Configuration of calibration process

sir i am new in sap pm.my boss given me a task that how to configure a calibration process in sap pm.i have seen on scn or google but i didn't get any document related to that please help me to configure a calibration process in sap.if you have any pdf or doc file then please share it to me.

Hi
It is a Huge data but Inshort I can tell you
1.Create Equipment using IE01
2.Create task list in IA01/IA05
3.Create Maintainance plan using IP01
schedule the equipment in the same with fix cycle.
4.Schedule through IP30.
Also In customization against PM order define the Inspection lot origin 14
After scheduling Inspec lot of 14 will be created
Then Do RR & DR
This is how it will be used
REgrads
Sujit

Similar Messages

  • QM & PM Calibration Process Configuration

    Hi
    I wanted to configure a calibration process. I have made the settings for PM and QM integration but unfortunately in our implementation QM is not in scope but I need to do the QM settings which will be required for calibration. Can anyone provide me a configuration document for calibration process which contains the settings for QM as well as for PM.
    Thanks a lot for help.
    Thanks & Regards
    Vineet

    Dear  Vineet,
    In  QM SPRO you have to assign  inspection type 14which is for  inspection in plant maintenance. Also you have to maintain number  range for this. most of  work in calibration  belongs to PM only.
    Following is the flow:
    1) IE01 : Create test quuipment.
    2) QDV1: Create sampling procedure for plant mentenance.
    3) IP42 : Create maintenance plan for equipment.
    4) IA01 : Create equipment task list.
    5) IP02 : Assign task list to maintenance plan.
    6) IP10 : Schedule  maintenance plan.
    6) IP30 : Deadline monitoring of maintenance plan.
    7) IP24 : Viewing schedule for calibration with order released.
    8) QE71 / QE53 : Calibration Result recording  and UD.
    This is the way i have mapped  the  calibration process.
    Hope this will help you.
    BR
    Shekhar

  • How to maintain calibration process in qm

    sir,
    i am new in qm module n and i m going to implement for qm module.
    so pl tell how i maintain qm configuration data n calibration process of qm.

    Hi
    It is a Huge data but Inshort I can tell you
    1.Create Equipment using IE01
    2.Create task list in IA01/IA05
    3.Create Maintainance plan using IP01
    schedule the equipment in the same with fix cycle.
    4.Schedule through IP30.
    Also In customization against PM order define the Inspection lot origin 14
    After scheduling Inspec lot of 14 will be created
    Then Do RR & DR
    This is how it will be used
    REgrads
    Sujit

  • Is it possible to configure Team calibration for Objective Setting Appraisals in EHP7

    Hi Friends,
    We are on EHP7. We have implemented objective setting appraisal for our client.
    We have created an appraisal template under category group "Personnel appraisals". We have configured the VA, VB, VC, Column ids.  Status tab flow is used from In preparation - Completed.
    The enhancements are used to accommodate customer specific calculations for the scores based on the final ratings.
    An additional requirement from the client is; once the appraisal process is over for a team; the team manager should be able to see the scores of his direct reportees in the MSS.
    1) He should be given a provision to modify the final rating score; incase if he finds that one of the team members deserve a better score in line with the comparison of other team members. He should be able to call the template and be able to revise the final ratings from his MSS directly.
    2) When he modifies the final ratings by calling the appraisal template on the MSS; that new score should be stored in the appraisal template (database tables); that is; this should overwrite the final scores which was initially calculated during the final appraisal discussion between the apprasier and appraisee. This new values should be taken for all reporting or new compensation revision process.
    Should this requirement be addressed by Assessment of Employees and Calibration Process for Employee Assessments standard configurations?
    If that is the option; I have already done these settings for flexible performance appraisal.
    But in the MSS > under Talent Management > Assessment
    We are getting a blank screen in the "In process & Completed " tabs. No employee is listed.
    The calibration grid is empty. But under under talent profile; we are able to see the names of the team members.
    Is there any other method available for this purpose ?
    Request your comments on options to deliver this functionality.
    Thanks.
    ER.

    Hi Srujan,
    For every paying company code you can have multiple sending company codes.
    You can make this configuration in FBZP > Paying company codes tab.
    Once in 'Paying company codes', here click on 'Company codes' button on top right.
    This means you will need all the FBZP setup for your paying company code only.
    Also, please refer to below link to configure cross company settings
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/90f33e12-aeac-2a10-2186-ed8301f778ba?QuickLink=index&overridelayout=true
    Also, this document will be useful:
    http://help.sap.com/printdocu/core/print46c/en/data/pdf/FIBP/FIBP.pdf
    Cheers,
    Zubin

  • Equipment calibration process

    Hi experts,
    in  equipment  calibration  process we have created a plan and scheduled.
    maintenance order with inspection lot created.Calibration completed and closed.
    But for the next calibration due date again we have to save the schedule (IP10)
    in order  to create maintenace order with inspection lot automatically by the system.
    is there any solution for this problem so that we don't have to save the schedule again and again to create maintenance order automatically ? Plz answer.

