Confirm Successful Test in Normal Correction (SDMJ)

Hello,
In normal correction (SDMJ) workflow, the action Confirm Successful Test is selected in the Development with Release phase of a project/maintenance cycle. The status of the Change document changes to Consolidated after that, and you then be able to move the cycle to Test phase.
How can we customise the standard workflow so that Confirm Successful Test is selected in the Test phase? This seems to make better sense.
I'd appreciate any help from any one of you who have done some customising to the SDMJ standard workflow. Many thanks in advance for your help.
BR Li

Hi Li,
I had the same dscussion with my customers more than once, it is hard to understand to perform the action "Confirm Successful Test" before Test phase.
You could add another status to SDMJ (or a copy of SDMJ, for instance ZDMJ) before Consolidated.
But we selected another option, by using test messages during test phase and therefore following SAP standard process. So, a developer confirms successful integration/unit testing after he finished his development/customizing activities in dev by changing the status to consolidated.
If some issues are detected in Test phase, we are using test messages to correct it. But you are right, at the end of test phase there is no additional status which says: all is fine, go ahead and move it to production. Only be checking that all Test messages are finished, the Production transport approver can be sure, all issues have been resolved.
But by adding another status, please consider this: You have to create a copy of SDMJ (ZDMJ). After this, all enhancements and changes to SDMJ delivered by SAP, you have to do manually for your new transaction type ZDMJ, otherwise you will not get the functionality. That's why I'd recommend to use SDMJ as delivered by SAP and also use Test messages during test phase.
Best Regards,
Holger Slomka

Similar Messages

  • Unable to chage the status of normal correction to confirm successful test

    Hello,
    I am unable to chage the status of normal correction to confirm successful test in solman. Its shows error:
    Not all test transports are imported .
    I have imported the test trasnport in to test system successfully but still i am getting this error . I have also checked blogs in SDN but non of them refers to any solutions. But I can see lot of people have faced this issue.
    My configuration is fine and no error in application log.
    Can any body help me to find the resolution for this problem? answers will be rewarded.
    Regards,
    Bhavesh

    Hello Mark,
    Thanks for the update. But non of the above option can resolve m issue because :
    1) Note 1352886: is not relavent as I laready have the higher patch level of solution manager for ST comonant( SAPKITL431).
    2) I have already gone through this blog this blog talks about the status of maintenance cycle but in my case the maintenance cycle status is fine  (in developemnt without release) . So as per process till now i am on the correct status.
    I appreciate your updaes but still I am not able to change the status to consolidate. because of error Not all test transports have been imported.
    Please let me know if you have any other solutions for this error.
    Regards,
    Bhavesh

  • Charm Status hangs while saving Confirm Successful test

    Hi, I'm Unable to set the status to <Confirm successful test>...ChaRM document is hanging without getting saved.
    Please let me know what are the possible issues.?
    Sonel

    Hi,
    Can you tell us if your transport imported with error in QAS system?
    If yes,then in SCMA you can click on  'Correct import(repair flag)' button. It will give you the list of transports that went in error for all (*) users in QAS or PRD systems. Then you can select the transports one by one and click 'error corrected' button.
    After this you can try again to change the status of CD to 'Successfully Tested'.
    If No,please check the job log of collector job SM:TMWFLOW_CMSSYSCOL and see if it is running fine.
    The production import queue doesn't get updated with QAS transports due to failure of mentioned job,so when you are scheduling import job it may not be getting any transport to import.
    Also,  if you have 5 system landscape and you are moving the changes to QAS system of N+1 landscape, and because of ChaRM configuration, changes are not yet allowed to go in import queue of N landscape ,then we get such warnings.
    Hope this helps.

  • Normal corrections "SDMJ" are not visible under tcode "DSWP"

    Hi!
    I have the following problem by working with ChaRM and normal corrections.
    There are two types of normal corrections:
    1) Normal Correction (type:SDMI)
    2) Normal Correction (type: SDMJ)
    Problem
    Since a few days it is not possible to see all the SDMJ normal corrections within tcode
    DSWP --> Change Management --> Drop Down "Not Completed".
    Only the SDMI normal corrections are visible there.
    Questions:
    how can this issue be customized in order to see the normal corrections of type: SDMJ in tcode DSWP?
    Thank you very much!
    regards

