Anybody will explain about Order Acknowledgement , Confirmations and Inbound
Delivery Process.
Thanx,
Key.

Monitoring Vendor Confirmations
Use
The confirmation monitoring facility enables you to check whether the expected confirmations
have been received and whether the delivery quantities and dates are as you requested. The list
analyses that are available for monitoring purposes provide you at all times with an overview of
the status of your purchase orders and their influence on materials planning and control.
Prerequisites
_ Analyses are only possible for items having a confirmation control key.
_ You can specify the deadline for receipt of confirmations for each confirmation category in
Customizing for Purchasing (Confirmations _ Set up confirmation control under Confirmation
sequence.)
You can specify in Customizing that you wish to see the following in the monitoring list,
for example:
_ Which order acknowledgments have still not been received a certain number of days
after the PO date
_ Which shipping notifications have still not been received a certain number of days before
the delivery date
Activities
To monitor vendor confirmations, choose <Purchasing document> ___Reporting___Monitor
confirmations.
Order Acknowledgment Expediters
Use
You can send messages to vendors urging them to submit outstanding order acknowledgments.
You cannot issue such messages with respect to other vendor confirmation categories.
Prerequisites
A prerequisite is that the Acknowledgment requirement indicator has been set in each relevant
PO or scheduling agreement item.
Activities
Choose <Purchasing document> _ Messages _ Monitor order acknowledgment.
If the indicator has been set, the system proceeds as follows when the reminder program is run:
It checks whether the confirmation control key has been set:
1. If it has not, it checks whether the acknowledgment number has been entered. If there is
no such number, a message urging the vendor to submit the overdue acknowledgment is
issued.
2. If it has, the sum of the quantities from all previous order acknowledgments is calculated.
If the result is less than the order quantity, an urging message (expediter) is issued.
Creating a PO or Outl. Agreement w. Acknowl. Reqt.
1. Create a purchase order or an outline purchase agreement and maintain the items.
2. Select the item to be acknowledged by the vendor and enter a confirmation control key in the
Deadline monitoring area of the item detail screen.
If the confirmation control key provides for the submission of order acknowledgments by
the vendor, and you wish to urge the latter to do so in the event that they are still
outstanding after a certain period of time, set the Acknowledgment requirement indicator.
3. Save the purchase order.
If you wish to work exclusively with order acknowledgments (i.e. without using a
confirmation control key), your only option is to set this indicator. You need not make
any other entries.
Monitoring Confirmations
Monitoring Confirmations in PO or Outline Agreement
1. Select the item for which you wish to see the accumulated confirmations and choose Item _
Confirmations _ Lists.
2. Then branch to one of the following lists:
– Quantities relevant to MRP
– Quantities that have been reduced/offset with regard to MRP
– Cumulative quantities
A line from a PO delivery schedule covering 100 tons of steel is reduced to zero as a
result of the relevant order acknowledgment for 100 tons. The subsequent inbound
delivery of 100 tons in turn reduces the order acknowledgment quantity to zero, and,
finally, the GR of 100 tons completely offsets the inbound-delivery quantity.
Monitoring Several POs or Outline Agreements
1. Choose Purchase order _ Reporting _ Monitor confirmations.
2. Specify an interval of purchase orders and enter the category of confirmations to be
monitored (for example, AB for order acknowledgment).
3. Choose Program _ Execute.
You obtain a list of all variant quantities and delivery dates.
Manual Maintenance of Confirmations
1. Change the purchase order or scheduling agreement.
2. Select the item for which you wish to enter a confirmation and choose Item _
Confirmations _ Overview.
3. On the confirmation overview screen, maintain the confirmation category, date, time-spot,
and quantity, as well as the confirmation number used by the vendor.
You can also receive a confirmation with respect to a material with a manufacturer part
number (MPN). For more on this topic, refer to Manufacturer Part Number (MPN) [Page
452]).
If you work exclusively with order acknowledgments (i.e. without using a confirmation
control key), enter the acknowledgment number on the item detail screen. This
number can be any identifier customarily used in your enterprise (e.g. the date of the
order acknowledgment or an external document number).
If you wish to enter the same number for each item, choose Edit _ Fast change.
Quantity Checks
_ If a vendor notifies a quantity that is greater than the still-open notified quantity, the system
issues a warning message.
_ If the cumulative quantity from all inbound deliveries relating to a PO item exceeds the order
quantity (taking the overdelivery tolerance into account), the system issues a warning
message.
This warning can also be defined as an error message on a user-specific basis.
_ If the cumulative notified quantity is less than the quantity already delivered, a warning
message is issued.
Depending on your settings in Customizing, an indicator showing whether or not the data in the
confirmation is used in materials planning is set in column D. If the indicator has not been set, the
data is for information only.
In column E, you can see whether the confirmation was entered manually in the PO (1), or
generated automatically upon entry of a shipping notification using the function Create inbound
delivery (2).
Creating Inbound Delivery Against Shipping Notif.
1. Choose Purchase order _ Inbound delivery _ Create.
2. On the initial screen, enter the vendor, the delivery date and the PO number. You also have
the option of entering a transport identification code (e.g. a vehicle registration number). In
this way, deliveries for several purchase orders can be grouped together.
If you do not know the PO number, choose Inbound delivery _ Select purchase orders
and enter selection criteria.
Choose Program _ Execute.
You obtain a list of the purchase orders from the specified number interval that contain
still-open notified quantities.
Select the relevant purchase orders and choose Adopt selected.
3. Press ENTER. The overview screen with the suggested quantities appears.
The default quantity is taken from the PO item. However, you can overwrite this
suggested quantity and enter a different unit of measure. In order for this to be possible,
the desired unit must be defined as an alternative unit of measure in the material master
record with the appropriate conversion factor.
All quantities (e.g. the notified quantity) are converted into the order unit and recorded in
the purchase order by the system.
You have a PO for 100 tons of Steel 1, and the vendor sends you a shipping
notification for 5 crates. You wish to enter the inbound delivery in the unit of
measure „crate“. The system checks whether the alternative unit of measure can be
converted into the order unit. If so, you can save the inbound delivery in the
alternative unit.
A batch split can be made in the inbound delivery, which is taken into account in the
confirmation overview for the purchase order and at the time of goods receipt. If the
batch split is to be taken into account at the time of goods receipt, the confirmation
category Inbound delivery must be confirmation-related (GR assignment indicator).
4. Check the data and make any necessary changes.
5. Save the document.
After this, the confirmation overview is updated in the relevant purchase orders.

