Confirmation of goods with "Approved" Status

Hi All,
We are at SRM7.0 and working on extended classic.
After performing confirmation of goods receipt in SRM, the status is still showing as "approved" and not "posted in backend".
Kindly let us know how to reprocess these confirmations in SRM system.
Regards
K Gp

Hi Masa,
The document status in BBP_PD is showing as I1022 (Inactive = Blank).
There is no entry with status "Currently being transferred" in Status section in BBP_PD for this confirmation.
Checked in RZ20 tcode and didn't find any error related to this.
I tried executing the FM - BBP_PD_CONF_TRANSFER and BBP_PD_CONF_TRANSFER_V2. But no success.
If there is a way to process this confirmation again then pls let me know.
Regards,
K Gp

Similar Messages

  • How to show catalog items with Approval Status:Pending in a Content Search Webpart

    How to show catalog items with Approval Status:Pending in a Content Search Webpart using cross site publishing. Thanks in advance.

    I don't think you're going to be able to. Usually Approval Status is used in conjunction with Major/Minor versioning and while Approval Status is pending the item is usually a draft.
    As a result the search crawler should not be able to see the draft items as it would not have the necessary rights to do so. (Good practice ensures that the Search Crawler has only read access and is not an elevated account for this reason)
    Paul.
    Please ensure that you mark a question as Answered once you receive a satisfactory response. This helps people in future when searching and helps prevent the same questions being asked multiple times.

  • Leave with approval status ''Work in progress''

    Hi,
    I try to delete or complete the leave with approval status ''Work in progress'' and there is no way to do that .. can anybody help .
    This issue happened when i request annual leave and the session expired .. i login again and i found the request stuck at absence summary and i can't do any thing even deleting.
    snapshot of the issue:
    http://www.2shared.com/photo/B2F8Aysg/work_in_progress_leave.html
    Thanks in advance

    Hi,
    Yes i know its not should be disabled at site level i did that on test envroment .
    i tried to put it at user but its not possible
    after i put the profile on value 'Yes' the delete and update columns appeared at absence summary with warning massege and i can delete the Leave with approval status ''Work in progress'':
    http://www.2shared.com/photo/QqRfjReY/Warning_mass-2.html
    and when i try to create new leave gave this error massege:
    http://www.2shared.com/photo/LL1sU9xB/Warning_mass-1.html
    can you guide me how can i know the earlier personalization done on the absence page ??
    thaks alot for your helping

  • Need to Display Approvers name with approval status in PR

    Hi,
    We have a requirement to display the Approvers name with the approval status(for each Approve) in the purchase requisition. the developer has all the logic to achieve this and he said we cannot display this in the release strategy tab in PR but we can display the same in the tab- Customer data at the item level since it has more space. the user came back saying we should have this information in a new tab in PR with the name Approvers overview or else in any place in PR where the Buyers can easily identify where to find the list of approver names in the PR.we don't want to create a new custom tab just for this reason in the PR item. not sure whether we can really create one.
    can you please let me know where can we display the Approvers name in the PR(item level)so that the users can easily identify those.
    just wanted to know how is this handled in your company do you display the approvers name with release status any where in the PR, if yes where do you display?
    Thanks
    Mahendra

    /* Formatted on 10/12/2011 9:57:19 AM (QP5 v5.149.1003.31008) */
    WITH ADM_MENUS
            AS (SELECT 19 menu_id, NULL parent_menu_id, 10 seq_no FROM DUAL
                UNION
                SELECT 18, 19, 10 FROM DUAL
                UNION
                SELECT 20, 18, 30 FROM DUAL)
        SELECT menu_id,
               parent_menu_id,
               seq_no,
               CASE CONNECT_BY_ISLEAF
                  WHEN 0
                  THEN
                     REPLACE (SYS_CONNECT_BY_PATH (seq_no, ','), ',', '0')
                  ELSE
                     SUBSTR (REPLACE (SYS_CONNECT_BY_PATH (seq_no, ','), ',', '0'),
                             LENGTH (SYS_CONNECT_BY_PATH (seq_no, ',')) - 5)
               END
                  disp_seq_no
          FROM ADM_MENUS
    START WITH parent_menu_id IS NULL
    CONNECT BY PRIOR menu_id = parent_menu_id
    19          10     010
    18     19     10     010010
    20     18     30     010030

