Confirmation for sub-operation

Hi Expert,
As we know that confirmation has to be maintaned for each work order confirmation.
Current condition, we also have to maintained confirmation for each work order sub-operation.
Is there any possibility that only operation level of work order that need to be confirmed? instead of sub-operation level? in assumption that work order created with both operation and sub-operation
illiustration:
Operation 0010 Greasing
      Sub operation 0010/0011 cleanning
      Sub operation 0010/0012 inspection
Confirmation conducted for operation 0010 Greasing only, instead of all operation and sub operations
Thanks
Pls Help
Rgds

Leni,
There is nothing in the standard system that would force you to create confirmations at either operation or sub-operation level (unless you have done something in your system)
PeteA

Similar Messages

  • Control key for sub-operation

    Hi, what is the control key used for sub-operations for which we do not want seperate confirmation. when main operation confirms, the sub-operation should get confirm automatically. please advise.

    hi,
    You can use PP03 or *PP05 * or any other which dont have tick for confirmation required.
    only thing is that , other details also you need to check for.
    Depending on your requirements, a sub-operation can contain the following data:
    A control key, which specifies
    Whether costs are determined for the sub-operation
    Whether the sub-operation is processed internally or externally by a vendor.
    Whether, afterwards in order processing, a confirmation can or must be made
    A wage type for settling incentive wages
    Standard values, which are planned values for the activities to be performed in a sub-operation.
    External processing data, which form the basis for externally processing sub-operations
    User-defined fields with any customer-defined data
    Check and revert back
    regards
    Ritesh

  • Goods movement in QC confirmation for inprocess operation

    Dear Friends,
    I am doing inprocess inspection for routing operations. After results recording, I get the window where I am entering yield.
    If I go to confirmation tab, I can enter the activities and qualntity. But ther I am not getting goods movement tab.
    I want assign batch no. to material in the goods movement tab.
    How can I get it?
    Please help me.
    Waiting for reply!
    Thanks!
    Kiran

    No Inputs?????

  • Automatic Time Confirmation for an operation in a Maintenance Order (IW41)

    Hello,
    We have a requirement to do automatic time confirmation (while saving the order) on an operation when the user selects "DONE" standard text key on Operation line item. Is there a user exit or BADI available in Plant Maintenance that can be used for Automatic time confirmation?
    I went through some of the user exist/BADI in PM and didn't find anything for automatic time confirmation. The only thing that I found useful was user exit CONFPM03 (which allows to carry our own checks once and operation is selected for confirmation).
    Appreciate your responses. Thanks

    Hi ,
    Normally thru confirmation we enter actual hrs worked in IW41 .. but if you do not want to run that tcode then not sure of any BADI but i would suggest you to create a Z Programme which runs as a batch job at some 30min everyday . The Z Programme checks all the PM orders of particular order type  which are with  released status and then gets into operations and checks for standard text and if its value is DONE then calls programme SAPLCORU - IW41 Programme .. you can suitably put a variant for that batch job .. plz check the option with ABAPer ..
    regrds
    pushpa

  • Confirmation for Split operation in Production order

    Hi Experts,
    I have one production order say order no. is "100000000000" and its order qty is 100pcs and in operation no. "20", i have splitted the operation into two individual capacities and allocated 50pcs to each individual capacity. Now can any one explain me or tell me the steps required for confirming the operation quantity by individual capcity.
    Regards,
    Satya.

    Hi,
    Thanks for your response on my post.
    As you mentioned I am using T-code CO11N for Production confirmation, but in this screen if I select operation no. 20, by default, system is read work center from production order "operation overview" screen. Now I want to capture the confirmation quantity against "induvidual capacity" and want to see some reports based on "induvidual capacity" level of the same work center.
    Could you pl. advise on this.
    Regards,
    Satya.

  • TIME TICKET CONFIRMATION IS NOT EXICUTING AT SUB OPERATION

    Hi,
    We are trying to post Time ticket Confirmation at sub-operation level
    through standard web service. Up to Operation level,standard web
    service is working fine but problem arises when we do posting at sub-operation
    level.Web service is not working for sub operation level.
    Please find attached step wise details of the process which we
    are following.

    Dear Sir,
                   As per your reply I have set the Act. Data in OPK4. Screen areas in OPK0 for Dates were already set open. After doing the OPK4 settings if I am setting execution start and finish time for a phase in COR6N as 10:00:00 and 10:15:00 accordingly in the order for that particular phase in the details screen start and finish time (in the Dates tab) is updating but in the Qty/activities tab the confirmed time is not updating to 0.25 hrs (it is showing 0). Even during COR6N after putting start and finish time in the Dates tab the activity in the u201DTo confirmu201D tab is not updating . When I click actual data in COR6N screen, that activity(time) is picking up the value as per the scheduling through recipe. And only if I manually change that time to 0.25 hr, then it is updating in the Qty/activities tab in details screen of that phase in the order. But I want to select the Execution start and Finish time in Dates tab of COR6N and want the system to update the figure in Activities tab of COR6N as the calculated difference between start and finish and the same updated value should be transferred to the Qty/activities tab of the phase details in the order. Please suggest how to achieve this....
    Regards,
    Sunit

