason being that users are not expected to lock planning books as they would be defaulted into the display mode (through a development object). Also most allocation uploads will be through batch jobs. Setting it to ‘Yes’ reduces one step of moving data between the planning area and the allocation group.
    Check Date - Material Availability Date. Consumption of allocation quantity and checking of available allocation quantities is determined by the check date.
    Time Bucket Profile – Week
    Characteristics – Product Allocation Object (1), Product (2), Plant(3), Customer(4)
    Consumption Period – Bwd Consumption 1  
    Meaning that first the order will consume from current week allocation and then go 1 week backward to consume.
    <b>c-</b> Product Allocation Procedure --- PAO-4567
    Step Sequence:
    <i>Step</i> -
    <i>Step Name-</i> -
    Prod Alloc Group -
    Wild card
    1                      First Step             PAO-1234                     9
    <i>Alloc Procudure</i> - PAO-4567
    <i>Prod Alloc Step</i> -1
    <i>Control</i>
    <i>Valid from -
    Valid to---- -
    Object -
    Active -
    Factor</i>
                            12/31/2037      PAO-001    Check the Box                  1
    <b>d-</b> Maintain Connection to Planning Area (APO) 
    In this step, we maintain the assignment of the planning area to the product allocation group. We must make this assignment because characteristics of the product allocation group have different names from the info objects of the planning area.
      All characteristics of a product allocation group must be assigned to an info object. But multiple info objects can be assigned to one info object. It is not always necessary to assign every info object to a characteristic. It is possible for aggregation and disaggregation (depending on the direction of transfer) to take place with info objects that are not assigned.
    <i>Product Alloc Group -
    Planning Area -
    Version -
    Time Buckets</i>
    PAO-1234                         xxxxx                     000             W
    <i>Characteristic</i>
    KONOB - Prod Alloc Obj
    MATNR --- Material
    WERK -
    Plant
    XXXXX---- Customer
    <i>Key Figures</i>
    Order Qty - AMENGE
    Alloc Qty - KCQTY
    <b>e-</b>  Check the Product Alloc Settings
    This is only a check- Everything should be green and OK .
    (4) You have planned the Characteristic Combination on which you want to do ALLOCATION.
    <b>Create a new POS-</b> Which has your chracateristics as PRODUCT, PLANT,CUSTOMER, Product Alloc Object ( 9AKONOB)
    <b>Planning Area,-</b> Key figures required are Alloc Qty, Order Qty( Sales Order Qty)
    <b>PLannig Book, Data View</b> which has the following characteristics- Product, PLant
    Assuming you are allocating at the following CVC level- Product, PLant,Customer
    Step 1:
    /n/sapapo/MC62-Create Time Series- Basicallly your CVCs -
    Example: Product 1234, Plant INDIA, CUstomer WALKART
    Step 2:
    Move Characteristic Values Combination to Allocation Group (APO) 
    /SAPAPO/ATPQ_PAREA_K
    INput :
    Planning Area: xxxx
    Prod Alloc Group: PAO-1234
    (5) In the INtegration MOdel - Activate the ATP CHECK Integration model for the Plant and material
    THis is the KEY which decides whether availability should be done in R3 or APO
    Material Active in the integration model -- Means Availability( GLOBAL AVAILABILITY: Prod Alloc+Prod Availability) is done in APO
    Material not active in the integration model --- Means Availability Check is done in R3
    (6) APO MASTER DATA SETTINGS:
    Material Master:  On the ATP Tab, Assign Loc Dep Procedure ( Prod Alloc Procedure)
    Location Master: Calendar Tab> Create a shipping time stream calendar
    Additional Info: Please contact your R3-SD people as this involves a lot of understanding and I have not listed all the details here.
    This config shown here is a very basic one which not even 25% of the companies might be using.
    If you have any questions on this part- please see my business card and email me**
