Hi Experts
Please help me. I want to configure Unplanned Delivery Cost hit Price Diff. G/L account right now its hit Martial A/c. Please let me know where I can do that. 
Thanks & Regards,
Hemant Maurya

Hi Kiran,
Thanks for your reply. In my system we have not maintained any G/L Code in OBYC  Unplanned Delivery Cost (UPF). Then what will I do? Please let me know.
Rgds,
Hemant

Similar Messages

  • Unplanned delivery cost account assignment

    Dear Friends,
    I have configure the transaction key UPF in obyc. Here I have entered Inc/Dec account, but during the MIR7 Simulation, The Unplanned delivery cost is hitting Inventory Account of material.
    Can You please suggest, where the issue may be and how to resolve it.
    Rgds, Kraheja.

    Hi,
    Check the settings in the below mention path
    SPRO--  MM -- Invoice Verification --- Logistics Invoice Verification -- Incoming Invoice --Configure How Unplanned Delivery Costs Are Posted Assign 2 against your company code. It will help you to post in another line item
    reagrds

  • Unplanned delivery costs requirements in MIRO

    hello,
    at present we are using sap ecc 6.0. While doing MIRO at present, the Unplanned delivery cost are taxed. Client has the requirement that they should have options to choose whether they should tax or not tax the unplanned delivery costs. is there a way to give them this option.
    Edited by: soumyaps on Feb 10, 2011 10:35 AM

    Hello,,
    Sometimes, during the creation of a PO, we will not be knowing the actual Delivery / Freight Costs to enter in the PO. This will be known or available at the time of Goods Receipt. At that time we may have to change the PO and enter the Freight and then do the GR. Some times if already some GRs are made for a PO and for the latest delivery the Freight Vendor has charged some amount then changing the PO option also will not be correct.
    During these situations we can use the Unplanned Delivery Charges in MIRO and enter the amount and post it
    Check this answered links
    Re: Unplanned delivery costs
    MIRO unplanned delivery costs.
    Re: unplanned delivery cost - miro
    Re: configure Unplanned Delivery Cost Account
    Regards
    Mahesh Naik.

  • Unplanned delivery cost picking rounding off value in sap miro

    Dear Experts,
    I have configured unplanned delivery costs to be posted to separate GL account. I have set the default tax code also. In OBYC i have set the frieght and transportation GL account against UPF transaction key. Now even though the user is not entering any value in unplanned delivery cost field, system  is automatically taking the rounding off values(manually entered by user to match the vendor invoice) from MIRO line item and is posting to the freight account.
    Query -2 - while reversing the already posted MIRO document in MR8M the rounding of value  which has been taken automatically in unplanned delivery cost is showing in the error message as :
    "Balance is not equal to zero: 0.35- inr"
    please refer below screen shot for the error message
    Please suggest.
    Regards
    Chinmaya

    please read my blog it explains how to close a question, just replying "closed" does not do really this job
    How to close a discussion and why

  • Unplanned delivery cost report per vendor

    Hi All,
    Is there any SAP report that lets us run all unplanned freight charges per supplier.Thanks in Advance.
    Rgd's,
    Jagdish

    Hi,
       you can use FS10, enter the unplanned delivery cost account , click the account to see detail transaction by supplier.

  • Post unplanned delivery cost to different freight G/L Accounts

    Hi,
    Regarding the freight costs the business process is at  the time Purchase Order creation, the company does not know what is the freight costs that is going to be charged by the vendor. The freight charges will be known when the vendor sends the Invoice. The purchase order contains the materials to be drop shipped by vendor directly to customer or cross dock delivery to company premises.
    The business requirement is when the MIRO invoice is posted, user will enter the freight charges at the document header level and that value needs to be split among the PO Line items and needs to be posted to separate Freight Cost G/L Accounts based on the account assignment category. For drop ship items the freight cost to be posted to one G/L Account and for cross dock items it needs to be posted to a different G/L Account. Later on this freight cost to be applied to customer invoice for charging the customer with the vendor freight cost.
    The solution option we have considered is to define two statistical freight condition types at PO Level (one to be triggered for Drop ship materials and the other to be for Cross dock items), in the pricing procedure assign two different Account keys to these condition types. At MIRO users enters the freight cost as unplanned delivery cost, write the code in a user exit to split this value among the freight line items of the MIRO invoice. As separate Account keys are assigned to the condition types the values can be posted to separate G/Ls. To bring these values to customer invoice we will develop a custom routine in SD pricing procedure.
    Request the experts to let me know if there is any simple way to map this requirement.
    Thanks & Regards,
    GLN.