    When you create a maintenance plans for calibration in the third tab you will find sort field, define one sort field specific to calibration in configuration and attach it with your all calibration plans. Now after completing the calibration work don't forget to run the dead line monitoring program. Simple select the sort field and execute it will not take more than a min and all your next planned dates will be adjusted automatically
    Regards,
    EJ

  • How to configure  Oracle BPEL Process Manager for JBoss 4.2.1

    can any body help me to configure Oracle BPEL Process Manager for JBoss 4.2.1

    Look here:
    http://download.oracle.com/docs/cd/E10291_01/doc.1013/e10538/toc.htm
    Marc
    http://orasoa.blogspot.com

  • Configuring an Integration Process

    Hi All,
    Are there any good articles or weblogs explaining how to configure an integration process in the integration directory? I have an integration process which implements a sync-async bridge.
    Thanks,
    Sandeep

    Hi Sandeep,
    check this links, it should help you.
    This would help you with confgiguring BPM,
    /people/krishna.moorthyp/blog/2005/06/09/walkthrough-with-bpm
    This gives you info on SYNC-ASYNC Bridge, /people/sriram.vasudevan3/blog/2005/01/11/demonstrating-use-of-synchronous-asynchronous-bridge-to-integrate-synchronous-and-asynchronous-systems-using-ccbpm-in-sap-xi
    cheers,
    venk!

  • How to configure a status process

    I would like to configure a control process using a percentage bar for a VI

    Hello Novice Programmeur,
    The file that I sent to you, is a ".LLB" file : It allows to save all VIs, objects and external subroutines, excluding those in the folder vi.lib, to a library. It allows to save a hierarchy of VIs (Main VI and SubVIs) in one file. This kind of file can be open by LabVIEW.
    You will found in the attached zip file the same program with the main VI and SubVIs. Launch and execute the VI "ProgressBarExample".
    Best Regards,
    Sanaa TAZI
    National Instruments France
    Sanaa T.
    National Instruments France
    #adMrkt{text-align: center;font-size:11px; font-weight: bold;} #adMrkt a {text-decoration: none;} #adMrkt a:hover{font-size: 9px;} #adMrkt a span{display: none;} #adMrkt a:hover span{display: block;}
    >> http://www.nidays.fr/images/081110_ban_nidays09_468X60.gif
    Attachments:
    test.zip ‏54 KB

  • Fund management configuration and business process document

    hi,
    Can anyone provide me fund management configuration and business process document
    Mahendra M

    Hi,
    maybe this document will help you more:
    http://perlhosting.net/download/968192356.html
    SAP78V

  • Doubts on calibration process

    Hi,
    I AM DOING CALIBRATION PROCESS FOR THE FIRST TIME. The process i followed is:
    IE01:Equipment
    IP11: Maintainence Strategy
    IA05: Task List
    IP42: Maintainence Plan
    IP10: Scheduling Of plan
    IP30: Job Planning
    Above this i have assigned Inspection type 14 to PM order type for calibration.
    My doubt is:
    1) Is the process that I am following is correct.
    2) If yes, then after I schedule the orders by IP10, Do i need to relese the orders manually in IP10 or do the orders are made & released automatically when I execute IP30. Please let me know what is the process.
    3) If i reject the MIC in result recording does the order still get the status of TECO as it gets when i accept the UD.
    4) Do the maintainence orders get generated automatically after executing IP30 automatically.
    PLease respond, I will award points.
    Regards
    Ashish Khurna

    hi
    Following is the pre requisite for calibration orders.
    Maintain the inspection type 014 in customising (done by QM consultant)
    Assign Inspection type 014 to order type PM05 in customising.
    Maintaing the following master data:
    Create Master inspection charecteristics
    Maintain sampling procdedure
    Tasklist with inspection point as 300 for equipment
    Assign inspection charectersitics to operations
    Maintain catalogs for results recording / usage decision
    Create Maintenance Plan
    Schedule the maintenance plan
    Calibration orders would be generated
    release and inspection lt will be created
    Check through Tcode QA32 and process the inspection lot - results recording, usage decision
    Trust this may help you.
    Regards,
    E-Jad

  • How to Configure alert for process failures

    Hi Friends.
    How to Configure alert for process failures due to any reasons like mapping, runtime exceptions .
    I am devloping one scenario which is file to flatfile. In this scenario I am also using mail adapter for sending mail daily to admin that tells about record size and no of records parallely. I am not using BPM in this scenario.
    I am having very little experience in XI.
    Please answer this with clear steps so that I can do it.

    hi,
    check the links below for all the details and help on configuring alerts
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/9418d690-0201-0010-85bb-e9b2c1af895b - How to setup alerts for monitoring in XI 3.0
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/003de490-0201-0010-68a4-bf7a1e1fd3a5 - Monitoring in XI 3.0
    /people/michal.krawczyk2/blog/2005/09/09/xi-alerts--step-by-step - XI: Alerts configuration - Step by step
    /people/michal.krawczyk2/blog/2005/09/09/xi-alerts--troubleshooting-guide - XI: Alerts - Troubleshooting guide
    /people/bhavesh.kantilal/blog/2006/07/25/triggering-xi-alerts-from-a-user-defined-function
    /people/community.user/blog/2006/10/16/simple-steps-to-get-descriptive-alerts-from-bpm-in-xi

  • 'Cannot save the configuration.  Another process already wrote version 11.

