Hi,
We are having Process order Scenario & we watn following options.
1. Having 2-3 BOM of the same FERT/HALB with alternate Raw Materials.
2. Selection of Specific BOM for Process Order depending on the Availability / Requirement.
3. Creating Issue Slip / Reservation for the Specific BOM.
4. Issuing Material accordingly.
5. Booking consumption accordingly.
Thanks in advance.
DON
Dear
Please find below the answers of your question ;
1.Having 2-3 BOM of the same FERT/HALB with alternate Raw Materials. ; Goto CS01-Enter Plant-Enter Material -Enter Usage and List down all the items in frist Alternative .Again to create Alternative 2 and so on , you need to go CS02 with same menu path -System will automatically take the Alternative 2 or you can copy Alternative 1 if you have similar items with additional new items..
2. Selection of Specific BOM for Process Order depending on the Availability / Requirement ; As far as MRP is concern , BOM selection and explosion of BOM for depdent , needs to have BOM Selection methods Blank , 1,2,3 in MRP4 view .If you have maintained Producton version with all those aternative with proper validity and lot size , then MRP will explode as per lot size and valididrt depeding on the order qty or you can also create demand MD61 with Production Version based on the avalabity of BOM [MD61-Enter User parametes -Scheculie Tab -Goto Settings-Production Version -Enter PV with spefic BOM based on availablity ] and then run MRP in MD02-NETCH ,3,1,1,3,2 .Howver , you can also select this production version manually while creation of Process order based on the Order Type Depent Parameters in OPL8-Select Process Order Type-Goto Detals-Here Master data tab -Select Production Version -Keep it 1-Manula Selection .Remember , as sequence , MRP will select the frist PV listes in MRP4 view of Material master if it does not find proper lot size and validity.
3.Creating Issue Slip / Reservation for the Specific BOM. ; Generally , MMD/Store will be given Reservation Number and they will chekc in MB51 for open reservation for Goods Issue and carry out MIGO-261.Frosm Shop Fllor you can try Pick List or you can print Process Order Print out in COP1 or MD4C print out also .Otherwise develope customs Forms as per the information permissible from you business to store .
4. Issuing Material accordingly.; It will happen in MIGO-261 or automatcally based on Backflkashing in MRP2 view -Always back flash so that at the confirmation time in co15/c011 , you can automatically goods issue the material .
5.Booking consumption accordingly ; It is Process Order Cycle from Releasing of Process order to till Goos Recipt of Process Order in MIGO-101.You can also use Auto GR based on the Control Key set up in Master Recipe which triggers the Auto GR.
Regards
JH
Similar Messages
-
Missing raw material position (from BOM) in process order
Hello to all,
Please help me on my issue on missing raw material position (from BOM) in process order.
On transaction CS11, for a particular formula/plant/BOM application, the BOM was produced. It was found that this BOM has 20 positions (from 0010 to 0200).
Now, when the user proceed on the process order for this, the position 20 is missing into the order. What checks should be needed to proceed on checking why the item is missing into the process order?
Thanks.
Regards,
PatrickPatrick,
The last check what i would suggest is to check the "Plant-Spl- material status" of the material in line item 0020. You have to check this using transaction "MM03" and in MPR1 - view.
You can check the defination of the status in the customizing transaction "OMS4", here check under "Production Section".
I definately think that there was a error message which should have popped up and ignored by the user due to this defination of the status.
Regards,
Prasobh -
Setting for "Exploding BOM in Process order"
Hello All,
I have a requirement where I want to create BOM for sales order using CS61 and then I want to explode this BOM automatically in Process order(Production order) and it should happen automatically.Please let me know the settings for the same.
Regards,
RohitHi Subhro,
I thought you are talking about the BOM material for the ref technical object say functional location or equipment in the service order. If you have maintained the BOM for the equipment you can pull the all the component list in the component tab.
In the component tab click on the List button available in the component tab. You will see the list of BOM material.
DP -
Alternate BOM in Sales order?
HI Dears,
I am in a Pharma Company and i have one product with same raw material but in a diff. pack means i have a material said A with raw material AA & Packing Material BB and second one said A with raw material AA & Packing Material GG. {The product is same but in different pack (For Exam. : Paracetamol Tablet in 10x10 pack and 1000's pack)}
By useing Alternate BOM i creat the both products. But When i creat sales order (VA01) their are no any indication for alternate BOM (BOM version).
Please solve my problem as soon as .
Thanks
Sameer Kumar PradhanHi,
You cannot create alternate BOMs if your working with Order BOM in MTO scenario.
If you have created alternate BOMs in MTO scenario and wants to select this automatically from MRP then define prod version or selection criteria of BOMs in MRP4 view in Material master and please remember that 'Dont create any Order BOM from CS61".