    Hi,
    As at the time of the PO you do not know the freight costs and you want to post the freight costs in the MIRO as unplanned delivery costs . and there is no way you have to post as unplanned .
    Here your requirements are 1. Post to separate GL accounts and 2. distribution among line items .
    However both of your requirements are given with sap standard functionality with the below sap  link .
    Logistics Invoice Verification (MM-IV-LIV) - SAP Library
    check spro--mm--liv--incoming invoice ---configure how unplanned delivery costs are treated .
    at the same time when you maintain the condition type for frieght iN PO , they will become the planned delivery costs . if this come in to picture FR/IR account will come into the pictute at GR and IR .
    i think your requirement will be partially met . and the coding part may become fuzzy rather to go with the standard.
    Regards,

  • MRHR Unplanned delivery costs different GL account

    Hello gurus,
    I am working in SAP system 4.0B.
    The requirement from my client is that the "Unplanned delivery costs" can be defined in a different G/L account.
    This should happen when they are doing the invoice, through MRHR.
    I though that this is possible and I have customised the following:
    - SPRO > Materials Managemet > Invoice Verification > Incoming Invoice > Configure how unplanned delivery costs are posted
    There, I have defined the value "2 - Different G/L line" for the company code.
    - OBYC. Here I have customised a new G/L account for the transaction "UPF - Unplanned delivery costs".
    But, when I am posting a new invoice, the unplanned delivery costs are still going to the old G/L account.
    Could you let me know what is wrong here? Or if I need to do something else? or, if with this version of SAP I cannot assign the unplanned delivery costs to a new G/L account?
    Makes me feel concern where the customising said "2 - Different G/L line" and not "2 - Different G/L account".
    Please, let me know your feedback and thanks for your time and support.
    Cheers,
    SP

    Hi Syed,
    Good link, but, this is not resolving my issue.
    Kind regards,
    Sandra Palomo

  • Unplanned Delivery Costs and Price Variance - Account Determination

    Hi,
    I am facing the following issue:
    My goal is to automatic post the unplanned delivery costs to an account depending on valuation class.
    The account should be diferent from the one used in purchase (EIN)  post but both values should affect the moving price.
    Can we do that?
    Thank you for your cooperation
                   Best Regards
                     João Fernandes

    My take is that you can have or the other, not both.
    You configure how the uplanned costs are handled, a) Distributed among invoice Items or b) to a different G/L line.
    Path : SPRO>MM>LIV>Incoming Invoice
    If you pick, the costs goes to the stock account.
    If you pick B, the cost goes to a separate account but it will not affect the item price.
    The account is defined in OBYC, for transaction UPF, and it is Valuation class independent.
    Hope it  helps

  • Assign GL account for Unplanned delivery costs

    Hi,
    When I post a vendor invoice (MIRO) and I enter 'Unplanned delivery costs' (in table Details) I can't save the invoice because the sytem didn't find the GL Account for Unplanned delivery costs ?!
    Can anyone tell me please how to assign GL acount for 'Unplanned delivery costs' in Customizig ?
    Regards.

    Hi,
    Please try through "Configure how unplanned delivery costs are posted".  IMG --> Materials Management --> Logistics Invoice Verification --> Incoming Invoice --> Configure How Unplanned Delivery Costs Are Posted.
    Regards,
    Elias

  • Unplanned delivery cost to material through G/L account during Invoicing

    Hi,
    We have a problem of capturing unplanned delivery cost to material
    The scenario is as follows
    We are not sure of few conditional value's during Purchase Order creation.
    We come to know only during Invoice verification,
    These conditions might be many, like labor Charges,Unloading Charges etc which should go to material.
    Though we can post it to material directly with reference to PO,we will not be knowing the purpose of posting,as the client wants the complete landed cost including these.
    And if we post it to a G/L account it does not go to material,Even if we set up UPF key, it still goes to G/L account only.
    Is there any way to post to material via G/L Account,as we want to give G/L account as reference to those conditions.
    Thanks and Regards
    W.Raghuram

    hi
    there r two options either the cost will distribute to the items or it will come to some different acct
    now u can set this
    Spro > MM >Logistic Invoice verification > Incoming Invoice > Configure how unplaned delivery costs are posted.
    here select appropriate option
    if u want it to be loaded on material then select distibute among line items
    if u want diff acct then chose 2nd option
    if u want diffrent gl acct for diff types of delivery cost then u can directly activate the direct posting to gl acct
    Spro > MM >Logistic Invoice verification > Incoming Invoice > Activate Direct Posting to G/L Accounts and Material Accounts
    then u will find a G?L acct tab
    here u can directly debit a amount to an acct
    regards
    kunal

