Component change in respective BOM

Hi All,
I have situation, one raw material used in 10 diff BOMs, but now i want to replace this component by other,
Is there is any mass transaction to amke this replacement effective.
Thanks
Regards

Hi,
Yuo can try here CS20 mass changes in BOM  .Where you can change material ..
Just try it.
Regards
SANIL

Similar Messages

  • BOM Component changes when changes done in VC

    Hi All,
    When ever we are changing the characteristic values in Variant configuration, it result the component changes in the BOM.
    Please any body let us know how to find the what are the component changes in the BOM when we change any characteristic value in VC. Is there any FM or it will store in any table?
    Regards,
    Vasu.

    Sure Vasu,
    Find explanation on  this as below :
    BOM components are selected by making use of a special type of dependency called SELCETION CONDITIONS.
    If you want to find which BOM components will be selected on selecting which characteristic value, then follow the below given procedure :
    1. goto T.Code CS03.
    2.enter BOM header name , plant etc. and press enter.
    3. now you are in inside BOM.
    4. Select any BOM component for which you want to check when will it be selected during configuration.
    5. then, in top menu , choose  Extra --> Object Dependencies --> Assignments
    6. It will display all Object Dependencies assigned to that BOM component.
    7. Select the Dependency with type Selection Condition.
    8. Click on Dependency editor.
    9. It will show you the Dependency code
    10. when the condition as per this code is satisfied, the component is selected during configuration.
    Please revert back if you have any doubt.
    Reward Points.
    Regards,
    Gaurav Raghav.

  • Component changes when changes done in VC

    Hi All,
    When ever we are changing the characteristic values in Variant configuration, it result the component changes in the BOM.
    Please any body let us know how to find the what are the component changes in the BOM when we change any characteristic value in VC. Is there any FM or it will store in any table?
    Regards,
    Vasu.

    Hi Anji,
    Thanks for your reply.
    The above FMs are returning only the characteristic changes. But i need to to find the Changed Components in BOM if the characteristic value changes. Plese give any other FM if you are having.
    Regards,
    Vasu.

  • Mass component change in BOM

    hi
    i want to  mass change some components in BOM. For example in the BOM i have 10 components. Now i want to change 5 components in the BOM
    I have around 500 FG How to do that? Is it possible in LSMW?. or CS20?

    It is better to go for getting a BDC developed for all the mass changes in the BOM.
    Using CS20 you can only change a single component and replace with a new material. I think BDC is the best alternative.
    Hope this helps you.

  • Edit or Change a Change Number in BOM

    Good Day
    Dear All
    Please can anyone can tell me is any process is there to Edit or change the CHANGE NO in BOM

    Hi Radhakrishna,
    Masters like BOM and Routing can be created and changed with change number. Accordingly changes can be tracked with respect to the change numbers. For Eg BOM created wit hqty 10 with change number X , then BOM changed to 12 with change number Y, then system will display the reports on BOM changes with respect to change numbers. Historial data you can track.
    You can create new change number in CC01 with different validity date and make changes to BOM. You cannot edit the change number once its is created.
    Have a look on the below doc posted by me on usage of revision level with change numbers.
    Usage of Revision Level for PP Masters -BOM and Routing
    Thanks & Regards,
    Ramagiri

  • Changes made in BOM are not reflected in Configurator.

    Hi all,
    When i update minimum and maximum quantities in BOM, the new values are not reflected in the configurator.
    I have found a patch (patch# 4410573) for this issue in metalink and applying that patch did not resolve the issue.
    I have logged an SR with Oracle for this and Oracle support have asked me to run "Refresh Single Configuration Model" concurrent program and see if the changes are reflected.
    This program has 2 parameters one for folder and the other for Configuration Model Id.
    When i try to run the program, for any of the folders, the value set for the parameter Configuration Model Id does not show any values and hence i am unable to run the program.
    We don't have a separate instance for COnfigurator.
    Do i need to do any set up so that my Configuration model is reflected in the LOV?
    Can anyone please help me on this?
    Oracle Apps version: 11.5.10.2
    Configuration software build: 11.5.10.25.43A
    Regards,
    Sreekanth