  • Importing PO in approval status

    can we import Project coded POs in Approved status or if there is an API to achieve this without having to trigger PO Approval workflow.  Several years ago, as part of Procure.Net project in 11.0.3 version, we used to trigger the Requisition Approval work

    Yes.. you can import the PO with approved status and project using PDOI (Purchase Document Open Interface).
    Following 3 interface tables are used to import the PO.
    PO_HEADERS_INTERFACE
    PO_LINES_INTERFACE
    PO_DISTRIBUTIONS_INTERFACE
    You have to populate the project id to import the po with project no.
    Oracle Apps: Purchase Order Interface

  • GL Interface (Approval Status ) problem

    Hi All,
    I have successfully imported Payroll data to GL Journal using GL Import Program (GL Interface) with APPROVAL STATUS  =  N/A
    Now, My requirement is that the APPROVAL STATUS of journal should remains REQUIRED after importing Journal.
    Can anyone help/guide me ?
    regards
    Sanjay

    Hi Sanjay,
    If i am right, the way you set up the journal approval for a source is by doing the following settings:
    1) Enable Journal approval at the SOB level
    2) Enable journal approval for the source at the Journal Sources window for the particular source i.e. Payroll
    3) Thereafter when you import the journal for the payroll data, using the GL interface the status of the approval flag will be set to required.
    Please correct me if i am wrong.
    Thanks
    Manish Jain.

  • SRM 5.0 Confirmation in Awaiting Approval Status

    We have the confirmations in "Awaiting Approval" status.
    I had checked the following steps but still the status remains as-is.
    1. Transaction SWUD
    2. Enter workflow WS10400010, press enter
    3. Execute 'Test environment'
    4. Check 'Including subworkflows'
    5. Execute 'Consistency check for components'
    There are no errors for BUS2203 (Confirmation business object).
    I have cross checked the BUS2203 for WS10400010 Active Status is both T-Codes SWETYPV and SWE2.
    We had a previous issue of BUS2203 with some errors and that went away after following steps in OSS Note and SDN comments. Note 962488 - "Workflow definition '&' not in version '&' (WD 401) and SDN.
    WS10400010 is No Approval Workflow for confirmations that is active and classified as General Task.
    Can you please advise on this status issue?

    Please analyse the Workflow log from SWI2_FREQ. I think you can check this issue in SRM forum. I think this is discussed.
    Thanks
    Arghadip

  • Confirmation ending in Awaiting for Approval Status

    Hi Experts,
    The Confirmation of Goods receipt was working fine till last month. Now For some PO's Confirmation is going to Awaiting for Approval status this is happening only for few PO's and for others PO's Confirmation is happening properly and the status is Posted in Backed.
    I observed that Workitem ID is not created for those confirmation's which are in Awaiting for Approval Status. 
    Please help me resolve this issue.
    Any valuable inputs are Appreciated.
    Thanks and Regards,
    Devananda A J

    Hi,
      First point if you make a GR confirmation means the PO change version will be generated and the PO  workflow will restart for the PO change version.
      Goto BBP_PD  and enter PO number check the PO change version is closed or not. If it is not closed then PO change version workflow will be in Error. If it is in Error then GR confirmation workitem will not be genrated.
    all these things will happen because of if you create a GR confirmation or any changes made to PO when the PO status is still in Transfer status.
    regards,
    Devi

  • Buyer change the PO line items and end up with Awaiting Approval status.

    Can you please help to look into this issue.
    1.Buyer change the PO line items and end up with Awaiting Approval status.
    2. But user claim that she got enough limit and should not route to her manager's approval. Also check with her manager and this PO do not exist his queue.
    Any clue or tips on how to investigate on this issue. All your tips are appreciated,
    -Rick

    You cannot change these POs because their changed version has status
    'Deleted'. My proposal to fix them will be the following:
    You will have to set changed version as closed(DOC_CLOSED set to X)
    and in active version set DOC_CLOSED to space.
    __-For the above statement, Can you guys please let me know, which table DOC_CLOSED belongs to and what are the steps to do this, as i come from a functional back ground.__

  • SC with awaiting approval status and no work item for Approvers.