    (7) SCHEDULING: This is a major task which determines the route and transit times for calculating the
    Material Availability date
    Goods Issue Date
    Delivery Date
    on the sales order line item- schedule line
    I dont know whether you need info on this**There are many ways of doing this
    a- Configurable Scheduling
    b- COndition records
    c- User Exit
    You can find documentation in SPRO or else let me know*
    For simplicity- Let me take the easiest to create and difficult to maintain master data- Condition Records
    Step1 --Define Field Catalog for Condition Table (APO) 
    /SAPCND/AU01
    Require Plant and Route defined here in the field catalog
    Step 2- Define Condition Table for Scheduling (APO) 
    /SAPCND/AU03
    Create a new table- 901
    901 -  Pick Time based on Route with key as Route
    902- Route Time based on route
    Step 3- Maintain Access for Scheduling (APO) 
    /SAPCND/AU07
    Take the important ones- PICK and TRAN
    I am assuming again as I dont know what kind of Scheduling is maintained on R3 Side. Mostly 80% companies have only two lead times- Pick and Route Transit time.**
    PICK- Select pick and click on accesses > <i>Acno</i>-10-- <i>Table</i>-901
             >> Then save it > and go in again
    Select PICK and click on Fields> A popup will appear > Enter the access sequence as PICK--- Enter the access as 10  and click on the GREEn ARROW and save it
    TRAN- Select TRAN and click on accesses > <i>Acno</i>-10-- <i>Table</i>-902
             >> Then save it > and go in again
    Select TRAN and click on Fields> A popup will appear > Enter the access sequence as TRAN--- Enter the access as 10  and click on the GREEn ARROW and save it
    Now coming to maintaining the Condition records in APO EASY ACCESS
    /SAPCND/AU11
    Create  SCheduling Step for PICK : Enter condition type- PICK
    <i>Enter Route</i>- USCAN --- <i>Duration</i> -24:00 (Hrs)
    Create  SCheduling Step for TRAN: Enter condition type- TRAN
    <i>Enter Route</i>- USCAN --- <i>Duration</i> -48:00 (Hrs)
    Now Let me answer your questions:
    (1) Question 1- <i>In ECC the product exists at the manufacturing plant only (and not at customer as in APO).</i>     
    I did not undertsand what you mean here. As we can create a Material at the following locations in APO( Dist Center(DC), Manu Plant(PL), Cusomter, Vendor, etc)
    For GATP all we need is the material at a PLant location
    STrategy Group on MRP3 tab: This is purely used for determining the CHECK MODE value on APO Product Master.
    When this is blank on R3, the check mode will be blank on APO.
    However SAP recommends Putting in a strategy group value on R3 Material Master
    or
    a default Check MOde value for all those Products who have blank check mode-   041 is the best value * This piece SAP hasnt recommended but I found that there is No harm in anyway and it is MANDATORYfor inventory transactions like GOODS ISSUE otherwise you will get a QUEUE in SYSFAIL **
    Even if this is blank this has no effect on the GLOBAL ATP as the Check mode for a SD transaction is determined as follows
    98% of the SD transactions will generate a CHeck mode of 041 and Business Event- A ***
    Through the item category and the MRP type in the MRP view
    The item category is derived from the item category group in the Sales view of the material master record and from the order type of the sales document. Together with the MRP type in the MRP view of the material master record, the item category determines what requirements type is selected. The advantage of this method is that the selection of the requirements type depends on the business process (such as quotation, sales order, or repair).
    (2) Question 2 - I guess now you must have understood why when you do a simulation in APO, it is taking the Check mode from APO product Master
    and when you do a ATP Check from R3, the check mode(041) is different
    You dont need to ensure that they are the same- It doesnt matter in anyway.
