Config for Cost & budgeting at activity level and WBS element level in PS

Dear GURU's,
please suggest me how to do the spro configuration for budgeting and costing, here my requirement is I need to do cost planning and budgeting at WBS element level and Activity level. We two deferent types of projects.
Regards,
Bha

Hi Bhanu,
Cost planning in projects can be done through two techinques:
I.  Manual cost planning (at WBS level)
1.  Overall planning (Struture-oreiented planning)
2.  Detailed planning (Cost element planning)
3.  Unit costing
4.  Easy cost planning form
II.  Automatic cost planning using networks and assigned orders
For customizing:  Use transaction OPUV  and enter the required entries for cost planning.
Budget can do only at WBS level.  For configuration do the following steps:
1.  Create Budget profile - OPS9
2.  Assign Budget profile in Project profile - OPSA
3.  Then allot budget to your project - CJ30
hope it will be very clear.  Appreciate with point if it useful.
Thanks and Regards
vetrivelan

Similar Messages

  • How to do budgeting at activity level and WBS element level in project syst

    Dear GURU's,
    Can any one please suggest me how to do budgeting at activity level and WBS element level in project systems, friends please I required set by step process.
    I need how to do this configuration to map this scenario.
    Regards,
    Bhanu

    Hi Bhanu,
    Use this link :
    http://help.sap.com/saphelp_45b/helpdata/en/86/98853478616434e10000009b38f83b/frameset.htm
    after page opens , click on BUDGET MANAGEMENT , There you will find each and every step you want .
    Thanks ,
    Dhruv Kumar Malhotra

  • Table for Cost Center and WBS Element.

    Hi Experts,
    i done the creation of Servcie Contract with account assignment category as Cost Centre "K"  & Project "P". Now i'm trying to take the report for this document.
    Plz help me, in which table the Cost center data and WBS Element data is stored.
    Regards,
    sudhakar

    hi!
    check the table T163K and the field is KNTTP.
    Reward if useful.
    Yuvi.

  • Report Painter Request - Cost Center and WBS Element

    Hi Everyone,
    Currently, my company settles all project related expenses through to a cost center by way of an internal settlement cost element (category 21).  The issue with this is that when the expense gets to the cost center, they lose all visability as to where the expense originated, such as salaries or travel expense (category 1 cost elements).  We can't switch the settlements to the originating cost element from wbs to cost center just because of the additional data/volume that will cause.  My thought was to create a report painter that can run by cost center but also show the wbs's that settle to that cost center and group the expenses by primary cost element (cat 1).  I'm assuming that there is a way to marry a cost center and wbs element by way of the wbs settlement rule but how would that be done for reporting purposes?  I've seen it done before by way of a nightly job that created sets based on the combination of cost center and wbs but I'm not sure how that was done.  Any advise and examples?
    Example:
    Cost Center:  IT
    WBS: A.0017.01.01 (settles to cost center IT)
    Postings made:
    1.  CC IT and CE 552000 "salaries"..............................$20,000
    2.  WBS A.0017.01.01 and CE 552000 "salaries"........... $5,000
    3.  Settlement of WBS to CC (expenses flow through to CC IT by way of CE 985000)
    I want to run CC IT and see that the account 552000 really shows $25,000 and can be broken down by cost object (CC and WBS by the amounts above)
    Thanks,
    Pete

    Hi Peter,
    I had a similar requirement and used report painter report group 1SHK-002 (in library 1VK).
    I took a copy of the standard and ameneded it slightly, I switched the explode so it occured on the cost center not cost element.
    The report runs so that direct costs on the cost center are shown at primary cost level. And values settled to the cost center are shown on the partner object. In your case i guess WBS Elements (Partner ObjType WBS).
    Now in my case I didnt need cost element breakdown on partner level, just on cost center so effectively I have(sorry for text alignment but I hope you get the idea):
    GL1   .............  100
    GL2   .............  250
    + Cost center1 total ....350
    GL3 .............   50
    GL4 ............. 100
    + Cost center2 total.... 150
    Primary Cost Total ..... 500
    X-YZ-1.200 .............   50
    X-YZ-1.400 ............. 100
    + WBS total ............. 150
    IO 1............. 100
    IO 2  ............. 100
    +IO total  ............. 200
    Partner Total............. 350
    Overall total .............  850.
    Its not exactly like your requirement but it might be a good report for you to work with to get what you need.
    Elaine

  • Valuation at plant level and company code level

    Hi,
    Can someone explain me the difference between the valuation at plant level and company code level with a real world example?
    Regards,
    Malsha Kalubowila

    Hi,
    Inventory can be valuated at two levels either at company code level or at plant level. If you select valuation at company code level, all materials across all the plants will have same material price since valuation is at only company code level.
    Say for example Company code 1000 is buying a material which unit price is Rs. 10 from a vendor who supplies to two different plant A & B of company code 1000.  Assume Plant A is situated near vendor premises itself (so freight cost is Re 1 extra)  whereas plant B is situated at far away from vendor place (so freight cost rs 2 extra) and both cases freight cost is borne by the company and not by vendor.
    Assuming you have selected valuation at plant level, now in plant A same material will be valauted at Rs. 11 (10 +1) whereas at plant B it is valuated at Rs. 12 (10+2).
    Whereas if you have selected valuation at company code level, price will not be valuated at plant level rather at company code level which will get updated at moving average price in this case.
    So it is always best practice to select valuation at plant level rather than at company code level.
    Reg
    Karthikeyan G

  • Can Budget Availability Control be turned off at WBS elements Level?