Similar Messages

  • PO Confirmation Date (OA) & Inbound Delivery Date  Report

    Dear All,
    Please let me know SAP Standard Report
    PO Confirmation Date (OA) & Inbound Delivery Date  Report
    Regards
    Amey

    Hi,
    I guess ME2A will give u unconfirmed orders that require a confirmation, but have not yet been confirmed according to the dates configured for your monitoring period. First, ensure that you have such an order
    Also, ensure that your confirmation control (OMGZ) has BOTH a value in Monitoring period AND Reference date.
    Pls chk note for more information.    https://service.sap.com/sap/support/notes/500502
    BR,
    Krishna

  • Confirmation control key check for inbound delivery creation

    Hi,
    Currently, in the Client's company, the process of receiving goods from purchase orders looks like that (SAP-wise):
    - create a purchase order,
    - receive goods using MIGO and automatically create an inbound delivery,
    - pack the delivery and post goods receipt.
    Recently, some patches have been installed, including one described by note 1602047 (which basically enforces checking confirmation control keys if goods receipt assignment and goods receipt relevance are activated for inbound deliveries). Note says that it only affects two-step stock transfer and creation of automatic inbound deliveries using SPED output but it seems it also affects other basic processes like PO receipt in MIGO.
    Now, when using the old control key (that had MRP-Relevant and GR-Relevant fields checked), the system is unable to automatically create an inbound delivery after the goods receipt is posted with MIGO (with message VL148 - Not possible to create an inbound delivery). I learned that this is because the "GR Assignment" field must be checked in the confirmation control key so it's possible to automatically create aninbound delivery after receiving a purchase order in MIGO.
    After changing the confirmation control key to have the missing field checked it's not possible anymore to receive goods from PO in MIGO as the PO requires shipping notification in order to be processed in MIGO thus requiring of manual creation of an inbound delivery.
    Is there any way to skip this check so the process would remain the same (this model has been working fine for few years in the Client's system) and the inbound delievery would be created automatically after posting the receipt in MIGO?
    Thanks in advance,
    Piotr

