Confirmation of parallel sequence operation.
Hello friends,
I want to do confirmation of parallel sequence operation. I use 3 or5 work centers at a time for doing one operation. So i have defined parallel sequences for standard sequence. When I do confirmation of quantity and activity time in CO11N for one parallel sequence, other sequence quantity and activity time should be decreased. But system takes actual quantity and time.
How to make settings , so that quantity and activity values should be decreased automatically for next parallel sequence.
Waiting for Reply!
Dear ,
You are not able get the paralle sequence operation in CO11N because production order will copy the Routing based on the Order Type dependent paramter-OPL8-Routing set up.
Here , basically , you might have chkeced Alternative Sequence and Sequence Exchange field (0) , so while creation production order , routing with operation which are in alternative sequnce will be copied and will be used in CO11N confirmation.
2.You need to maintain "Operation Sequence is not checked " for operation sequence for the Ordertype/Plant combination in confirmation parameters using transaction OPK4.-Confirmation parameters of Order
Try and revert back
Regards]
JH
Similar Messages
-
The deleted operation affects the confirmed yield of the parallel sequence
there is a production order.
the control key of the last operation is PP03,and it's confirmation is : Milestone confirmation.
and the production order has a parallel sequence,a external processing operation.
but i marked the external processing operation deleted.
then i confirm the last operation,and it's sysstatus is CNF
but the parallel sequence operation is not CNF.
WHY?Dear,
did you delete the operatrion after release or before the release? -
How to use parallel sequence for split the operation qty. urgent or other o
PP guru
My scenario is as follows.
I ve one material suppose xyz.
For that material I' ve created bom, routing.
In routing I' ve mention only one operation. 0010.
Now I' ve the production order of 1000 kg.
I want to use two work centers to run this production order. ( e.g.work center a and b)
In routing I used work center a.
In short I want split that operation.
So what I ve to do or use parallel sequence and how???
or else is there any other option to split the order to two or more machines/work center?
Pls explain me in brief.
Regards,
RamHi,
If you want to carry the production with two different work centers , first you need to split the operation qty.
For this in the order type dependent parameters OPL8
in the controlling tab page enable the indicator Cost collector
and set the default rule as PP2.
Create a Product cost collector with KKF6N.
Now in the production order , select the operation and choose functions--->>> split.
Now enter the operation split quantity and execute.
Now in MD04 you can see two production order.
In the second production order change the work center in the operation overview as desired and save.
Regards,
nandha -
Parallel sequence - scheduling operation
Hi,
when I was creating parallel sequence in routing I was faced with problem in scheduling operation.
After making a routing with parallel sequence, which are executing on the others work centers, system doesn't take into consideration the fact that order is divided on for example two work centers ( parallel sequence ! ).
How to divide the time of operations for equal parts ( or different proportion ) in two work centers.
Please help me solvede this problem.
ArturArtur,
The logic of parallel sequence is bit different from what you expect.
The parallel sequence is the sequence of operations which runs parellel to main sequnce.
But you can use it to serve your purpose.
After creating the parallel sequence in the routing, select the standard sequence, click on operation.
In operations overview, select the desired operations & follow path, 'Details'-- 'operations' or press F6.
In the operation details screen, under 'Unit of measure conversion', maintain value against 'Header' as 1 & against 'Operation' as 0.5 (if you want to divide the value equally).
Navigate with the arrows in the upper left & maintain these settings for the desired operation.
Now click on 'Sequnces'.
Select the parallel sequnce & repeat the above given procedure for the desired operations in the parallel sequences aslo.
Now whenever the order will be created, the order quantity will be divided equally on the sequences & accordingly scheduling will yake place.
Hope this helps you.
SmanS
Edited by: SAP PP Consultant on Jun 8, 2009 10:21 AM -
Error in schedulinq parallel sequences with flow production operations
We have a routing with a standard sequence with operations in wich we have set "Continuous flow prod"
and "Min. Send-Ahead Qty=1".
We have a parallel sequence as well with operations set in the same way "Continuous flow prod"
and "Min. Send-Ahead Qty=1".
When you run the transaction "MD11" to create a planned order for the item the scheduling of the operations is correct
as regard the standard sequence,the system, correctly, schedules the operations overlapping
them according to lead time set in the operation details.