    Hi Jason,
    Please see my comments below
    Jason said*
    Support is correct. If you haven't run the Refresh a Single Configuration Model concurrent program for your model, then the new BOM attributes will not be visible in your model. Changes to items/BOMs are not directly reflected in the configuration model. You must "refresh" the model to see the changes.*
    Even without running the "Refresh a Single Configuration Model" concurrent program, in some scenarios, changes are being reflected in Configurator.
    Ex:
    When i change only minimum and maximum quantities, the changes i.e. new minimum and maximum values are not reflected in Configurator.
    But, when i also change any of the following fields along with minimum and maximum quantities, new values are being updated in Configurator with out running the refresh program.
    effectivity_date, disable_date, component_quantity, planning_factor, component_yield_factor and optional class
    Can you please explain this?
    Also, i have already tried executing the query by commenting the enclosing_folder check. But still, the query is not retrieving any records.
    Basically, the sub-query that fetches devl_project_id itself is not retrieving any records.
    Jason said:+
    Based on the SQL above, the only criteria for importing a model is that the item under the folder must be:+
    a. A Model (PRJ = Project)+
    b. The Model cannot be deleted (Deleted_flag must be '0')+
    c. And the model must have been imported from Oracle apps, e.g. it cannot be a non-BOM model (orig_sys_ref is not null)+
    Can you please tell how can i check whether model is imported into configurator or not and if it is imported from where is it imported?
    Regards,
    Sreekanth
    Edited by: Sreekanth Munagala on May 12, 2011 8:52 AM

  • How to see changes in all BOM" s under plant for a period ?

    Hi Gurus,
    i want to see the list BOM's which was changed with in period and the details of changes like Quanity and user names who have done the change.
    Regards,
    mahesh.

    HI Mangalraj,
    Thank You For the response, My Client Is asking For a report Where We can Get details Of BOM list under a plant which have Gone Under changes with in a specific Period. Plant level Of .
    Ex; in the plant 1111 we have some  200 no of  BOM s . some users have changed 30 different BOM in a Month. how can i get list of BOMs which gone under Change (Header and Item level) changes.
    i have taken  Plant wise BOM no and passed it to STPO and get the details , but in STKO the Fields are showing as CHANGEDBY, CHANGEDON,but i am not able find the changes happen.
    EX:  base quantity  of header material was changed from 1 to 2 by a abcd user in 01.01.2014.
    by using STKO we can see the user name and changed date but i am not able find the change details.
    Please help me how can i develop a report to extract data of BOM changes based on input of plant and date range.
    Thanks in Advance...........
    Regards,
    Mahesh.

  • Changes visible in BOM although ECM not released yet

    Hi,
    I have a BOM which has been updated together with a change number. The change number still has status "in work" and not released.
    When I go to CS03, with all dates removed on the selection screen, I see the changes in there with the change number. That is ok with me, because then I expect to also see future changes in the BOM.
    But when I go into CS03, with today's date in both date fields on the selection screen, I expect to see the old version of the BOM which should still be valid until the ECM is released. Not the changes done by this specific ECM. CS03 shows the BOM with the changes already in, and I think that is not correct. Why should the changes show when the ECM is not released?
    Is this behaviour SAP standard or could there be a mistake in the customizing of the ECM status?
    Any hint is useful.
    Thanks,

    Hi,
    Though the status is set as "in work", the changes will be effected based on the valid from date maintained in change master CC01. You can practise putting a imaginary future date like 02.10.3333 on the valid from date in change master and when the change to be released change the valid from date as required.
    You can also go through alternate date assignment in BOM.
    Regards,
    jyj9ja

  • Changes documents for BOM and Routing

    How Can I find the change documents for a BOM and routing?

    Change Documents For BOM
    CS80 - Material BOM
    CV80 - Document Structure
    IB80 - Equipment BOM
    IB81 - Functional Location BOM
    CS81 - Standard BOM
    CS82 - Order BOM
    CS83 - WBS BOM
    Change Documents for Routings
    CA60 - Task List Changes
    CA61 - Routing
    CA62 - Reference Operation Set
    CA63 - Rate Routing
    CA64 - Reference Rate Routing
    Hope the above may help you.

  • Add and edit BOM component in the Equi BOM using LSMW

    Hi All,
    I created a Batch input recording in LSMW to add BOM component in the Equi BOM (IB02). It is working fine. But my requirement is while adding it should check the material already available in the BOM, if not insert a new line or if it is there then it should only edit the quantity. Is it possible in LSMW?

    It is not possible with LSMW as it is an SAP standard program.
    To meet your requirment you can create an BDC with help of your ABAP team and in that program you can put all the mentioned conditions and requirement you want.
    hope your problem is resolved.

  • Substitute Component independent of the BOM

    Does Oracle have the concept of a substitute component, irrespective of the BOM in which it could exists?
    For example, Component A can always be replaced by Component B. This would be applicable to Product X or Product Y, both of them use Component A.
    Oracle seems to have the concept of a substitute component on a specific BOM (BOM_SUBSTITUTE_COMPONENTS).
    http://download-west.oracle.com/docs/cd/A60725_05/html/comnls/us/bom/bomtas05.htm
    Using this functionality, I would have to specify B as a substitute in two different BOMs - one for Product X, one for Product Y.
    I am wondering if there is a global "Subsititute Item/Component".
    Edited by: user8578890 on Feb 19, 2010 10:27 AM

    The substitute component relationship is used on Work orders and sales orders.
    And in both cases, you need a constrained ASCP plan to make use of the relationship.
    And no, there is no way in ASCP to globally subsitute A for B.