    Hi Experts,
    We are implementing Classic scenario with SRM7.0 and we are having Application controled Workflow.
    We are fasing issue in workflow. On SC getting ordered the status is showing as awaiting approval and there is no work item found in BBP_PD.
    When we approve this SC in SWO1 then there is no PO getting created.
    If the SC value is less than spend limit we have enabled no Workflow and in that case the approval agent table is showing as System Approver and after SC getting ordered the SC is still with the status Awaiting approval.
    Can any once have an idea how to go about with this issue.
    Regards,
    B.N.Karthikeyan

    Hi,
        Did you check the event linkage in SWE2? what do you see in SLG1? Did activate the task groups 40000003 and 40000007? also check in SM58 and SM21..
    Saravanan

  • Standard Report, for checking the PR approval status by a certain User

    Hello Experts,
                          Is there any standard report in the SAP where we can find out for the given managers, if level 1 approver is Mr. X, then which all has been approved by Mr. X and and pending with subsequent approvers?
    Please help.
    thanks and regards,
    Yawar Khan

    Hi,
    Yes, standard report is available for PR approval status list using T-code ME5A - List Display of Purchase Requisitions and the following input data's are given .
    Purchasing Group                  :    ___
    Scope of List                         :  ALV
    Plant                                       :  _____  (if required)
    -  Assigned Purchase Requisitions to be ticked.
    -  Released Requisition Only to be ticked.
    -  Requisition for overall Release to be ticked.
    -  Requisition for Item-wise Release to be ticked.
    Now execute the report and then report top layout button click for  'Release indicator' option selected for released status confirmation purpose.  If release indicator status is 'X' means PR released, otherwise PR is not released.
    Hope, it is useful for you.
    Regards,
    K.Rajendran

  • Approval Workflow does not update the Content Approval status if started automatically

    Hi,
    I’m using a simple Approval Workflow associated with
    Content Approval on site pages. It works fine when I set it to be started manually (by using
    Allow this workflow to be manually started by an authenticated user with Edit Item permissions
     option) and on the completion of the workflow the
    Content Approval status is updated accordingly. But when I set it to be started automatically (by using
    Start this workflow when a new item is created
     / Start this workflow when an item is changed
    options), it does not updates the Content Approval status. Note that I’ve set the
    Update the approval status after the workflow is completed (use this workflow to control content approval)
    option to true.
    Regards

    Hello,
    It is recommended to select "Start this workflow to approve publishing a major version of an item" when you want to use the workflow to manage content approval for
    a library.
    According to the Notes for “Enable Content Approval” option in
    this reference:
    If you are using this Approval workflow to manage content approval (moderation) for a library, and you selected the Start this workflow to approve publishing a major version
    of an item check box on the Add a Workflow page..
    If you did not select the Start this workflow to approve publishing a major version of an item check box on the Add a Workflow page because you do not want this workflow to
    be the default content approval workflow for a library, you can select the Update the approval status (use this workflow to control content approval) check box to make this workflow a secondary content approval workflow that specific users can
    start manually.
    That means having an approval workflow start automatically when a document is changed or created is not a good practice when you want to use the workflow to manage
    content approval for a library. You should either select "Start this workflow to approve publishing a major version of an item" or give users the option to start the workflow manually at the time they want to submit for an approval.
    Thanks & Regards.
    Lily Wu

  • Approval status of PR is in process, but action history show 'Approve'

    Dear all,
    I am on EBS 11.5.10.2 and encountered a problem during the approval process of PR.
    The approval hierarchy with PR is planner -> approver1 -> approver2,
    and approver2 is the final approver.
    Everything of the approval process is OK except that the action performed
    by approver1 shown in Action History is 'Approve', but not the appropriate
    'Forword'.
    Sequence Performed By Action Approval Status
    0 planner Submit
    1 planner Forward In Process
    2 approver1 Approve In Process <---- Here the 'Approve' action should be shown as 'Forward'
    3 approver2 Approve Approved
    Any ideas will be greatly appreciated!
    Regards,
    Henry Huang
    Edited by: user8960428 on 2011-7-7 上午8:13
    Edited by: user8960428 on 2011-7-7 上午8:15