  • Need to confirm production order on operation,sub-operation & sub-sub-operation

    Hi Friends,
    I've a requirement to confirm order below sub operation level. eg There is operation 100,200,300....and sub operation 110,120,130...further, below these sub operation, there is sub-sub operation like 111,112 for sub operation 110 and 211,212 for sub operation 210.
    Requirement is,till sub operation we can confirm the order but below this level we can't confirm.Is there any solution in standard SAP.
    Thanks
    Pankaj

    Dear Pankaj,
    What is the reason behind creating a sub-operation for another sub-operation?
    For meeting what business requirement, this has been mapped so?
    In my understanding this is not possible in standard SAP.
    Check and come with your further queries.
    Regards
    Mangalraj.S

  • Collective confirmation for operation

    Hi expert
    my requirement is below.
    suppose in my maintenance order I have three operation
    operation 1 with 8hrs 4 person with 2 hr each
    operation 2 with 6 hrs 3 person with 2hr each
    operation 3 with 4 hr 1person with  4hr  
    Ii go in IW48 collective confirmation there i do confirmation for only  operation 1. save it
    next time again I go in iw48 I expect remaining two operation should come in list as for first operation is finally complete.
    but it not happens . it is display in list and shows worning meassage for  operation 1 while doing again confirmation .
    worning meassage is fine but I want even that operation should not come in list . only those operation who are not confirm that should only dispaly in list
    how to do this ??
    Regards,
    prasad

    Hi Narasimhan
    Thanks
    but I tried that also .
    this status is system status for order right ?
    what happens ......my orderr is having three operation outof this 1 is finaly completed and two are partially . So my order status remains PCNF .  so now if I put PCNF status in said field then also all three operation get displayed in next screen
    where I want only two operation for which confirmation is not done that should display
    one more thing .. ....................when I put selection criteria in IW48 ,in next screen I can able to see all confirmation no and order no matching the criteria .then I select confirmation no and click on ALL ACTUAL DATA button. this showns me conifrmation details and shows error for those  finaly completed
    Is this right way to make collective confirmation ??
    regards,
    Prasad

  • Reg.Sub operation

    Hi all,
      How to create sub operations in Routing and how to confirm it.Please guide me with detailed Explanation.
    Thanks in Advance,
    M.Badrinarain.

    Hi,
    Say for example you have an operation 0040 and you want to perform the operation on 3 machines so you will use sub operations.
    Operation Sub operation work center
    0040
    010 1111
    020 1112
    030 1113
    Maintain timings like set up, machine & tare down as per your requirement for every sub operation.
    Next do confirmation in TCode: CO11N. Give only timings for sub operations confirmations and give quantities at operation level confirmation.
    You are not getting sub operation field in T Code: CO11N, then goto T Code: OPK0.
    There select one confirmation Profile consisting of suboperation in Header, then mark that particular as Standard profile. i.e Activate it in main screen of T Code: OPK0.
    Then you will get suboperation also in T COde: CO11N
    Regards
    Jagadeesh K

  • Auto Confirmation for combined order with quantity distribution

    Dear All,
    we need your help that we have using the auto-confirmation for normal production order , but got the problem in combined order confirmation for final operation , in final operation we are not getting quantity distribution with respect to child order.
    please suggest any BAPI is there?

    Not possible in standard system.

  • More than one work center for one operation

    Hi Experts,
    Is it posssible to assign more than one work center to one operation,in a maintenance order?
    for example if head fitter and helper has executed maint.activity,how we can do this
    Thanks in advance
    Regards
    Prashil

    Dear,
    You cannot assign more then one workcenter to a one operation.
    But you can assign to a sub operation,i.e to operation one workcenter and to suboperation anotherworkcenter.
    For Sub-operation:
    Go to task list change >>> Operation tab.
    Let say your first operation number is 0010. Then below it for next operation change operation number to 0010 and next to it there is field for sub-operation give there number 0001 or 0010 as per your requirement. Select suitable control key and work center, give description and press enter. your sub operation 0001 will be created for operation 0010.
    I hope it will solve your query,
    Thanks,
    Mohit

  • Good Movement at the confirmation of an operation

    Dear All,
    I tried to make good movement when I maked an confirmation for an operation.
    I configured whit TC: OPK4 automatic good movement and whit TC: OP67 I choosed option automatic good movement for control key.
    However, when I maked an confirmation (TC: CO1F), the system didn't propose the material from BOM, for issues, or the finished good to get in stock.
    And an additional question: if I have many operations on the routing and each of them have the same control key (PP01, for example) the system cannot accept any automatic good movement.
    What can I do in this case?
    Thank you very much for the answers.
    Regards,
    Marian

    Hi,
    You are trying progress confirmation right...
    As per my knowledge for production order confirmation you could findth egoods movement...
    in CO15 or CO11N...
    For th e second question if u have N number of operations then you could confirm operation wise in CO11n and for first operation goods issue and for the final operation goods recipet will happen
    Regards,
    sravanthi
    Edited by: Sravanthi683 on May 21, 2009 10:34 AM

  • How to maintain sub-operations?