    Hi,
    don't know if you found a solution, but we received the following message from SAP:
    The advent of the new version requires some attention to the users. It
    was necessary to avoid inconsistencies which in the past version the
    system was susceptible.
    Main Program SAPMM07M
    Source code of MM07MLVS
    sy-msgid VL sy-msgty E sy-msgno 148
    I have checked the process and through debugged I could confirm the
    following information SAP is providing to all similar incidents reportedfor us:
    Error message VL 148 is issued if in the confirmation control key used
    in the purchase order, the fields for MRP-relevance (T163G-KZDIS),
    GR relevance (T163G-WEREL) and GR assignment indicator (T163G-WEZUO)
    are not set.
    The correction of note 1602047 was necessary to avoid inconsistencies
    (table EKES) in the purchase order. Without having the GR assignment
    (T163G-WEZUO) set, there is no unique reference created between the
    purchase order history (table EKBE) and the inbound delivery
    confirmation (table EKES) at goods receipt which leads to a problem if
    several inbound deliveries exist for the same purchase order.
    If you set T163G-WEZUO to 'X', this assures that, for an inbound
    delivery, the confirmation record (EKES) belonging to this inbound
    delivery (EKES-VBELN) is also accurately updated at goods receipt.
    How to solve the issue?
    Use a confirmation control key with the GR assignment indicator set
    and then create the inbound delivery with VL31N. If you want to be able
    to create the inbound delivery with reference to a certain line item in
    the PO, use transaction VL34.
    If you still want to use transaction MIGO, there is the following
    workaround:
    - Create a purchase order without any confirmation control key
    - Create a goods receipt (GR) in transaction MIGO with reference to this PO and post the GR to a non-HU-managed storage location
    - Create a transfer posting with MIGO using movement type 311 to
    transfer the goods from the non-HU-managed storage location to the
    HU-managed storage location.
    As the transfer posting is an additional step for the user, the whole
    process could be automated using a partner storage location
    (T001l-PARLG) for the GR which then triggers (through a modification)
    the BAPI 'BAPI_GOODSMVT_CREATE' to create the transfer posting without
    user interaction.
    I hope to have satisfied you on the reason why it is now happening and
    also I believe you can explain to business that it is a new behavior
    necessary done from SAP side to avoid worse situations, we are aware of
    potential dissatisfaction it might cause. SAP Support is always
    available to clarify any issue.
    Sorry for not having a more positive answer.
    I hope it helps!
    Leentje

  • Generating Inbound delivery based on Vendor Confirmation for Purchase order

    Is there a way to create Inbound deliveries based on Vendor confirmation for a purchase order.
    Here is the complete scenario.
    Buyer Creates the PO for qty 100 and Date August 29
    Vendor Confirms that he can supply a qty of 50 for August 29 and remaining 50 for Sep15th
    Based on vendor confirmation, Buyer creates 2 vendor confirmations (AB) to match with the data received from Buyer, without modifing the PO.
    Requirement:
    Inbound deliveries should get created based on the vendor confirmation.
    As MRP looks at Inbound delivery for Planning purposes once they are available, Inbound delivery should match with vendor confirmation data.
    Is it possible to get this requirement met with standard config available in SAP.

    could you eventually get the answer from the docu Set Up Confirmation Control

  • How to skip the Inbound Delivery while updating LA confirmations via EDI

    Hi Experts,
    I have a requirement wherein I dont want to create Inbound Delivery automatically when updating the LA (or a copied Conf Cat of LA) confirmation via EDI.  When we are using the message type DESADV, LA confirmations are being updated, but simultaneously, the Inbound delivery also being created.  My client desires that Inbound Delivery should not happen and only LA confirmation should be updated via EDI.
    Is there anyway, by which we can skip the Inbound Delivery while updating the LA confirmations in the PO?
    Thanks in advance
    Regards
    Radha Krishna

    Hi Prabhaharan,
    Thanks for your quick response.
    My requirement is to have both AB and LA confirmations.  I have included these two in a new the conf control   So, your suggestion will not work.
    Is there any other way out to fulfill my requirement?
    Thanks & Regards
    Radha Krishna

  • How can I delete an Inbound Delivery with HUs and Confirmed TOs?