    For Project and WBS elements, we activate the budget  availability control in the budget profile and assign the budget profile to the Project. So once we budget one WBS elements under that project and release the project, the availability control is active for all WBS elemens under this project.
    My question is whether we can turn off the availability control for one WBS element under that Project and let the availability control on for the other WBS elements under that project.
    thanks,
    Ting

    Hi,
    I doubt if this can happen. CJBW will deactivate avalability control for entire project. Try OPSX for that particular WBS, it will reset budgeted status. Not sure if this will help, try and confirm.
    One more way could be assigning userstatus to the WBS and restricting 'Availablity control' by that status. This option looks more practical.
    Regards
    Edited by: Shrikant Rakate on Sep 10, 2008 9:21 AM

  • Availability check box at schedule line level and requirement class level

    Hi All
    What is the significance of availability check field at schedule line level and requirement type level.
    If I remove the check box at schedule line level, then there won't be any availability check carried out in the sales order, even though in requirement class it is checked. Is it for doing availability once the requirement is passed to MRP...
    In make to stock scenario, no availability check is active at schedule line level.
    scenario 1. stock is 0 in plant, when i place an order for 10 quantity, does system give any confirmed quantity on so and so date...or the confirmed quantity will be zero or as there is no availability check carried out, it confirms 10 quantity on customer requested delivery date and the time of creation of delivery, it gives an error message stating zero quantity is available. which one is correct in all the above.
    In make to order scenario, no availability check is active at schedule line level.
    order was created for 10 qty, as there is no availability check active, does the system give some date based on the lead times maintained in the material master or not?
    Regards
    Sree

    Hi sreekar
    The significance of availability check at schedule line level  is to determine weather availability check and TOR should be carried out for sales orders  or not. 
    If you remove check box at schedule line level , availability check and TOR wont be  carried out at sales order level.
    Coming to the scenario you said , make to stock , i think the availability check you are using is 01 make it 02. which is planned requirements. and stratergy group as 10. in MRP3 view in MMR. .
    as the availability check u have put 01 & stratergy group as 10 availability check doesnt carry
    coming to the scenario 2  , if the stock is 0 in plant and if you create a sales order, then the confirmed quantity should be 0 and that particular order will go to backorder processing.
    sometimes it  confirms the ordered quantity as the  confirmed qunatity, and it gives a confiremed delivery date on which the stock is confirmed , but that date is a tentative date.
    all these unconfirmed orders will go to backorders. once the qunatity is confirmed automatically , delivery date also will be done
    Coming to scenario 3 , when you create MTO order there will be availability check checked at the schedule line level. can you tell wat is the schedule line you are getting is it CP or ND?
    for schedule lines , ND - no availability check will be there , PD - availability check will be there
    Note: plz check 1st the availability check you have entered in MMR , if it  is 01 make it as 02. and then run these cycles.
    Reward points if useful and if Any queries let me know
    Regards
    Srinath
    Edited by: sri nath on Mar 21, 2008 7:53 PM

  • Mismatch in InStock Quantity in Item Master at Item level and W/H Level

    Hi,
          All,
                I get some mismatch in 'InStock Quantity' at Item level and W/H Level, in Item Master.
               for Some Item and mismatch increases day by day.
    ex:          At one total item Instock Qty : 100
                   but in W/H 1 InStock Qty :   -80
                   in W/H2  InStock Qty :   -2
    Please give me reason for such a problem and also, solution to overcome this problem
    Thanks
    Vivek Kumar Gaurav

    Dear Gordon,
    Thanks for replying me.Yes,there are multiple add-ons are running on client. There is no work done with SAP inventory. So you can consider that it's a problem of vanilla SAP B1.
    Warm Regards
    Vivek Kumar Gaurav

  • Enhancement for project definition and WBS element.

    Hi Experts,
    I have a client requirement for creation of the custom specific fields for the project definition and the WBS element level called IT relevant and they need to use this fields for the purpose of structured reporting in PS.Can you please guide me as to how do in need to do this.
    When i go in to the transaction CMOD and SAP Program SAPMSMOD it says you are not authorised.Please let me know the process as to how it has to be done.
    Thanks for your cooperation.
    Shivkumar

    Refer the IMG documentation against the SPRO node 'Create Customer-Specific Fields in a Project Definition' and 'Create Customer-Specific Fields in a WBS'.
    Regards
    Sreenivas

  • How to make mandatory(usr01) field for level 1 wbs elements only from CJ20N

    Dear All,
    I have made mandatory for "PRPS-USR01" field from CJ20N transaction
    by using field exit. But mandatory field (usr01) is working for all wbs elements. I want to make this usr01 field mandatory for  LEVEL 1(prps-stufe), WBS ELEMENTS(prps-posid) only. Not for level 2 and level 3 wbs elements. Please let me know how to fix it.
    urgent.
    Regards,
    Karthik.