    (3) Question 3- <i>In APO I ran simulation for the product at customer location (and maintained the required ATP settings in the product master).</i>I
    When you run ATP simulation- AC04, you generally run it for the plant as that is the supplying location and not the customer.
    <i>In case of Sales Order creation in ECC how does system pick up the Check Mode and Business Event for the product (having Sold-to as customer and Supply Plant as the plant code) and use it in APO.</i>
    PLease look above for this answer.
    (4) Question 4 - <i>Any other setting/configuration that is missed causing this behaviour.</i>
    To my best knowledge, whatever I could remember I have listed out. However there are some more steps which might be needed.
    Follow all the steps as I have mentioned and whenever you get struck somewhere, shoot me a message and I will help you.
    ONe more pointer here to what you have mentioned
    Relevant setup in SPRO - Product Allocation Object, Group, Procedure, Sequence etc., Planning Object Structure, Planning Area, CVC generation, Connection between Planning Area and Product Allocation object in GATP, assignment in Location Product Master (at Customer Location) Product Allocation Procedure, Check mode, ATP Group has been done in APO.
    After entering data in appropriate keyfigures (Allocated Qty) it shows up under GATP>> Reporting >> Product Allocations >> Time Series per CVC
    <u><i>Have carried out ATP Simulation to check that for a given product at Customer the Product Allocation against a Required Quantity takes place correctly.</i></u>
    Somnath, I believe you might have a wrong picture here. The concept of allocation is  Controlling Supply against huge Demand which is in this case coming from SALES ORDER
    When you place a sales order, the supplying location is your plant and that is where you would like to put in allocation quantities
    Say for example for a material 12345 - You have stock of 100 Qty in Plant KING fo this week and it shows as follows in the planning book
    Customers say are WALKART, GE-FUG, MACROGUN
    The CVCs which we have to create are as follows
    Similar to Demand PLanning**
    Material 12345 -PLant KING-Cust WALKART-Prod Alloc Obj
    Material 12345 -PLant KING-Cust GE-FUG-Prod Alloc Obj
    Material 12345 -PLant KING-Cust MACROGUN-Prod Alloc Obj
    And this is how it appears in the planing book when you go into DETAILS ALL
    You basically enter the Allocation Quantities just as how you enter forecast quantities in DP Book*
                            Wk1   |  WK2     WK3   WK4  WK5
    Alloc Qty                     |
    Material 12345                |
    Plant KING                    |
    Cust WALKART            50    |
    Cust GE-FUG             30    |
    Cust MACROGUN           20    |
    Incoming Order Qty               |
    Material 12345                   |
    Plant KING                       |
    Cust WALKART           <u>50</u>|
    Cust GE-FUG            <u>25</u> |
    Cust MACROGUN          <u>20</u> |
    <u>50</u> : Say the Cust WALKART has ordered 250 for this week, however only the allocated quantity -50 will be confirmed for him and the remaining 200 qty will be confirme at a later week when he is given the allocated amount.
    <u>25</u> :Similarily say this customer GE-FUG has ordered 20 qty. So his remaining allocation is basically 5 which cannot be used by any other customer.
    <u>20</u> : Say this customer MACROGUN has ordered exactly the allocated amount of 20. So his remaining allocation will be 0.
    This is the basic idea of how Allocation Concept is used in GATP.
    Ofcourse you can add the other functionalities like
    Rules Based ATP(LOcation Substitution, Product Substitution)
    Multi ATP( BOM-COmponents)
    Check Aginst Forecast
    Etc Etc
    Like any other module of SAP- this module has much to offer which unfortunately I cannot list here**
    GOOD LUCK and let me know If you need additional help.
    Regards
    KUMAR AYYAGARI
    Message was edited by:
            Kumar P Ayyagari