    Hello:
    I shutdown the directory server 6.3.1 on Solaris 10, then modified the file dse.ldif by hand, then restarted the DS.
    Now whenever I try and make changes through startconsole it gives me an error. I have put back the *.startOK" file and even rebooted.
    I cannot seem to figure out how to correct this problem. Any ideas?
    WARNING 21 console hostname "The console caught exception: 'Cannot save the configuration. Another process already wrote version 11.' at 'SaveConfigurationTask:74'."
    Thanks

    Well I finally figured out a way to correct this problem. Not sure what caused it or if this is a good fix of not.
    But what i did was go into the DSCC
    selected my directory server and then chose the server configuration tab
    I then enabled a plugin, stopped/started and then disabled it, and then stopped/started.
    then i could make changes in my startconsole (isw settings)

  • How to configure advance payment process in sd and fi

    hi,
    sap gurus,
    how to configure advance payment process in sd an fi
    how it will trigger  from sd and fi.
    and the accounting entries is also needed
    plz help me on this
    regrds,
    balaji.t
    09990019711

    Hi
    As far as my knowledge goes, this has lot to do with FI configuration for Down payments.
    Regards
    Aravind
    Assign points if useful

  • Calibration process

    Dear Friends,
    I am new to SAP PM module. I wish to do calibration process by using measurement document. Hence I created measurement document for the respective equipment with the annual estimate and counter reading. I created the maintenance plan based on counter and schedule it. While scheduling , notification has been created in the background and from that notification I wish to create calibration order. At that time of creation, the information in the notification copied to the order but the information regarding maintenance plan alone has not copiied into the order. Therefore, while releasing the order inspection lot has created in the background but there is no characteristics attached to the lot. So I can't do the result recording for the particular lot.
    Can any one solve this issue?
    Regards
    Karthik

    Hi Karthik,
                     I guess that you have posted the thread in the wrong Forum,
    any ways the key to the Calibration Process is the Task List that you have to define in the Maintenance Order,
    you need to define the Inspection point in the Task List as 300, then the system will give you another Tab in the Operations as the Master Inspection Characteristics.
    there you give in your MIC no.
    can you please tell me in detail where you are getting Stuck ?
    Regards,
    Yawar Khan

  • Dynamic configuration in integration process using abap mapping

    Hi everybody,
    i have the following scenario:
    file adapter -> integration process -> file adapter
    The integration process uses an ABAP mapping and sets the filename in dynamic configuration as follows:
    *-- Set Parameter
        clear ls_dyn_record.
        ls_dyn_record-name      = gc_dyn_config_name.
        ls_dyn_record-namespace = gc_dyn_config_ns.
        ls_dyn_record-value     = <new_file_name>
    *-- Write configuration
        ir_dyn_config->add_record( ls_dyn_record ).
    But now the new filename is not reflected in the file adapter (receiver). In the integration monitor (SXMB_MONI) i still find the old filename.
    Whats wrong?
    Elko

    The ABAP mapping is more complex, setting filename in Dyn. Conf. is just one step in mapping.
    If I check the Workflow protocol of the Integration Process, I find the following in the Trace of the ABAP-Mapping:
    The filename has been set to 3233340.SWNF00HW.P10I. The Suffix P10I has been added in the ABAP mapping.
    When I check the subsequent message in SXMB_MONI I find:
    The added suffix is missing in the filename !!
    Elko

Maybe you are looking for

  • Saving a file in the same location as run .jar

    I have been playing around with an auto updating client for a project I am working on. I have been able to get the client to update fine and save a copy of the new client into where ever the original was run from using the below code: File file; Code

  • SQL Query doubt

    Hi, I have a Customer info table Table1 it has the following fields apart from many other fields like cust account info. Account_number Tax_id Tax_ID_format (this field has values S, T and the column is NUllable. I need to find all the tax ids that h

  • Statistical posting to Internal order and Cost center while real to PSG

    Dear SAP Gurus, There is a requirement is to post statistical posting to Cost center and IO while real posting to PA. I tested and found that I can have only either of Cost center or IO as statistical receiver. Is this standard behaviour or some erro

  • Import book from iPhoto into aperture

    hi, i would like to create a book in iPhoto and then tweak it in aperture. i want to do this because A: aperture doesn't offer the same themes...(if i could share/import the theme then that would also solve the problem). B: iphoto doesn't have the sa

  • Error in downloading data from R3

    Hi Experts, I am having one z program having alv grid display. there is one field of order(aufnr) in the output. While downloading data to desktop in excel format last character of the order is getting deleted. e.g. if order is 14001090931 then it is