    Hello Guys,
    My client  has an Inbound delivery created from a PO line item. The goods receipt could be reversed through Vl09N so a 102 material document has been created. The problem now is that he wants to delete the ID (Vl32N) and it still has OTs confirmed with HUs created. Do you think it could be possible to delete this Inbound Delivery? Which would be the correct steps???
    Please ADVICE!

    Hi,
    Not possible to delete the IBD if it has material GR done and confirmed TO.
    \\ Shankar

  • IDoc type "DELVRY03" for INBOUND delivery confirmation and Outbound Deliver

    Hi ,
    We have a requirement where we have to send Inbound delivery confirmation as well as outbound delivery notification to our same customer. (3PL case)
    We have a EDI partner who is receiving our messages and transforming them before sending it to customer.
    Now my problem is , since I am using same idoc type (DELVRY03) for both cases therefore wondering how my EDI partner will differentiate whether received message is a INBOUND delivery confirmation or OUTBound delivery notification.
    regards
    Shrey

    Thx for your reply ...
    Wondering about the impacts , if I create a new message type like ZDESADV and attach it to DELVRY03.
    In this i could have two message types DESADV and ZDESADV.
    Will it impact anywhere ?
    Regards
    Shrey

  • IDoc Message Type to create Inbound Delivery + Confirm +  GR

    Hi Experts,
    I need IDoc message type which can create Inbound Delivery / Confirm / Create GR with Inbound Delivery as reference and i dont want to use DELVRY05
    because I need to create Inbound Delivery / PICK / Confirm but not with Transfer Order Creation means Unnecessarily  we dont want to create Transfer Orders. We need to exclude Transfer Orders and create GR.
    Please do the needful.

    Dear Kishore,
    It's possible via writing code in enhancement spots of transaction code VL31N, MIGO_GR/MB01.
    R,
    Amala

  • How to create inbound delivery for items with no confirmation control key.

    hi Please help me with this..
    are there any user exits to create an inbound delivery for scheduling agreement items with no confirmation control key.
    my req is
    i have 12 items (me33 transaction) of them three have confirmation control key populated and out of those three 2 will be deleted so only one item is left for inbound delivery creation, but i need to have all this possible for all items with or without confirmation control key.
    thank you

    hi
    for inbound delivery there is BAdi called LE_SHP_DELIVERY_PROC... in there is method called ITEM_DELETION... in this u can flag the item to delete or not..
    this will be triggered for inbound as well as oubound delivery..
    you can check confirmation status for the PO in the table EKES... in this table there is filed called EBTYP.. using this field u can check the PO item confirmation status..
    I hope above information is helpuful for u

  • Inbound delivery duplicate in ME23N confirmation tab

    Hi guys,
    I am using ECC6 and SCM/EWM
    When I create an inbound delivery in ECC6 using VL31N and when  material is batch managed If I don't enter a batch number I
    got an incompleteness error message (batch number required) this is normal.  Then I enter a batch number and save.
    In this case the inbound delivery is show twice in ME23N this create a big issue for me because the quantity shown is double and
    it prevents me to reveive remaining quantities.
    Thanks for you help.

    Hi
    In confirmation tab of purchase order, you can see two confirmation , because one is order ackowledgement which needs to be entered manually. The other confirmations comes automatically when inbound delivery is created and transfer orders are confirmed, with goods reciept.
    Now order acknowledgement is enterd manaully, which says that your vendor has recieved purchase order and he will committ you delivery dat on which goods will be delivered.
    Shipping notification confirmation cmoes automatically while doing Goods reciept.
    You can also check that goods reciept is done for all the materials only once in  MMBE transaction.
    I hope this helps
    Br,
    Tushar

  • Confirmation key and inbound delivery

    Hi Gurus
    I am trying to do MIGO against a PO (Mvt type 101),  they system gives me an error message that PO do not have confirmation key and in some cases it creates an inbound dlivery.  I do not want to use confirmation key as well as inbound delivery.  I just want to post GR against a PO.  What settings do i need to change in the system?
    Any advice will higky appreciated
    Thanks