    Hi all,
           How to maintain sub-operations? I am not able to do it as as soon as I enter the operation data the field for sub-operation disables, kindly let me know what to do?
    Regards
    MANS

    Dear,
    Insert the "Main operation number" again at Operation field and give the "new number" for Sub opetaion number at SOp.field in the opreation Overview of CA01.
    Steps are as,
    1. Create the operation as usual (say 0010)
    2. In the next line again give the main operation number & in the Suboperation column i.e. column next to operation i.e. in SOp enter the suboperation no u want i.e. say 0002.
    The moment u enter Sub operation no and press enter; system will prompt u to enter time for activities and finally it is created...
    U will observe that whenever there is a suboperation; there is no check box under sub operation where as in 0010 you can see that check box (Column before Base Qty). Also u click on that Sub operations and can see the details within it.
    Hope it will work for you.
    Regards,
    R.Brahmankar

  • Problem in BOM explosion for a operation Sub Contract.

    Hi All,
    Please advise how to explode a BOM or Assign component in a Purchase order with Item category (L) for a Operation SubContract External Processing  oriented material for which no material code is created from a Series Operation production order .
    Actually in my scenario, no raw material component will send to the Sub -Contract Vendor. Only Assembled operation material lets say operation 20 from a routing ( which is not having material code ) from an In - house production from a shopfloor has to be sent to the vendor to create a operation 30 material , which is also not having a material code." How to explode a BOM or component allocation for the Non- codified Item in a PO".
    regards,
    YK

    Hi
    Change the control key of the operation to PP02. System will prompt u to PR data screen where u have to tick on Subcontracting checkbox. Enter other mandatory field like material grp, cost element, purchasing grp etc. On saving system will create PR with line items. System will trigger the components reqmt based on the assignment to operation. Example if for operation 20, materials M1 & M2 are assigned, then in the PR u will find M1, M2 in the component screen which u have to send to the vendor.
    Hope it is clear to u.

  • DB-Table PO for time to confirm for each actvity type (operation)

    Hello All,
    I search the DB-Table for the time to confirm for each activity type (operation/production order).
    (CO03>operation details>qty/activities-->to confirm).
    I have found the following tables - but without success:
    AFRU
    AFVC
    AFVV
    PLPO
    I search not the standard vals (AFVV). Who can help me?
    Thanks & regards
    Sascha

    Sascha,
    Table AFVV has the details:
    Standard Values:
    VGE01     VGWRTEH     UNIT     3     0     Unit of measure for the standard value
    VGW01     VGWRT     QUAN     9     3     Standard value
    VGE02     VGWRTEH     UNIT     3     0     Unit of measure for the standard value
    VGW02     VGWRT     QUAN     9     3     Standard value
    VGE03     VGWRTEH     UNIT     3     0     Unit of measure for the standard value
    VGW03     VGWRT     QUAN     9     3     Standard value
    VGE04     VGWRTEH     UNIT     3     0     Unit of measure for the standard value
    VGW04     VGWRT     QUAN     9     3     Standard value
    VGE05     VGWRTEH     UNIT     3     0     Unit of measure for the standard value
    VGW05     VGWRT     QUAN     9     3     Standard value
    VGE06     VGWRTEH     UNIT     3     0     Unit of measure for the standard value
    VGW06     VGWRT     QUAN     9     3     Standard value
    For actual values confirmed:
    ILE01     CO_ISMNGEH     UNIT     3     0     Unit of measure for the activity to be confirmed
    ILE02     CO_ISMNGEH     UNIT     3     0     Unit of measure for the activity to be confirmed
    ILE03     CO_ISMNGEH     UNIT     3     0     Unit of measure for the activity to be confirmed
    ILE04     CO_ISMNGEH     UNIT     3     0     Unit of measure for the activity to be confirmed
    ILE05     CO_ISMNGEH     UNIT     3     0     Unit of measure for the activity to be confirmed
    ILE06     CO_ISMNGEH     UNIT     3     0     Unit of measure for the activity to be confirmed
    Hope this is useful.
    Regards
    Ram

Maybe you are looking for

  • Calendar events not showing in ical

    when i input an event or an invoice out of quickbooks as an all day event it puts the from: date later than the to: date. and does not show up in the calendar until i go in every time and change it to match or make the from date earlier than the to d

  • How to print from an ipad

    Does anyone knows how do I print from an ipad?  The screen on the ipad shows the message "looking for printer" but it does not recognize my Hp Wireless printer which is already configured to the same ISP. Then appears a message "No AirPrint Printers

  • Aperture  and blurb

    Is there still not a plug-in for using Blurb with Aperture?  If not can someone please direct me to the best way to use Aperture and then Blurb as I would like to try their publishing as well As direct via Aperture (they have more options) Also, re t

  • Trying to "See" time capsule on samsung tablet. Can it be done?

    Trying to see our time capsule from a samsung tablet, can it be done?

  • Server Instances

    Hello All, I would like to do more than 200 conversions at a time which sends input to server for exporting indd to inx. I don't know how many instances the server supports at time? Can someone tested this? Thanks, shail