    We implement SAP Work Center

  • SDMJ  can't set "Confirm Successfull Test"

    in SDMJ i want to set status CONSOLIDATED status by the action "CONFIRM SUCCESSFUL TEST" but its not setting the status "consolidated" so that i can import the actual TR to QAS.
    Any idea??
    I have released and imported the TOC from my tasklist and i can see it in my QAS as well.
    Regards
    Sidra Hasan

    i reimported transport request from task list, it was performed successfully ut still cant change the status of the cjange request.
    Any idea why??
    still the same three warnings
    Further can u please tell me what does it mean by "REQUEST DELETED"??
    here:
    Action System Logon in system QAS 300 of type Target Systems completed
    General Note
    13.12.2011          07:25:59            H_SIDRA
    Requests  are deleted
    Action 'Create Test Transports without Open Transport Requests'
    performed
    The status was set to the value 'To Be Tested'
    General Note
    13.12.2011          06:57:31            H_SIDRA
    Requests  are deleted
    General Note
    13.12.2011          05:50:22            H_SIDRA
    Requests  are deleted
    General Note
    13.12.2011          05:48:53            H_SIDRA
    Action System Logon in system DEV 300 of type Source Systems completed
    General Note
    13.12.2011          05:47:03            H_SIDRA
    Requests  DEVK903558 created
    Action Create Transport Request in system DEV 300 of type Source Systems
    completed
    Edited by: Hasan Sidra on Dec 14, 2011 11:33 AM

  • CHARM: Developer and Tester same USER in normal correction

    Hi Expert,
    i'd like to know if in a normal correction it is possible that Developer and Tester are the same persone.
    So the same user have to confirm development and confirm sucessful test.
    Now if i try to use the same user i've an error.
    Can you help me ??
    thanks
    Francesca

    SPRO
    search for Make Settings to Change Transaction Types, and select that activity.
    Highlight SDMJ, select the Use Partner Functions folder on the left
    in the table on the right:
    The first column in the table is the status
    The second column in the table  is the partner function that the current business partner will be assigned to when save is clicked and the status becomes the first column.
    The third column in the table is used for determining if partner functionsu2019 business partners are the same when the document is saved and the status becomes the first column. For example, the Tester (SDCD0002) equals the Developer (SDCD0001) when the status is Confirmed (E0009).
    Delete the value in the third column to stop the comparison.

  • ChaRM: Normal Change - Not possible to set "Successfully Tested" unless the Maint. Cycle is set to "In Development with Release"

    Hello,
    I'm doing some tests with ChaRM, Normal Change scenario.
    As far as I know, the following steps would be the correct sequence (concerning development and test phases only):
    1) Developers perform the correction in DEV and release their TASKS of the transport request
    2) Developer Lead set the Normal Change document status to "to be tested"
    3) In background, a Transport of Copies is created with all data previously stored in the original transport request. Then this ToC is transported into QAS
    4) Change Manager set the Maintenance Cycle status to "Test"
    5) Tester performs the test into QAS
    6) Tester provides a valuable feedback and set Normal Change document status to "tested successfully"
    According to the following SAP Portal article, it seems to be correct:
    http://help.sap.com/saphelp_sm71_sp10/helpdata/en/48/db938dceba518de10000000a42189c/frameset.htm
    During my tests, however, I have noticed that it is just possible to go from step 5 to 6 if the Maintenance Cycle status is set to "In Development with Release" (go a step back in the Cycle). Otherwise, I get the following error messages:
    Warning Message Details Status was reset by system
    Warning Message Details Action RELEASE_ALL cannot be performed during this maintenance phase
    Warning Message Next status cannot be set because some actions cannot be executed.
    Once I have done the Cycle status change, then it is possible to move from 5 to 6 without errors and then the original transport request is transported into QAS too.
    Question: Is this the correct behavior or am I missing customizing?
    Thanks in advance for your help.
    Daniel

    Hello Vivek,
    Thanks for your reply.
    It is kinda weird the steps sequence, since the Tester needs to tell the Change Manager to move the cycle's status before approving the correction done in QAS (successfully tested).
    Perhaps a new action between "to be tested" and "successfully tested" could exist, in order to request the CM to perform the cycle update.
    But OK, that's how it is.
    Regards,
    Daniel

  • Normal correction: how to assign developer or tester?

    Hello,
    I have implemented ChaRM. I have one concern infront of me regarding the process. My ChaRM is working fine. When I create a Normal Correction (NC) or UC, I can see the tab for Change Manager, IT Operator and Current Processor. I do want to know how the request will determine who is the developer or tester? Once I create a request, it is visible in the assinged person's queue. As I am not able to specify Developer and Tester in the request, how they will come to know about the CR?
    In Partern Determination procedure, I can see SDHF0001 function is assigned for SDMJ and SDHF. I can only define 4 roles there. How can I add more?
    Please help me ASAP.
    Regards,
    Rajeev
    Edited by: Rajeev P on Jun 16, 2009 2:56 PM

    Hi Rajeev,
    did you have a look at the partner tab under "transaction data"? Is that what you are looking for?
    It is just possible to display four entries under "fast entry", but you can assign lots of partners in the partner tab.
    There are also several possibilities for the customization of the partner determination like access sequences, see IMG activity CRMC_PARTNER_AS.
    Kind regards,
    André