    Hi,
    There are two things you have to do to avoid conf. control in PO:
    1)Go to change PO "ME22N" & delete the confirmation control key from the Itel details table (tab page-Delivery Schedule)
    2)You will also have to change the configuration settings.The path is SPRPMMConfirmations--Set up confirmation control.
    Now, click on External Confirmation Category-select confirmation category LA (shipping notification)-delete confirmation control key (ASN).
    after the above is done,you can post your GR without creating inbound delivery.
    Hope this helps.
    Thanks,
    Kaveri

  • Confirmation against ECC Inbound Delivery in SRM?

    Hi Friends,
    We have business scenario wherein we would like to post confirmation in SRM (No SUS) against an ECC Inbound Delivery. We are in a Classic scenario SRM 7. 
    Can any one let me know whether its possible or not?
    We could not find Inbound delivery option in SRM for confirmation.
    Regards,
    Sandeep Parab

    Please help.
    Sandeep

  • Confirmation key for inbound delivery / subcontracting

    Hi,
    Vendor A has a confirmation key which creates a inbound delivery. For a regular purchasing, this is ok. However, the same vendor can also be used for subcontracting. In this case, we dont want a inbound delivery to be created. Is there any way to exclude a certain combination, i.e. item category, from using the confirmation control?
    Regards,
    Martijn

    Hi Martijn,
    You may want to test with inforecord.
    You can create an info record for standard material and one for the subcontracting.
    Each info record can have a different value in Confirmation Control.
    When entering the PO the confirmation control will be defaulted from the info record.
    If your current vendor master has a value in the confirmation control (purchasing view), be careful when you create your subcontracting info record because the value of the vendor master will be defaulted.  Just delete the default value and save.
    If you have any questions let me know.
    Hope it helps.
    Monica Araoz.

  • Inbound delivery quantity update with the confirm putaway quantity

    even if i set up the update indicator (1or 2) during a TO confirmation, the system do not update the inbound delivery with the quantity confirmed, especialy in case of difference.
    this option is possible during the TO creation, but not works with during the TO confirmation, could you help me?

    It works with the outbound delivery only.
    Though updating quantities in inb. delivery would be very useful for quantity difference handling.

  • Inbound delivery can be deleted despite confirmed TO

    Folks,
    I am facing a situation in which the inbound delivery has been deleted despite a confirmed TO. I believe deletion was only possible when TO status is "A" and not "C" (and "B").
    Anyone seen this before? SAP bug?
    MZ

    The WM postings are (to an extent) independant of the IM postings.
    Assuming that you are not working with HUM, you can do putaway against a delivery and confirm the TO. This does not enforce you to post the GR for delivery. If you decide to delete the delivery then obviously you have to clear the negative quant in 902.
    You can always do a GR regardless of whether putaway has been done or not. To achieve this, I think it is reasonable for SAP to allow deleting a delivery with pick status C.

Maybe you are looking for

  • How to connect my imac to appletv

    I'm having trouble connecting my imac to my appletv thats on a LG smart tv. Can anyone explain? I've youtubed it, googled it nothings working.

  • ODBC data source administrator

    Hi, I have installed Oracle ODBC driver 10.2.02. I'm trying to add a system data source in System DSN tab in Control panel/administrator tools/data source(ODBC). In the Oracle ODBC Driver configuration dialog, I select the TNS service name from the d

  • Lookup ejb deployed in wls8.1 from wls9.2 env

    hi guys i was wondering if anyone had encountered problem when looking up home interface of ejb deployed in weblogic814 from weblogic9.2? basically i have an ejb build with weblogic.appc task and deployed in wls814. this also generated a client jar t

  • Replace a character in a String array

    I have an array of strings and am trying to replace the ' character with a space. I keep getting either a cannot be applied or cannot resolve symbol error. Can anyone help? String arrayList = request.getParameter("field"); String newList = arrayList.

  • BEx variable screen to exclude values from selection

    Hi, I have a requirement in the BEx report variable screen here my user want to select values for the variable and from the values in selection on right hand user wants to exclude few values.I want the red color exclude button to appear in the screen