  • BAPI_ROUTING_CREATE problems with component  allocation of phantom BOMs

    I try to create a routing via the BAPI_ROUTING_CREATE and all works fine until I try to do component allocations for phantom BOM lines in the next level.
    In my simple BOM I have the following structure:
    00004465 (ROOT BOM)
    +
    +---Phantom_BOM_B (BOM 00004466)
        +
        +---Material_X
    +---Material_Y
    I only can allocation Material Y and BOM_B but I am not able to allocate the material X instead of the BOM_B, in that case I always get the message "The component to be assigned has not been completely specified".
    My COMPONENTALLOCATION Table Code:
    T_COM-SEQUENCE_NO = '000000'.
    T_COM-OPERATION_ID = '0010'.
    T_COM-BOM_TYPE = 'M'.
    T_COM-BOM_NO = '00004466'.
    T_COM-ALTERNATIVE_BOM = '01'.
    T_COM-ITEM_ID = '00000001'.
    T_COM-ITEM_NO = '0010'.
    T_COM-BACKFLUSH = 'X'.
    T_COM-PLANT = '1000'.
    T_COM-MATERIAL = ''.
    T_COM-BOM_TYPE_ROOT = 'M'.
    T_COM-BOM_NO_ROOT = '00004465'.
    T_COM-ALTERNATIVE_BOM_ROOT = '01'.
    *T_COM-PATH = '000001'.
    I hope some can help me to find me, a solution to solve my problem.
    Thanks
    Jörg

    Dear ,
    Phantom BOM means which you want to plan interm of Operation Hrs and Issue Componenets but not intereted to Physically Store  rather re-ssiue it to Main FG .
    Now ,from your requirement it s clear that BOM : 00004465(ROOT BOM) is for your FG (Let Say A) BOM :  00004466 is  a SFG (Let say B) as Root BOM component  , which is In House produced .
    Bascically , If you do not want to *Store B( Phantom BOM) *  but want plan the depedent of B ( X, Y , Z  etc )  along with A's dependent and also cost of B ( Phantom BOM )   , then the routing hrs /component along will be issued directly  to  A( Root BOM)  ,
    So you do not need to create Routing for Phatom BOM and also no componenet alocation required . Better ,  you can add that routing operation hrs to main routing of the FG .
    Hope this is clear
    regards
    JH

  • External component changed

    Hi all,
    Could anyone help me on this ?
    When opening this VI (see attachement) on one computer it says that the VI was changed (external component changed) and that I have to save it. When I save it and open the VI again on a second computer, LabView outputs the same message, an external component has changed... so I have to save it... Back on the frist computer same message again... etc...
    I still don't know what's the 'external component' that changes from one computer to another... and how to find it.
    Thanks in advance for any help or hint...
    Attachments:
    untitled.JPG ‏119 KB

    Ok, this is one of these VI's that have an external component changing...
    As I said Before, when I open this Vi in two different computers, LabView tels me each time that an external component has changed and that I have to save it. I don't know what is the external component changing... how to find it ?
    Thanks.
    Attachments:
    ADO Connection Open.vi ‏14 KB

  • CO02 component change log

    Dear experts,
    Are there any logs or change reports for the production order componenent changes such as adding a component, deleting a component or changing the quantitiy of component in CO02.

    Dear,
    In standard component change log is not available.
    In order to achieve for future record, implement the Note 390635 - Change documents for production and process order
    or activate OCM

  • BOM changes inputting the BOM component -reg

    Hi Friends,
    we would like to know the BOM quantity changes happened for a particular BOm component .
    Using CS80 we have to input BOM header to know BOm changes , but our requirement is for a BOM component what changes are made and when they are made .
    Our BOM component say a paint part number is used in many BOM headers
    it is not possible to see CS80 by inputting one by one  BOm header and check whether the BOM component quantity changes are there .
    instead we would like to input BOM component and know when and what changes are made to its quantity (menge) in what BOM header by which use
    please help
    regards,
    madhu Kiran

    Dear Madhu Kiran,
    This is possible only if you are using ECM - Engineering Change number and you can obtain the details
    from the tables STAS,STKO,MAST &STPO.
    Without ECM I dont think its traceable.
    Check & revert back.
    Regards
    Mangalraj.S