  • Charm Normal Correction(Maintenance) not able to generate with SDMJ

    Hi,
    I have configured Servic Desk & CHARM newly. Urgnt correction is working fine.
    But when i select the subject ' Normal Correction(Maintenance) ' in change request it creates a correction with Transaction type-SDMI
    My requirement is SDMJ Normal Correction(Standard). why system is automatically taking SDMI insted SDMJ.
    Regards
    PK

    Hi
    Hav  you activated the following BC Set
    SOLMAN40_CHARM_TRANSTYPE_SDMJ
    hope it solves
    Regards
    Prakhar

  • Customizing steps to make visible any SDMJ normal corrections in tocde DSWP

    Hi!
    I have the following problem by working with ChaRM and normal corrections.
    There are two types of normal corrections:
    1) Normal Correction (type:SDMI)
    2) Normal Correction (type: SDMJ)
    Problem
    Since a few days it is not possible to see all the SDMJ normal corrections within tcode
    DSWP --> Change Management --> Drop Down "Not Completed".
    Only the SDMI normal corrections are visible there.
    Questions:
    how can this issue be customized in order to see the normal corrections of type: SDMJ in tcode DSWP?
    Thank you very much!
    regards

    We implement SAP Work Center

  • Normal Correction flow & Transport of copies

    Hi,
    I am performing following steps for Normal Correction. But when I first time schedule the imoprt job, nothing is moved to Quality system.
    u2022     Action u2018Set to In developmentu2019. Status changes to u2018In Developmentu2019.
    u2022     Perform action u2018Create Transport Requestu2019. Transport Request (ID6K900342) created.
    u2022     Change the Maintenance Cycle phase to u2018Development with Releaseu2019
    u2022     Developer completes the work & releases the Task in satellite system
    u2022     Action: u2018Test Transportu2019. Creates Transport of copies (ID6K900344)
    u2022     Schedule the import job. ( But after executing also nothing will be moved to Quality)
    u2022     Action:  u2018Complete Developmentu2019. System creates another new Transport of copies (ID6K900347) for Original Request.
    u2022     Schedule the Import job. ( But after executing also nothing will be moved to Quality)
    What could be the reason. both the TP copies are in queue only, nothing is moved to quality.
    Regards
    PK

    Hi PK,
    Let me try to explain:
    NC => 80000001
    1. Create TR
    XXXK0001 (Original TR)
    2. "Test Transport" or "Complete Development"
    XXXK0001 (Original TR) -> still not released
    XXXK0002 (ToC- copy of XXXK0001)-> is created in DEV
    3. Import TRs to QAS (from task list)
    XXXK0001 (Original TR) -> still not released
    XXXK0002 (ToC) -> is moved to QAS
    4. Now the changes are in QAS, but is not placed in the PRD import queue. So, you can test it with no risk.
    5. If you have problem, go back to 'In development'
    Correct the problem in XXXK0001
    and go to step 2 again.
    6. If the changes are OK in QAS
    - Select 'successful tested'
    XXXK0001 (Original TR) -> is released
    7. Import to QAS
    XXXK0001 imported in QAS and automatically placed in PRD import queue.
    8. Import to PRD
    The ToC is used to avoid import an inconsistent TR into PRD system, because once it has been imported in QAS, the same will be available to import into PRD, without any test.
    BR
    Fernando

  • Reseting status of normal correction

    Hello.
    After update up to version ST 20 (SAPKITL430) one more error appear in system. After processing of any activity with normal correction and trying to save this document system resets status of correction to "Created". I have found coresponding SAP Note 919477, but it has't any correction instruction... Can you help me?
    Edited by: Dmitry Udot on Sep 25, 2009 11:02 AM

    Hehe... you are right.
    First off I think it should be SDMI_ACTIONS not DMI_ACTIONS.
    And yes, there should be some more instructions, hehe. Probably delete it (after making a screenshot).
    The selected schedule condtion looks strange. Because as for what I can tell it says:
    Set User Status to E0001 (new) when user status is not:
    consolidated AND NOT productive AND new (consolidated and productive belong to SDMJ not SDMI, new fits to both)
    OR
    in developement (fits to SDMI and SDMJ)
    So whenever you set (SDMI or SDMJ) to "in developement" it will be set back to E0001. Very strange.
    Guess you may delete it or at least disable the action.
    Regards