If there is no order BOM created then MRP (MD50) selects the available Material BOMs. If order BOM is created then this only will be exploded from MRP.
regards
Tajuddin -
BOM explosion in process order
Dear PP experts
In my scenario, the sales order and process orders for the corresponding line items got generated by uploading some details of master contract through some Z code. The client provide me details regarding the BOM for the process orders from their third party software, which process through XI. I have to trigger that bom into process order. for that i first maintain the bom details in CS61 and then trigger the "Read Master Data" in process order manually. Now i have to do it automatically. means when the BOMvdata flows from third party software, it should get updated in cs61 and simontaneously "read master dat" should get triggered. how can i do this. please suggestHi,
Check for any BAPI / Function Module in SE37 which can fulfill your requirement.
Search BAPI with SAP component ---> PP option in search help(F4).
Regards,
Tejas -
Track Deleted BOM item in Process Order
Hi Guys,
I am facing one issue which is described as below.
when user is converting the Planned order into Process order at that time he has deleted 1 BOM item.
Now i he is saying that i have not deleted that item and after that he released and done the GI conf GR.
Now i want to track the change history but i am not able to find the changes done by him.
I have check so many blogs but i come to know that if he is deleting BOM item during creation we will not able to find.
Pls helpHi D R,
To the best of my knowledge at the time of creation if some component has been deleted, you can not track. Because up to that time table entry has not happened. After saving you can see the component.
If you have some existing process order which is without item deletion, you can compare and check. As well Check the BOM in CS03 and check the BOM inside process order. You can easily find out the component.
Hope this clarifies and at per your requirement.
Success.
Regards,
Krishnendu. -
I want to create a Process Order without a BOM & Recipe . Is that Possible ?
I tried the following :
Material Master setting MRP 4 view -Explosion/Dependent Requirements section define " "(Blank) for Selection Method field
Order Type Dependent parameters (COR4)
Production Version Blank :
Recipe: Do not use Master Recipe
But the problem is that I cannot keep BOM application Blank
BOM application has the link for selection ID which is linked to BOM usage .
I am not able to bypass this check in any way & as a result it gives an error (No valid BOM) on Process order creation
Shall appreciate a responseHi,
Yes, it is possible to create process order without BOM & master recipe.
By having some config settings in place for BOM & recipe selection, you can create process order without BOM & recipe in SAP.
Normally, this scenario comes into picture where you're not sure about the operations to be carried out and materials to be consumed for an order.
For creating and testing such scenario, refer below SCN thread, which was discussed before,
Create Process order without Production Version | SCN
Regards,
Narresh -
Planned price in process order
Hi Gurus,
We have a problem with planned cost for the BOM in process order
We are not getting planned price for in-put materials, where as we are getting actual cost for the in-put materials
We have maintained price in material master.
Split valuation also maintained for the materials.
How to get the planned price for those in-puts.
please any body suggest me in this.
waiting for the reply
regards,
anand.MHi,
Please find the link
Difference between Planned cost..........
Thanks and regards
E.Rambabu -
BOM Explosion for Multiple Process Orders
Hi,
I hope someone can assist me with the following: Is there a report I can run or transaction I can do to have BOM explosion for multiple Process Orders? I would like to input process orders for a week and see the BOM details per PO.
ThanksDear Sukendar,
1.For this requirement you have to go for a Z report and you can give the Functional Spec's to prepare
this report to your ABAP consultant.Prepare the input format,logic of the program and the output format.
In the logic part you can make use of this Functional Modules's CSAP_MAT_BOM_READ or
CSEP_MAT_BOM_READ or CS_BOM_EXPLOSION or CS_BOM_EXPL_MAT_V2 .
2.Using CEWB helps you to identify all the material that's having the BOM,but here the report does not
shows you the level by level by BOM for a FERT.
Check and revert back.
Regards
Mangalraj.S -
Error for open process order when BOM alternative is not found
Dear colleagues,
When I open process order. BOM alternative is selected according to the production version. But when BOM alternative is not found system gives only information message and I can open process order, I want to prevent open process order when there is no BOM alternative according to the production version. Because the Bom can be deleted after creation production version.
Thanks for your helping,Hi,
U need to use an enhancement at the creation of order to check the active status of the bom and restricting the order creation when BOM status is inactive.
see whether following enhancement is useful for your scenario:
PPCO0006 Enhancement & EXIT_SAPLCOZF_003
Please confirm.
Regards
Suri -
Sale order bom can be used in to process order or not
To change the BOM for particular order items the sale order BOM can be created , to copy the sale order BOM into production order CO08 can be used , whether the process order can be created with ref to sale order any option is available is SAP
Hi,
There is no such transaction for process order with respect to Sale order.If planned order is created with respect to sale order after MRP,that can be converted to process order thorugh COR8 transaction.
try to explore COR8 transaction -
Need to show data related to Process order request , BOM in a smart form
Hi,
I need to show data related to
Process order request
BoM
Now in selection screen we are entering the followings.