    You could envisage the use of validation rules in PS.
    Transaction OPSI or SPRO
    Create a validation with a message ID (Z)
    Create a step
    - prerequisite : PRPS-STUFE = '001'
    - Check : PRPS-USR01 <> ' '
    affect a message number
    Regards.

  • Link between Cost element GL Account and WBS element.

    Hi,
    I want to get the List of all dollars sitting on the GL account  attached to the selected WBS element.
    For this, Any one please suggest me the table where i can get the link between the WBS element and GL account.
    or
    Table for link between the Cost element and GL account
    and Table for link between the Cost element and WBS element.
    Thanks,
    Suresh.

    Hi,
    1. There is no link between cost element and WBS
    2. Link between cost element and G/L account is one-to-one. This means, that if it's a primary cost element it has the same code as the G/L account. If it's a secondary element, no link exists.
    3. The table where you can see the postings on your WBS is COEP. There you will find the cost element, WBS, amounts, etc.
    Regards,
    Eli

  • Check on level of WBS element for capital purchase PO

    Hi Experts,
    We are facing a problem. While creating Capital purchase PO, all WBS elements are allowed. Although, system is configured in such a way that GRN can not be done for Level 1 WBS( Parent project). We want to introduce a check at PO creation level only, so that it should not take Level 1 WBS element. How can it be done( validation check can do here or not) .

    How did you set up the derivation rule???
    I think  that is where you specify a level of expenditue or  procurement.
    Thanks

  • Grey field for project definition and WBS element

    Dear all,
    I have created a project and WBS element in CJ01. Now I go via CJ02 to the change mode and the project ID and WBS element ID is not greyed out. But I would like that the system shows these key fields as not changeable anymore, only fields like description should be changable. Can you please tell me, which customizing step I missed to get the grey field for project ID/WBS element ID?
    FYI  I do not use a project mask to create the project.
    Thanks for your answer.
    Heidi

    Hi Heidi ,
    I don't think you can grey out the Project Definition and the WBS Element fields after the creation .
    If you want to restrict the users to change the Proj definition and WBS , a better way is through
    Authorization objects and restricting only specified users to change the WBS
    Kish

  • Assign WBS AVAC not in the lowest level of WBS elements

    Dear SAP Community,
    Our client has requirement to have budget availability control in WBS element level 3 while the WBS structure is until level 5 and the actual posting will occurred in WBS element level 5.
    Our current setting is to have WBS element level 5 as Planning Element and Account Assignment Element. So, user can upload their WBS planning data from the lowest level of WBS structure. Then we copy the Planning Data as Budget through CJ30 and release it through CJ32.
    If we set the value of Budget Data in CJ30 and CJ32 until the level 5, the system check AVAC in WBS level 5 instead of the amount rolled up in WBS level 3. If we set the value of Budget Data in CJ30 and CJ32 in WBS level 3, the system will check AVAC in WBS level 3 (as we expected) but the consequence is comparison of actual vs budget in WBS level 5 will have variance 100%.
    Is there any way to define the budget data until WBS level 5 but the AVAC control is in WBS level 3?
    Appreciate your inputs
    Thank you and best regards,
    Fitria

    Hi,
    >If we set the value of Budget Data in CJ30 and CJ32 in WBS level 3, the system will check AVAC in WBS level 3 (as we >expected) but the consequence is comparison of actual vs budget in WBS level 5 will have variance 100%.
    We had similar kind of requirement, we had followed the above process. THis will provide the required functionality except the variance in reports. Try and convince the client to settle for this if this meets your requirements.
    As AVAC  can't be managed at WBS levels.
    Regards,
    Harsh.

  • Creation of project definition and wbs element

    I want creation of project definition and wbs element upto 4 level using bapis.
    i am using transaction cj27,cj01,cj02
    which function module to use for this??

    Hi,
    to create project definition with customer fields the BAPI you should use is : BAPI_BUS2001_CREATE
    to create WBS elements with different levels and specific fields the BAPI you should use is BAPI_BUS2054_CREATE_MULTI
    these bapi must be used in the sequence of call :
    BAPI_PS_INITIALIZATION
    BAPI_BUS2001_CREATE / BAPI_BUS2054_CREATE_MULTI
    BAPI_PS_PRECOMMIT
    BAPI_TRANSACTION_COMMIT
    before using the bapi, you must apply OSS note :
    637345 - Syntax error with enhanced PS tables
    i sent you the oss note to your mail
    please reward points if helpfull.