  • Normal Correction document is reset to Created by itself

    Dear everyone:
    We have configured ChaRM - Solution Manager 4.0 (SP9). The ChaRM works fine on Urgent Correction, but not for Normal Correction. The Status of (Normal) Correction document always reset back to Created. It does not want to stay as 'In development' status.
    Here is the step I took to create new change document with a  Subject : Normal Correction(maintenance).
    I authorized the change document, then I choose Maintenance Cycle (Normal/Periodic Maintenance).
    Next document / correction document -> 8000000196, Status: Created. I choose set in Development. - Status of correction document is: In Development
    Next step, I choose Create Transport Request - transport request generated for document. Then all the sudden the status of correction Document is back to Created.
    And I can not go to any where else....
    Would anyone please help me out?
    Thank you.
    Kind regards,
    Rudy

    Hi Steven:
    There are some actions are the detail -
    Action 1: (yellow light) During Creation
    detail: (green) check successful
    Action 2: (yellow light) Check Consistency:
    detail: (green) Check successful
    Action 3: (red light) for Copy a Solution Manager Context:
    detail: (green) date/time stamp
    (green) Processing SOCM_COPY_CONTEXT is started.
    (red) Action could not be successfully executed (no processing parameter)
    The other one has yellow status, and the processing parameter shown as
    --> No container is available, for application name CRM_ORDER, Action profile SDMI_Action
    Action 4: (green) set to 'In Development' :
    (green) Processing HF_SET_STATUS Is Started
    (green) Action successfully completed
    Action 5: (green) Create Transport Request:
    (green) Processing HF_Execute_Action Is Started
    (green) Request ID and Number created
    (green) Action successfully completed
    As soon as triggered Create transport, then the Document status back to 'Created', and I only have two choices in the action button ... set in Development or Cancel Procedure.
    What would cause this issue ?
    Thank you in advance.
    Kind regards,
    Rudy

  • Charms :  Background job not scheduled (normal correction) ?

    Hi,
    I am trying to run a dry cycle for normal correction but when i go to task plan in any ticket to release a request. When i schedule this job " release a request" , i dont see any job running in background in SM37. I think job is not gettin sceduled properly.
    Please help me out

    Hi,
    All right. We need to dig this one
    I guess you schedule the import by going the the tasklist
    and you get a red flag for this activity in the calendar ? do you have any error message ?
    If the messagein the task-list is not self-explanatory you can check the SLG1 log in SOLMAN. Which error message do you get there. (select the correct time frame, the log could be big)
    My guess is that some S_RFC authorisation is still missing there
    This authorisation is outside SAP_ALL and is often the cause of this kind of issue
    Tell me the error message and we will hopefully  fix this (I had the same kind of issue when I started last year)
    best regards Xavier

  • I have an HP Officejet 7210 all in one printer, have loaded Printer Pro to IPad, get successful test pages in the Print Pro App but can't print emails (or anything). error message is No AirPrinter found.  How can I get connected?

    I have an HP OfficeJet 7210 all in one printer, have loaded Printer Pro and had a successful test while in Printer Pro.  When I try to print and email I get NO AIR PRINTER message,  How can I connect my printer to my IPad and print emails.

    Welcome to Apple Support Communities.
    If you're using the Printer Pro app, you're not going to use AirPrint services.
    They are not the same thing.
    Are you using the 'Open In' option to get the email into Printer Pro for printing?
    http://itunes.apple.com/us/app/printer-pro/id393313223?mt=8
    Once installed, Printer Pro appears in the "Open In..." list on your device. This lets you print documents from Mail, Safari, ReaddleDocs and many other applications on your iPad that supports this function.
    Using "Open In..." approach you can print files from many popular online storages: Dropbox, MobileMe iDisk, GoogleDocs. It just a matter of several taps to download your file via free Dropbox, iDisk or Google Docs application and send it to printer.

Maybe you are looking for

  • How do I set Firefox to be usable for all users on one computer?

    How do I set Firefox to be usable for all users on one computer?

  • Workflow report by parked document number / Company code / Year

    Hi, I need to develop an new ALV report to find out the status of the parked document. The selection criteria will be as below: 1. parked document number 2. Company code 3. Fiscal year The out put of the report should have the below details. 1. Docum

  • How to Set Video Dimension

    I have on the general tab a DV Playback or Playback for Windows and Im not for sure on how to set the Dimensions this is related to the Scaling Video thread.

  • ICloud Storm Rains on Safari

    After adding a bookmark to Safari on my iPhone, Safari on my Mac mini and MBP came up with everything reset.  I only want Safari bookmarks to sync between my iOS devices and my Macs, I don't want Safari to reset on the Macs when I add a bookmark to a

  • Problem in ADOBE Editor

    Hi Folks, I am facing some problem in using ADOBE interactive forms. I am using SAP NETWEAVER DEVELOPMENT STUDIO Version: 2.0.10 In Web Dynpro project after making UI Element Interactive form, to EDIT..it gives the error as An error has occured when