  • Global ATP with product allocations and SD returns

    Dear all,
    We have  been setting up an implementation scenario with an ECC 6.0 and SCM 5.0 system which verifies SD orders versus SCM product allocations.
    With SD orders and SD contracts everything works fine. But we have a problem with using SD returns (same material and plant used like the SD orders): We would expect the system also to check the returns for product allocation quantities but it seems that the SCM availability check does not enter the product allocation procedure at all (we have some user-exits in use but these are only accessed when we go via SD orders, no access at all for SD returns).
    Is there any special setting which we have to activate in order to have the SD returns properly processed with product allocations? (Customizing "Set the Transfer of Returns to SAP APO" within ECC is activated) The system somewhere gets stuck during the check within the SCM system.
    Thanks for providing assistance regarding this matter.
    Kind regards,
    Klemens

    Hi folks, did you resolve your issue here? I assume what you are wanting is for the Returns order to free up allocations qtys that had previously been consumed by the originating sales order, that is, incoming orders qty should be reduced by the amount of the returns order. I know that when a sales order line item is rejected the incoming order qty is reduced, but I'm not sure it is possible for a returns order to do this.
    ATP Man, are you saying that as category BZ is not supported by Allocations that it is therefore not possible for the Incoming Orders Qty to be reduced  by a Returns Order? I have a business reequirement to do exactly that.
    If it is not possible to do this through the automatically via the ATP check, the only way I can think to address this, would be to try and transfer the Returns qty to SCM after the order is saved and then to have a macro that reads the returns qty and reduces the Incoming Orders qty by the qty of the return.
    Paul.

  • ATP control in ABAP code, product allocation

    Hello,
    Scenario is like this:
    I am creating sales order for 10 PC of material. Material is fully available on unrestricted stock but product allocation is allowing me to use only 3 PC of material.
    Question:
    I am searching for ABAP code which tells me what is the reason of 'incomplete' availability control?
    So in other words I would like to know (in ABAP) whether the quantity is blocked due to the product allocation or due to the stock shortage.
    Regards,
    Piotr

    Hi,
    Please check the below code, MODULE should be in between Loop and End loop.
    PROCESS BEFORE OUTPUT.
    LOOP AT ITAB WITH CONTROL EMPTABLE CURSOR EMPTABLE-CURRENT_LINE.
       MODULE STATUS_0001.
    ENDLOOP.
    PROCESS AFTER INPUT.
    MODULE USER_COMMAND_0001.
    LOOP AT ITAB.
    ENDLOOP.
    Thanks,
    Sriram.

  • Third Party Drop ship and availability check against Product Allocations.

    Dear All -
    We are facing a situation where we need to create a third party drop ship Sales Order with an item category which still reaches out to APO and confirms against the product allocation quantities. This is not supported by standard SAP.
    Has anyone come across such a requirement and how has it been handled. I would really appreciate any suggestions.
    Regards
    Mandar

    Vladimir,
    I want the drop ship in which when you create SO, before selecting the vendor, system should perform availability check for plants. If material is not available in the plants ( nearest plant) then system should select the vendor who will ship the material to customer directly.
    _pat

  • Bypassing  product allocation procedure

    hi my requirement is that based on the delivery priority ( for sales order or stock transport order) , i need to bypass the product allocation procedure.
    i also know the name of enhancement names.
    however i cannot find which transaction code do i need to refer to on scm side ?
    is this automatically done via cif , or do u need to specifically execute transaction on scm side ?
    the exits given to me are on apo side , however i not able to find a transaction to trigger it ?
    where can i find the technical name for this delivery priority field ?

    Why dont you change the Check mode in AVAILABILITY_CHECK on R/3 side and send it through field catlog and drive different chek instructions in APO to not do Prod allocation chk?

Maybe you are looking for

  • How to erase a dead Time Machine: Necessary? If so, how?

    Are Time Capsule Time Machine backups encrypted by default, and if not, how can I erase the Time Capsule if the power supply is dead? Details: I bought one of the early Time Capsules (1 GB) two years ago, and it finally died. It just wouldn't light u

  • Problem with  AT command in LOOP

    Hi Experts, here i ve a problem like, in my table there are 3 PSPHI(projects) values, if i loop n calculate the sum it is getting total amt for 3 PSPHI values, but i want every end of PSPHI i need sum. the below code is working fine if there is no AT

  • Import data in user define table through DTW.

    Hi experts, Can any one tell me how can i import data from excle in User define tables through DTW. Is any other way/tool avaliable to import data from excel sheet to User define tables BR, Hari

  • How to access SAP Discovery system V4

    Hi, Can anone accessed SAP Discovery system V4? if so how to get the SAP discovery system server details and log-in credentials? Thanks, Sivapratap

  • Header conditions in purchase order.

    Hi experts, I want to omit the header and item conditions for a purchase order with document type 'CS', I mean I want to that purchase order doesn't have conditions when I check it in transaction me23 or the condition value be zerou2026. Does anybody