Manufacturing Plant ,MRP Controller, Production scheduler, Order type , Order , Material, Sales order, WBS Element,Release,Scheduled start, Scheduled finish ,Selection profile.
how to get 1> Process Order number,Produced Material,Material Description,Print date,Narcotics indicator , Quantity produced , Phase number , Phase description ,Resource description,Standard value to show in a request form.
2> Item category ,Component code,Component description , Component quantity ,Component Unit of measure ,BoM base quantity.
Please help me how to get those values , what should be the aaproach , how to write the select quiry.
ThanksHi
To get BOM details, do the following:
1. Use the material number and goto Article to BOM link table (MAST) to get STLNR (BOM).
2. With this STLNR, goto STPO table (where STLNR is the key field). Here you will get all the BOM details like components (IDNRK), UoM (MEINS) etc....
Hope this helps.
THanks
Vijay
<b>PLZ REWARD POINTS IF HELPFUL</b> -
Process Order -Batch determination for a BOM material(same batch)
Hi Friends,
Thanks in advance.
Let us say, a material (ROH) has so many batches as A,B,C & D. Whenever we create a new process order, system has to pick only the particular batch( say -C here) in the process order BOM through batch determination. (during process order creation stage)
1.How to achieve the same ?
2. What are the ways are there to achieve the same ?
3.Is there any Exit for this?
Regards,
ManiHi Velmurugan & Vishwas,
Thnaks for your feed back.
1. Is there any other ways without batch classification ? ( Because there are so many material without MM-classification view.....and client wants without extending the Classification view for MM master as it suggests same batch for all GI for delivery & GR for purchase.....)...We want only for process order batch determination.....
2. Is there any exit for this ?
3. Is it possible through any kind of Characteristic assignment in the Sort sequence? How?
Regards,
Mani -
Process order creation with out BOM
Hi
I have an requirement...
material A is finished good
i create process order for material A
but i dont use BOM... with out BOM can i create process order .
after creating process order cani isuue components against order ? is it possible please can any one help me in this issue
but one condition : i craet process order material A 10 KG
for this FG i used components materia A used 8 kg and material B used 2 kg
is it possibel pls..could any one gude me in this issue
Regards
Sesimaterial A is finished good
i create process order for material A
but i dont use BOM... with out BOM can i create process order .
yes, You can create a orderwith out BOM
after creating process order cani isuue components against order ? is it possible please can any one help me in this issue
Yes, You can assign component manually in component overview screen or you can issue material directly for order with 261 movement, It will go to unplanned consumption
but one condition : i craet process order material A 10 KG*
for this FG i used components materia A used 8 kg and material B used 2 kg
In The component overview screen of process order assign the Material A with 8 kg ,
& material B as 2 KG
Regards,
Sundaresan
Edited by: Sundaresan . E. V on Oct 4, 2010 2:41 PM -
BOM component Qty is getting rounded to next value in Process Order and BOM
We are in ECC 6.0, and maintaining BOM where Item quantities are decimal places e.g 0.3lb with respect to Hader qty. Now when we are craeting process order or exploding in CS11, we are seein that item quantities are getting rounded to next full integer e.g 1, 2 or 3.
What could be the reason for this behaviour.In standard "lb' doesn't have decimal point
If you want decimal point
go to CUNI
select the mass
you can find the lb
maintain the decimal point as 3, & decimal point rounding as as 3, system will show 3 decimal point in process order and in CS11
Maybe you are looking for
-
ENT-06954: Error while Displaying BIBean for Cube/Dimension Dataviewer.
Hi all, I have defined a cube with three dimensions. All elements are deployed and the mappings is executed successfully. If I try to open the dataviewer either for the cube or for the dimensions I receive the following errors: ENT-06954: Error while
-
Error message given... cannot open itunes any more???
Hi I tried to reinstall itunes but now whenever I try to open or gain access to my itunes library it will not allow me? It gives me a screen where it asks if I want to "reinstall" or "repair" itunes, but whatever one of these options I choose I get a
-
in sap standards is their any specific report 1) how many cheque realized in bank 2) how many cheques deposited in bank 3) How many cheques is not realized in bank
-
Hi Brijesh, XI cannot access shared file drives. I.e. the directory for the files must be on the XI server. Furthermore check if XI (or better the XIUSER) has sufficient permissions to read resp. write the files from / to the directories. Regards, Pe
-
Compiz starting with GDM allowing multiple users
When i start compiz after login I've got slow GDM when changing user and white screen after second login. So there's no way to launch compiz and support two different sessions? Or can I start compiz together with gdm and not individually for each use