Hi All,
I am looking for some clarifications. I can able to process confirmation in SRM (through Central goods/services transaction) for a PO created only in ECC. If I do any partial confirmaiton, then the remaining quantity will be available for further confirmation.
But this is not happening for ECC Return PO (PO where Return box is checked). I could able to process only one confirmation for that return item in SRM and it posts a goods movement with 161 mvt type in ECC. But after that, this return item is not available for further confiramation in SRM. That line itself is not there in the item overview screen of confirmation.
Has anyone come across this poblem? Can you please help me to undertsand the issue here?
Thanks,
Arun

Hi
You can use any of your existing purchasing group to create a return PO.
Thanks

Similar Messages

  • Pop - up smart form for Process Return Deliveries  in Confirmations

    hi..
    For Process Return Deliveries  in Confirmations
    At item level when i click on print icon a pop -up should show smart form...
    right now the smart form comes on the ITS and not as a pop - up.
    Thank you.
    Regards,
    Kailash.

    Hi,
    The file name has 2 PERIODS, so system has an ambiguity in deciding the extension of the file.
    test_2098079765.174_X.XLS
    174_X.XLS
    XLS
    Rename the file in such a way that it has only a single PERIOD.
    Best regards,
    Prashant

  • Difference between confirmation cancellation and return delivery

    Dear Gurus,
    can you explain to me the difference between confirmation cancellation and return delivery in terms of processes and impact on ECC postings?
    Thank you in advance for your collaboration,
    Fuffo
    Edited by: Fuffo Fuffi on Dec 21, 2010 2:36 PM

    Hi
    Confirmation Cancellation --> is used for reversing a confirmation which is posted wrongly in the system. This is generally used for reversing a faulty transaction.
    Return Delivery --> is used for sending the goods back to vendor. This happens when we receive goods from vendor and for some reasons the delivery does not meet customer's specification due to any reason. In these cases you record the goods movement as Return delivery sent back to Vendors.
    Regards
    Virender Singh

  • Text mapping from SAP SRM confirmation to ECC Servic Entry Sheet

    How can we map Item and Header texts from SRM confirmations to ECC Service Entry Sheet appropriate fields.

    Hello Sanjeev,
    FIrst, run report /SAPSRM/GET_TEXT_CUST_ERP in SRM. This report copy texts from backend to SRM.
    Then use SPRO to map texts between SRM document and R/3 corresponding document:
    SAP Implementation Guide > SAP Supplier Relationship Management > SRM Server > Cross-Application Basic Settings > Text Mapping > Text Mapping for Inbound and Outbound Texts
    Standard Text ID for ERP lines of service begin with "L". They are linked to customzing object ESLL.
    For more details, have a look at R/3 function module MMPUR_GET_TEXT_CUST_DATA.
    Regards.
    Laurent.

  • Service entry sheet (Confirmation for service) creation by supplier

    Service procurement MM-SUS.
    For processing service orders(no hirarcies, only one service line)
    I Have transfered the service Purchase order from ECC
    to SUS(SRM7.0).i am able to see the purchase order
    and POR created and transfered to ECC. Further confirmations
    for Creating SES in ECC,how?
    i have tried with create confirmations in start page of SUS.
    but service POs are not available.what are the settings  required in SUS (for service confirmation) to create SES in ECC.
    with screen shots is more helpful.
    regds
    Rami

    Hi Nikhil,
    thanks for your Feedback.
    we are not using EHP4. our ERP system is ECC6.0 only. I know EHP4 is required at ECC side. But  in this stage
    we are going with ECC6.0.with Custom developments. I think modifications are required in the Interfaces and at ECC side.
    as SRM is already upgraded to  SRM7.0.I think no custom developments needed at SRM side.only the service orders requests
    from ECC to PI and PI to SRM needs to be modified?
    scenario name  : ECC triggers Idoc to PI and PI generarate XML to SUS (Orders02 to Purchase order request).
    i have checked the Idoc and all  fields required for creating service order in SUS is available.is any other fields/check box required in Purchase order Idoc. so that we can map.
    in service purchase order Item detail screen(service lines) is not displaying in SUS side and also confirmation(SES creation).
    regds
    Rami

  • ITD State Code for TDS return

    Hi friends,
    kindly guide me the creation of ITD State Code for TDS return. Is it Local Tax Office or District Tax Office under Section Code of South Korea ? What is the exact creation procedure of ITD State Code as mandatory field in TDS Retrun screen(J1INEFILE - Version ECC 5) .
    Regards,
    Samrat

    Hi,
    This question is still pending and the two tables  J1ISTATECD and J1ISTATECDM which is required to be maintained is not available in SAP. Here version is ECC 5. If there is any SAP note or any alternative suggestions need your suggestions.
    Regards,
    Samrat