  • MIRO : Selecting accounts for unplanned delivery cost based on PO type

    Hi Experts!
    Actually throught the configuration of transaction OBYC (UPF), when I have an unplanned delivery cost, there is an account number that has been configured.
    For any type of MM bill (MIRO), all postings are being made on the same account number for unplanned delivery cost.
    My client want to define the account number based on the PO type being billed.
    Example : For PO of type A, account number for unplanned delivery cost --> XXXXXXX
    and           For PO of type B, account number for unplanned delivery cost --> YYYYYY Thus overwriting the configuration of OBYC.
    I was thinking of doing some configuration using substitution (FI module). That will change automating the account number (BSEG-HKONT).
    Do you have any ideas to meet that request ?
    Thanking you in advance for your replies.
    Regards,
    Mahesh

    Hi
    You can use the BAdI MRM_UDC_DISTRIBUTE to change the distribution of delivery costs' shares across invoice items.
    But i am not sure if we can use the same for determining the G/L accounts.
    Thanks & Regards
    Kishore

  • Question on unplanned delivery costs need to go to GL account ????

    Hello
    I have a question regarding unplanned deliver costs. I am a FI analyst  Can you please explain my how I can solve my problem . My user wants unplanned delivery costs to go in to the GL account .
    In MM account determination GL account is set up but when I am doing MIRO
    . I am putting  total amount in amount field and freight costs in unplanned field under ‘detail ‘ section.
    When I simulate it gives me ‘tax code ‘ related warning when I hit enter it credit vendor and debits  GR/IR clearing and some debit  to inventory  account but not  to freight account,
    What’s  the problem. Can someone explain me :
    1)     What do I need to do to make it go to GL account ( account is set up but what is tax code related error . how do I fix that,
    2)     How does unplanned delivery costs work if I have tax, discount and freight.
    3)     Is tax calculated off total amount (inventory + freight) and discount too. How can I prevent that so that my tax is calculated just on inventory amount?
    4)     DO I have to put total in amount field (meaning inventory amount + fright ) or not .
    I will be grateful if someone can guide me towards right direction. Please give me a detailed answer. How does it work???
    Thanks
    Kavita Reddy

    in standard setting the freight amount gets debit in the stock or inventoy account and gets credit in the fright accoutn at the time fo gr so it means the amount of frieght is gettting invenotrised
    now at the time of IV IN MIRO SYSTEM CREDITS THE VENDOR ACCOUNT AND DEBITS THE GR/IR account
    if u want to settele the planned delivery cost then select the laout variant for the planned delivery at item level
    or in case if u want to make use of the unplanned delivery cost then u r doing the right step
    but as u simulate the g/l accounts sytem will debit the inventory or stock account for it  rather then frieght account (i belive so )
    as the uplanned delivery cost may be getting inventorised that is added to the material price
    and as u said u dont want to have tax calulated on the unplanned delivery cost then i suggest u to post it as subsequent debit and there do not make use of the claulate tax option or do the direct posting for the g/l account option

  • G/L Account  for Unplanned Delivery cost.

    Hi,
    I have a requirement to distribute the Unplanned Delivery cost to different G/L  accounts based on the material type of the item.
    Is there any User exit or standard setting to solve this.
    Thanks & regards,
    Maruthu

    Hi
    Unplanned delivery costs can be trigerred by customizing the the account assignemnts in OBYC under UPD transaction key.
    For trigerring different G/L accounts based on the Material type, use Enhancement LMR1M002- customer exit EXIT_SAPLKONT_011.
    In that you need to determine the G/L account based on account category refernce & Event key UPF.
    You need to take help of ABAPErs for the same
    Award points if useful
    Thanks & regards
    Kishore