But the last operation of the parallel sequence is scheduled to finish the whole lot before the operation
following the "return operation" . The system doesn't overlap this operation. In this way the
last item of the last operation (in the parallel sequence) isn't finished at the same time
with the last item of the "return operation" (in the standard sequence) as we like it would be.
We have set "Backwards scheduling" type on customizing and we use the "Alignment key= 2 "
for standard sequence and in the parallel as well. We have also tryed to set "Alignment key= 1"
in the parallel sequence but the results are howewer not correct.
In conclusion the schedulation of continuous flow production operations
doesn't work properly between operations belonging to parallel sequences.
Could you suggest me what to do?
Thank you.Hi,
I tried with 5 ops 10, 20, 30 ,40,50 ( same work center wc1)
Set up time 1, Process time 1min for 1 pc
set the continuous flow prodn i at op 20 with min send ahead qty 1
Also a parallel seq was created with 3 ops op20 ,30 , 40 .
set up time was 2 min for all work centers( same work center wc2) and proc time
time is 1 min for 1 pc
In that set the continuous flow prodn at op 20 with min send ahead qty 1
sceduling type was forward
.Alignment key was 2 for both std seq and parallel seq .
After scheduling found that op 20 in std seq starts at 6.14am and op 40 ends
at 6.47 am where as in parallel seq op 20 starts at 6.11 am and op 40 ends at
at 6.47 am which is correct.( branch op is 20 and return op is 40)
The three minutes late start in op 20 of std seq is due to 3 minutes extra time
defined for three work centers setup time.
I also tried with alignment key 1in both std seq and parellel seq.
Kindly check that you have maintained the continous flow prodn radio button
in the same operation in both std seq and parallel seq.
Regards,
S.Nandhakumar -
Extracting return operation from a parallel sequence in a routing.
Hi all
I need to extract data on some existing parallel sequences in routings from R3. One of the fields i need is the return operation for each parallel sequence.
I was hoping the data would be in PLFL which contains most of the sequence information I need. But alas it doesn't have the return operation.
Checking with F1 and the tech button shows me that the field i want is PLFLD-VORNR2. But PLFLD is a structure that I can't get to.
Does anyone know how to extract this info from the system?
Regards
Simon PedersenHi Simon,
The field that you're looking for is PLFL-BKNT2 (for the return operation). Pay attention that in this field there's a number that is representing the operation node number, not the number that you see in the routing screen.
Regards,
Mario -
Difference between parallel sequence and parallel operation in a routing.
Hi Experts,
Can any one explain me with example the difference between parallel sequence and parallel operation in a routing? wHEN CAN WE USE PARALLEL OPEARTION AND PARALLEL SEQUNCE WITH COMPONENT ALLOCATION.
Regards
Deepak sharmaI think u need to modify ur quest... i think u r asking about Parallel sequence and alternate seq. Below are the details from SAP site.
A parallel sequence enables you to process several operations at the same time.
You use an alternative sequence for example, if
--The production flow is different for certain lot-size ranges
For instance you can machine a work piece on conventional machine or on NC machines. A NC machine has a longer set-up time than a conventional machine. However the machining costs are considerably less. Therefore whether you use NC machines will depend on the lot size.
---The production flow changes under certain business conditions.
For instance, if you have a capacity problem, you have some production steps performed externally by a vendor. -
Hi,
I have defined a parallel sequence for a material in routing. Say material has 4 operations 0010, 0020, 0030, 0040. I am having 4 diff work centers for the four operations. Now the output of the 2nd operation 100 and the capacity of the 3 workcenter in 50 so I want utilize the parallel sequence. Now while creating a production order, system is by default selecting the std. sequence and when I go for confirming the the operation 0030, i should get two workcenters for confirming the qty. My requirement is to confirm the qty against the actual workcenter where it is performedHi,
while confirming the order I am facing a problem. while confirming operation 20 and 25, the system is accepting the total qty. for individual confirmations. which is wrong, if I confirm 50nos. against operation 25, it should automatic give rest 50 nos. against operation 20. same control keys are kept for the operations PP01.