  • Production confirmations for Production order

    Hi all
    I am using ECC 6.0 and Production orders. When I do a final confirmation to the order the order is in a 'CNF' status. Now after it is in a CNF status if I try to perform another confirmation using a CO15 then it allows me to do a confirmation with a 'warning'. If I am using a CO11 or CO11N then its a hard error. Is there a way I can get a warning message on a already Final confirmed order in tcode CO11 or CO11N?
    thanks

    Hi John,
    You want the system to allow to confirm operation wise even though you have already confirmed with respect to order
    I dont think its possible,because if you see logically -once we do the confirmation for the order system will complete the confirmation for operations too ie it will book the time,cost to the respective cost center
    So logically it will not be possible to confirm the operations which are already confirmed when doing the order confirmation
    If you want to do order wise confirmation then you have to cancel the order confirmation & then you will be able to do operation wise confirmation
    Hope the above explantion is understandable
    Revert back if you have further query
    Reward points if useful
    Regards,
    SVP

  • Automatic TO creation and confirmation for a Material document

    Hi Dear All,
    i am new to MM andWM.
    I have to customization for auto transfer orders and confirmations for material documents what ever created with 101 movement type in Inventory Management. I have down configuration like below.
    SPRO->Logistics Execution->Warehouse Management->Activities->Transfers-> Set Up Autom. TO Creation for TRs / Posting Change Notices
    Double click on ‘control data ‘tab
    Hear for my warehouse I given input like   Auto TO = ‘1’,
                                                                             AddId = ‘select check box’.
    And in ‘Assign control’ tab for 101 movement type I have given input like below.
    Automatic TO = ‘1’.
    TO item can be confirmed immed. = ‘tick checkbox’
    Propose Confirmation = ‘tick checkbox’.
    Foreground/Backgrnd = ‘D’.
    After creating of Material document I am executing report RLAUTA10 in SE38.When I execute this report system showing message like ‘TO processing finished: TR total:   17, TO created:    0, Errors:   17’.
    If I check header details of transfer requirements in LB03, i am not seeing ‘Tick Mark’ in Auto TO Creation field.
    Can any one tell me what the mistake i have down or if i need to do any further configuration. Please help me regarding this concern?
    Thanks in Advance..

    Dear Steve,
    Thanks a lot for giving reply with what I need to do, but I am unable to see result.
    I have down configuration like below even though system not processing Auto TO creation. Can you explain me if I have down any mistake below.
    Click on ‘Assign’ button,
    Press on ‘New entries’
    WhN = ‘900’
    Reference Movement Type = ‘101’
    Movement indicator = ‘B’
    Movement type for Whse Mgmt = ‘101’
    TR create Transfer Requirement = ‘X’
    Immed.TO Creation
    Mail confirmation for background processing = ‘01’.
    GR date = ‘2’

  • Confirmation for Service Order

    Hi Gurus,
    How to create follow-up document of Confirmation for a service order in IC Agent role
    Thanks,Sarat

    You could use the left navigation bar to go to service confirmation tab and just click create on service confirmations, the prerequisite is you must be on the service order from which u want to create Confirmation, this will link up all the transactions your interaction record
    Second way of doing it, is click on followup document from service order to create service confirmation prerequisite here is that you must have the configuration ready for creating follow up documents
    Thanks
    Raj

  • No maintenance plan has been confirmed for Order 000004024181; Follow-up ca

    Hi
    I try to close a list of preventive order (initiated by maintenance plan) from the transaction IW38 but the system displays the following error message
    "No maintenance plan has been confirmed for Order 000004024181; Follow-up call exists
    Message no. IW597"
    thank you for your help

    Hi,
    You mean close -
    >TECO???
    If yes Go in IW38 select all orders  ,click Enviroment Tab and you can do the TECO but that order should not have Open reservation.
    Regards,
    Rakesh
    Edited by: RAKESH ASHOK MANE on Aug 26, 2010 1:02 PM

  • Automatic TO Creation and Confirm for the 321 Mvt type

    Hello Experts,
    Like to know the customisation invovlved for automatic TO creation and confirmation for the 321 movement type in which QM is activated.
    I have already activated in OMKZ as below
    1.Automatic TO for 321 mvt ytpe
    2.TO item to be confirmed immediately
    3.Propose confirmation
    Table T333 -AUTTA
              T333-SQUIT &
              T333-VQUIT is activated.
    Please let me know any other settings to be performed
    Regards
    Krishna