    For requisitions the action taken by the approver is recorded. If they click on Approve, the same is recorded in action history.Shivaraj, for POs with the similar position hierarchy, if the approve1 click on Approve, action history does show 'Forward'.
    Do you mean the action taken by the approver1 is different between Requisitions and POs?
    Edited by: user8960428 on 2011-7-12 上午8:03

  • Update a site column dynamically to Approval Status

    Hello all this is what I have;
    InfoPath form with Form Status field (Form Status promoted to SP form library as site column) form switches to read only view when Form Status = Approved
    SharePoint form library set to require content approval
    Copied and modified OOB Publishing Approval workflow with Association column, Form Status added,
    As it stands, the work flow runs and updates the list item, Form Status, to Approval Status, unfortunately Approval status is set beck to pending (which is correct behavior I assume) I need some help! can I insert the Update list item action in the workflow
    task steps? I want Form status to start as pending and then reflect whatever Approval Status value is.  This is my first attempt at modifying an OOB workflow, is this the right approach?
    Thanks for any help, I have tried several solutions but I am definately missing something. Should the workflow restart on item change? should I have versioning turned on? all I am trying to accomplish is have the form switch to read only if it's approved and
    then if for some reason someone needs to make a change I need Form Status and Approval Status to have the same value.

    Hi,
    If you only want to approve content, you can enable content approval.
    If you want to manage versions, you need to enable content approval first and then enable version.
    More information:
    Require approval of items in a site list or library
    Enable and configure versioning for a list or library
    Best Regards,
    Linda Li
    Linda Li
    TechNet Community Support

  • How to Control authorization for users with certain status for level 2 WBS Element

    Dear All,
    Is there any standard way or enhancement available to control authorization for users with certain status for WBS Element i.e. for example
    Pre-requisite:
    There is only 2 level of project i.e.
    Lev_ WBSE_______Description
    1___ 7-14.E_______summay outage controller
    2___ 7-14.E.2310__ Plant/unit # 2310
    2___ 7-14.E.2310__ Plant/unit # 2220
    Project Controller  (authorization role assigned "Z_PS_OP7_OTGCON_C") have all project level authorization
    Plant/Unit Controller (authorization role assigned "Z_PS_OP7_PLNTOTG_C_2310") have only level 2 authorization with enhancement that we did in system by Z table.
    User ID_ Plant #
    123345_ 2310
    122455_ 2220
    Issue:
    After System Status released and User Status approved the WBS basic date for Plant/Units should be restricted from updating/changing by Plant/Unit Controller level and only project controller should have this authority.
    Solution required: 
    Can any one tell how to control this scenario either by standard or enhancement available to control authorization
    BR
    Saqib Usman   

    Hi,
    Did you explore SAP Enhancement CNEX0002 Using Transaction CMOD?
    Thank you and regards,
    Varshal Kachole
    The SCN Rules of Engagement

Maybe you are looking for

  • Need to show total of condition result only not the detail

    Hi, I've created a query to report the number of shopping carts with a value over $1000 for a given period of time.  I included the shopping cart and its value in the query but do not display them.  Then I created a condition to keep only those > $10

  • Multiple libraries, Pbook/Pmac, advice for management & updating please.

    Hi Everyone, I travel frequently, and am looking for suggestions to keep all my iPhoto libraries up to date. I currently have a g5, Powerbook, and Mini. I just upgraded to iPhoto 6 and I have several thousand photos on my Dual g5. I just came back wi

  • Adding Images to the folders

    Hello All, Kindly let me know how I can attach an image to the Content Management folder and show the image along with the folder name on the portal? Do I have to use different UI? Any Ideas or suggestion. I wanted the way just like http://service.sa

  • Photos Forgot Their Crop and Edits in iOS 8

    I have an iPhone 6 Plus running iOS 8.1 with iCloud Photo Library (Beta) enabled and "Download and Keep Originals" selected. And as expected, I have all my photos from my previous iPhone on the new phone. But I noticed that all my old photos "forgot"

  • Tableview Filter/Sort Always open a new window!

    Dear experts, I have came accross a weird problem. When user filter/sort function in a tableview, a new window always display automatically with the result. But the old page does not change accordingly. But when you use filter/sort function in the ne