  • Unplanned Delivery Costs Post to a different GL Account Cost Center err

    Hi,
    We added GL account  in config (OBYC >> UPF Transaction key ) such that 'Unplanned Delivery Costs' entered during invoice entry in MIRO will be posted a different GL account. We also changed in config from 'Distribute among invoice items' to 'Different GL Line'.
    When we try to post Invoice and add amount in 'Unplanned delivery costs' field in MIRO, system is giving error to enter 'Cost Center' since GL account characteristics is such  that Cost center is mandatory. The Cost Center field at item level in MIRO is disabled. Remember, we want to process this for INVENTORY items only, meaning items that go to stock and later issued, and not for POs created with 'Cost center' as Account assignment. We can create another GL and no cost element and assign that GL Account in OBYC for UPF Transaction key, but the client's requirement is to create 'Cost Accounting Doc' too when invoice is posted, along with Accounting and profit center docs.
    How do we fix above error ?
    Niranjan

    Closing this thread as the heading of the 'message' did not appear properly. Posting another message so heading of 'message' shows correctly.
    Niranjan

  • Distribution of unplanned delivery costs during delivery cost LIV

    Hi all,
    This clarification is regarding delivery cost LIV - where difference between:
      -  the amount invoiced by the freight vendor
    and
    - the amount accrued based on PO
    is treated as unplanned delivery cost and is intended to be distributed amongst the line items of the accrued planned delivery cost.
    Customizing for the company code - Configure How Unplanned Delivery Costs Are Posted - is set as "Distribute among invoice items".
    When we try to post an LIV in regard to the aforesaid scenario [Tax code is with 0% tax], the system returns the following error message:
    ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
    Balance is not equal to zero: 58.42 EUR
        Message no. M8186
    Diagnosis
        You cannot post the document as the balance is 58.42 EUR.
    Procedure
        Check the gross invoice amount, the tax amount, the amounts in the items
        selected and any unplanned delivery costs in the document header. The
        items selected on the item list may not be the same as those in the
        invoice.
    ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
    Also, went through the OSS note 129066 which mentions that Unplanned delivery costs cannot be distributed to the planned delivery costs as of SAP release 4.6C.
    Our system is SAP 4.7 and hence we are unable to understand the reason for this error..
    Is there any enhancement relevant in this regard?
    Can anyone please throw some light on this.
    Best Regards,
    Bhargav

    Thank you for contacting SAP Global Support Center.
    It seems you're posting the planned and unplanned delivery cost
    simultaneously.
    The planned delivery cost and unplanned delivery cost cannot be invoicedtogether when only freight cost is being invoiced.
    Unplanned delivery cost and planned delivery cost can be invoiced
    together only when you invoice both goods and freight cost.
    This is the standard design of the system. Even in customizing for
    unplanned delivery cost, the system behavior is designed such a way thatit can be invoiced along with goods only. Both options which we have
    given behave similarly except for the posting to account.
    Therefore, your system behavior is as per standard design and there
    is no error in your system. For this functionality there are no other
    workarounds too.
    Additionally, Please consider if the workaround below is working.
    In order to post unplanned delivery costs with planned delivery costs
    the customizing has to be set so that the unplanned delivery costs are
    posted to a seperate G/L account rather than distributed amongs line
    items.
    SPRO
    >>Materials Management
    >>Logistics Invoice Verification
    >>Incoming Invoice
    >>Configure How Unplanned Delivery Costs Are Posted
    "2" Different G/L line
    May I ask you to review note 129066. The the validity is from 4.0 to
    4.6 C but it is valid for your release also.

Maybe you are looking for

  • Had to uninstall iTunes, now it won't reinstall. Please help!

    Info: (iTunes 10.5) (iPod Touch 32G 3rd Gen iOS 5.0/5.1 (not entirely sure)) (Windows 7) (HP Pavilion dv6 Laptop, bought in May 2011) Ok, so I decided that I wanted a new game for my iPod Touch 32G 3rd Gen, 'Pocket Planes'. A free, no hassle download

  • Purchased music but can't download it?

    I purchased an album a month ago and now trying to download it on my Macbook,iPad,iPhone but it won't work

  • I have to supress one field named PAYMENT GURANTEE PROCEDURE

    hi, i am trying to supress the field called payment gurantee procedure in CMR through OBD2. but unfortunately i am not able to find the field in customer master data in OBD2 in the relevant accoutn group. help me on this.. regards, balajit

  • Supplier list clarification

    Hello Guys I came to know that in Supplier list creation, we can display backend ECC contracts. And this is possible only with Classic scenario. If we activate extended, the SAP documentation says itu2019s not possible to do that. I want to know why?

  • Directing an AP to a specific WLC

    We have recently implemented a N+N controller configuration.  I expected to configure the test APs High Availability option with a primary controller of the new WLC and secondary as the current production WLC, then reset the test AP to have it join t