    Hello Experts,
    I am trying to create the Automatic TO and TO confirmation for the mvt type 321.
    I made the below settings
    I have activated in OMKZ as below
    1.Automatic TO for 321 mvt ytpe   -"A"
    2.TO item to be confirmed immediately  - tick mark
    3.Propose confirmation   - tick mark
    Table T333 -AUTTA
    T333-SQUIT &
    T333-VQUIT is activated.
    I have activated in OMKX as below
    Table T321-TBFKZ Immediate TO Creation with "A"
    T321-TAFKZ TR creation with "X"
    After doing the settings i am not able to see the Posting change number in the Material document created for the mvt type 321.
    Please let me know how to create the Posting chnage notice for the material document and how to convert the Posting change notice to automatic TO and confirmation.
    Thanks & Regards
    Krishna
    Edited by: Hariharan krishna on May 25, 2011 8:01 AM

  • Confirmation for Service PO from SRM to R/3

    Hi All,
    We are using SRM 3.0, EBP 4.0 ECS and R/3 4.6C.
    I have posted confirmations for a Service PO successfully in SRM and a GR and Service Entry Sheet has been posted in R/3 correspondingly. However some of the confirmation results in the status "Currently being transferred" and R/3 does not get updated with GR and Service Entry Sheet.
    I have checked that the workflow has processed succesfully and it is in 'Completed" status.
    Our observation -  While posting cofirmation for a Goods PO, the GR is posted in R/3 using IDOC. We can trace the same in transaction WE02. While posting confirmation for a Service PO, GR and Service Entry Sheet is posted in R/3, however not sure how this is posted as we are not able to trace any IDOC for a Service PO confirmation.
    I need to know how confirmation is posted for a Service PO.
    Any pointers to resolve the above issue would be highly appreciated.
    Thanks in advance,
    Francis

    Hi Francis,
    Please refer to the following threads for some ideas:
    Confirmation not transferred to backend R/3
    Re: PO confirmation havinmg status error in transmission
    Re: Coudnt create confirmation or Invoice from EBP
    Cheers,
    Serguei

  • Confirmation for Limit PO

    Hi,
    While posting a confirmation for limit PO, if I tried to add items from a catalog then I I am getting the error "Incorrect transfer of limit data from calling application". Are there any specific OCI settings required for this?
    In the link https://websmp101.sap-ag.de/~sapidp/011000358700005436392003E.pdf ...I could see that there is a presentation for "Access to catalog via OCI during confirmation" at the top of page 4. But not sure where can I find that PPT in service.sap.com.
    Could you please help me in this?
    thanks,
    Arun

    Gil,
    We found that, only service items can be added to limit confirmation as in backend R/3 service POs will get created which will accomodate only service items.
    You need to create contract and catalog with service items. Then only it will get added to limit confirmation.
    Hope this would help you.
    Thanks,
    Arun

  • Error while posting confirmation for limit PO

    Hi Experts,
    we are having a standalone scenario(SRM 7) and the issue is as mentioned below
    The situation is that the PO is a limit order with 2 line items. The first line item is complete and has been closed off with the u201Cno further confirmation/invoiceu201D indicators selected. However the 2nd line still has some limit remaining but the when the central confirmations attempts to enter a good receipt against the line they get an error message which is "No Confirmation could be entered for purchase order"
    please guide me how to solve this.
    regards
    smita

    Hi,
    please find furhte information.
    a limit sc is created for a value of 37000 GBP and after approval it created a PO. but the user went and added a line item directly in PO for 40000 GBP. Now the total value of SC is 77000 GBP.
    user has created a confirmation for 36000GBP and selected no confirmation required further.there is no issues with this lin item
    but with the second line item he posted confimation for value 37000 gbp and invoiced for 30000 GBP.
    when i am trying to post confirmation for 3000 GBP system is throwing an error that "no confirmation could be entered for purchase order"
    could any one guide me how to solve this or any suggestions for solving this.
    regards
    smita

  • Transfer rules are not exist for ECC Quality source system in BI Dev

    Hi,
    I Connected BI Dev system To ECC Dev and installed the sales, purchasing,... data flow, but here i am not getting the quality data to show the reports, to get Quality data  I established the connection between BI Dev and ECC QA, while installing the transfer rules for the ECC QA data sources there no transfer rules are exist(only some of them exist) in the business content, but all the update rules,... are exist, when i right on the data source say create transfer rules it is proposing App praposal.
    When i select source system as ECC dev while installing the transfer rules i can see all the transfer rules, but when i select source system as ECC QA i can see only some transfer rules.
    only problem with transfer rules(some of them exist), for remaining all objects are properly existing in business content for ECC QA source system.
    Regards,
    chandra

    Hi Fayzrakhmanov
    Thanks for the quick reply. We are not moving the stuff to QA. We are only connecting QA ECC system to BI Dev. We already have datasources moved to ECC QA and created source system for ECC QA in BI Dev.
    The problem is I am not able to get Business Content transful rule for new source system. We I can find some but not all unlike development.
    Help on this would be appreciated.
    Thanks

Maybe you are looking for