Pls let me know how to avoid this duplicacy while using parallel sequence.
Thanks in advance. -
Confirmation in alternate sequence
Hi
System proposes wrong qty to confirm after alternate sequence confirmation.
op 10 - 10 ea
op20 - 5 ea op11 - 5 ea(parallel)
op30 - 10ea
In confirmation, after i confirm op10 for 10 ea, i confirm
Case A: op20 - 4 ea (Final confirmation), op11 - 3ea (Partial)
system proposal for op30 is 8ea
Case B: op20 - 4 ea (Partial), op11 - 3ea(Partial)
System proposal for op30 is 6ea
why it is not proposing 7 ea for op30.Dear,
In OPK4 check the following
Operation sequence = Operation sequence not checked....then do confirmation it will work as required by you. -
Alternative sequence - operations number
Hi all,
I've got an issue on the alternative sequence.
The standard sequence is made by operation 10, 20 and 30.
I try to add a new alternative sequence to substitute the operation 20 with 2 different operations: 20 and 25.
The system give me an error on the routing: CP331 - Operation: date 28.04.2010: operation number incorrect.
I tried the option to change the standard sequence to 10, 20 and 40, but the error is the same. The system checks the return operation (20) and is not possible to add operations into the alternative sequence with operations number greater than return operation.
It seems that is not possible to substitute 1 operation with 2 operations.
Anyone has solved?
Thanks, regards.Hi ,
Okay, you want to create an alternaive sequence only.
Standard sequence is 10 20 30
Alternate Sequence:
1.Branch operation : 10
Number of the operation from which an alternative sequence is to replace the reference sequence.
2. Return operation: 30
(number of the operation up to which an alternative sequence is to replace the reference sequence)
Operations: 20, 25
This should work.
Please check and confirm.
Regards
Datta -
Scheduling of Parallel Sequence in Routing & Production Order
Hello Friends,
I have gone through sap library & many other threads related to maintaining & scheduling of parallel sequence in Routing as well as Production Order.
For the example, I have 3 operations : 0010,0020 & 0030.
I want to maintain 0020 & 0030 as Parallel Operations ( Parallel Sequence) i.e. for both operations I have maintained same lead times so that both should start & end at same time parallely.
First of all, I have maintained all operations in standard sequence 0 all 0010,0020 & 0030 operations and also maintained tick in Required splitting check box.
Same way , I have maintained operations 0020 & 0030 in Parallel sequence with branching operation as 0020 & Return operation as 0030. Ref. sequence i have maintained as 0 (Std. Sequence).
Now when I am checking in Graphic it is not showing both operation 0020 & 0030 as parallely scheduled and hence same is not reflected in Production ORder as well.
Kindly share your valuable views reg. what may be other settings for parallel sequence which I may be missing.
Thanks in advance.
Regards,
TejasHi Abhijt,
Thanks for your reply. I went through your thread & I followed same steps as mentioned by you in your suggested threads.
I have removed Parallel sequence fully & maintained Required Overlapping for all my 3 operations : 0010,0020 & 0030
I have maintained workcenters as below :
0010 A Set up 2.0 Hrs Machine 5.0 Hrs Labour 1.0 Hr
0020 B Set up 2.0 Hrs Machine 5.0 Hrs Labour 1.0 Hr
0030 A Set up 2.0 Hrs Machine 5.0 Hrs Labour 1.0 Hr
I checked scheduling in routing itself same way you suggested with start date today's date & forward scheduling it gives following results :
0010 start time 07:00:00
0020 start time 07:13:42
0030 start time 09:14:39
My concern is with mainly start time of operations 0010 & 0020 since for both of these are processed on different workcenters A & B respectively then why not starting exactly on same time on 07:00:00 AM only instead another operation is starting on 07:13:42AM. I am unable to find how this difference of 13mins 42 seconds is coming.
Kindly provide your feedback. Also let me know if you need any more details.
Regards,
Tejas -
Hi all,
I have defined a parallel sequence in routing linked to standard sequence. i.e. 0
Stand. seq. has one operation 0010 (work center L1)
Parallel sequence has 3 operations 10, 20 and 30. I am trying to make 10 (work center L4) and 20( WC L5) as parallel operations.
I have 2 quesries regarding this.
1. I am putting branch operation as 10 and return operation as 20 but I am getting error,
'The return operation is not defined'
2. I want this sequence to get selected in production order automatically in as operations but system ia selecting main seq i.e. with operation with WC = L1.
Let me know if I am missing something, concept wise or setting wise.
Regards,
YogeshHi,
Your first question:
You cannot have return operation as 20, as you standard sequence has only operation 10. So your branch operation and return operation has to be 10.
Your Second Question:
In the production order go to Sequence overview (Shift+F8) to select the sequence and then go to Operation Overview (F5) to look into the details of the operation.
Regards
Vinod -
Parallel Sequencing of Production between different resources
Hi all,
I want to consider the way to produce a product in parallel with other resources if available and cost efficient. ( Parallel sequencing of the production between resources)
I have setup groups for products. Also resources (machines)
every machine can do the same job (in different times)
According to setup optimization it may be useful to produce all in one resource but if I need to catch the requirement date, I have to parallelize the work.
Is there any way in SCM like (parallel sequencing in R/3) that takes us to a more feasible solution?Hi Mehmet,
In R/3, in the operation of routing, we can give "split" number . It can split one operation into several splits during scheduling or capacity leveling so that total execution time will be reduced accordingly.
But when you transfer such operation with split number, the activity duration will be automatically calculated by using machine time divided by split number.
However in PPDS, there is split function. I'm not sure if it is what you want.
http://help.sap.com/saphelp_scm50/helpdata/en/3d/7e653a0c52425fe10000000a114084/frameset.htm
Hope it can help.
Watson -
Production Order not printing with Parallel Sequence ?
Hi All,
User is unable to print Prod. Orders when Parallel Sequence is used, but Orders using Standard Sequence are printing fine.
Print is done in Update Task, so User is able to release the Order and when he saves the Order, the Order should get printed.
Currently this is not happening. There is no spool generated.
Can anyone please tell me the printer configuration required for this. Or any other configuration which we are missing.
Thanks,
BhuvanDear Bhuvan,
I'm not sure if this is the issue,at a high level,check if the control key assigned to the operations in the
parallel sequence supports for Printing in General(check box set).
Regards
Mangalraj.S -
Parallel sequence-Process Industry
Hi All,
Following is the scenario req in SAP
Stage-1: Crude prep- (Done in 10 reactors, R1, R2,R3......R10)-Parallel sequence
Stage-2 Pure prep- Done in single Reactor (P1)
Stage-3 Storage-(4 silos)
Stage-4 Packing
How to address this in Master recipe
Regards
SubbuHi,
Same Crude is manufactured in all the 10 reactors in the first stage
Raw material input would be given to the each crude reactor & it is simultaneous & output from the all crude reactor is mixed (Not measurable for each reactor wise ) in a single conveyor line to the next pure stage.
If you consider the crude reaction-10 hrs, since the 10 reactors are parallel, it should consider only 10 hrs for the entire operation.
They also need to analyze the resource wise activity entry details.
when I make 10 crude reaction as a each phase, it should calculate only the 10 hrs & not 100 hrs.
Regards
Subbu
Maybe you are looking for
-
Losing keystrokes in windows 8.1 with browser open
I'm having a couple weird problems with loss of keystrokes in windows 8.1. Not sure if it's a driver or malware issue. Right after I installed windows 8.1 I noticed that if a browser window is open, i lose keystrokes in any application. This happens
-
Best to start out explaining the situation...LOL. I travel full time for work, so almost always gone someplace, in a hotel in the evenings with wifi. I have a quite large and hard to manage iTunes library (over 80k songs) that I maintain on my lapt
-
HELP! adobe audition cc 2014, wont play no matter what,
The other day I was working on a project and everything was fine the next day when I re opened the project it wouldn't play. As far as i know i didnt change anything. I can move the tracks around and everything is still there but when i click the pla
-
It seemed that my question,which I posted on 22nd of July about modifying a view's query had been deleted. I posted a question about modifying a view's query. In the midst of tackling many problems, I missed to return replies to my question. Many tha
-
Adobe elements 10 keeps crashing and it used to work. Why? Fix?