Dear All,
The case is ,  User make mistake on putting large volume into material quantity within process order,  However, this process order has been released , confirmed and delivery (DLV) status. 
Since this large vquantity material will make the Cost extra larger than normal.  
Therefore, is there way to change material quantity and recalcuate the cost again? 
Many thanks !
Marco

Dear all,
After commuicated with User again,  user has been done as below.
Step1)
User has been cancel the process order confirmation by T-code:  CORS,
Step2)
Revesed the extra amount Quantity to Block stock to prevent Sales Person touch this extra quantity.
However,  I checked there is no different on Actual costs after the cancel the Process order confirmation.
I have some confusing now..
1) is that once Process order confirmation cancelled,  is that there Must no Actual cost in Accounting view?
2)  If there is part of physical product produced,  but the Process order has been cancelled afterward. How the cost calcuated?  is that include the cost or exclude the cost? 
Many Thanks for your help!
Best Regards
Marco

Similar Messages

  • Confirm process order problem

    hi
       I configure IMG settings under OPK1 for porcess order..I check "imediately proposal" for quantity/service..But when I use COR6N to confirm process order, the duration field is not proposed...Where should I configure in IMG?
      btw,is there any T-code like COHV in discrete planning to mass confirm process orders?thanks..

    Dear Monst,
    Ensure whether have you made this setting for the standard profile in OPK1 under default tab page check whether for quantity
    and services whether for the value is set as 1 - immediate proposal.
    check with this and revert back.
    Regards
    Mangalraj.S

  • Process Order is not picking the follow-up material

    Hi Gurus,
    We have changed a BOM by discontinuing a component and giving a follow-up material with the valid from dates as 18/5/09.  and then MRP is run on that nignt  ( mrp job set to run daily in the back ground). and on 19/05/09 a Process Order is created from the planned orders genereated by the MRP run.
    now, we found that the new componenet (follow-up) is not copied into the process order, but the old compomemt (discontinued) is removed. 
    MRP parameters are correctly defined (Planning mode is set to 2) .  Please let me know if we are missing anything.
    Thanks,
    N

    Hi
    Pl ensure that the Following requirements have been met before you can use the discontinuation functionality:
    1) Both materials must be planned using MRP.
    2) The base unit of measure of the follow-up material must be the same as the base unit of measure of the discontinued material.
    3) You must enter discontinuation data for the discontinued item and follow-up data for the follow-up item.
    and Also refer the SAP link for Complete Details
    http://help.sap.com/saphelp_45b/helpdata/en/b1/c044d1439a11d189410000e829fbbd/content.htm
    Regards
    Brahmaji

  • Sequential confirmation and restricting over confirmation - Process orders

    Hi,
    We have a process orders with phaes 20,40 and 60. Order qty = 100 pc
    1. We would like to have sequenstial confirmations from 20->40->60.
    2. When we confirmation phase 40 , quantity should not exceed the confirmed quantity of phase 20. ( Example , if 20 is confirmed for , say , 10 pc , then user trying to confirm 11pc in phase 40 , should result in an error )
    3.When we enter confirmations in COR6N , we would like to have the previous confirmed quantity to appear as default and if user changes to a higer quantity than the previous confirmation quantity , it should give an error message.
    ( for example , here when user confirms phase 20 - order qty less previously confirmed qty = 100-10=90 pc should come as default ;   for phase 40 , default confirmation qty should appear as 10 pc and user trying to change it to 11pc, shoudl result in an error)
    In order confirmation parameters , we have chosen " error when operation sequences are not adhereed to ".
    and in over delivery tolerance , we have chosen " wanring message"
    How can we achieve this modifitcation?
    Thanks and regards,
    Manohar

    HI,
    In the confirmation parameters OPK4(Customizing for Shop Floor Control, choose Operations -Confirmation -Define Confirmation Parameters) you set the Propose indicator in the quantities area, to stipulate that quantities should be proposed when confirmations are entered under "Operation Individual entry using Indv. scren" tab Page. and test
    If this is not working out
    Check
    Control key for operations (in Customizing for Shop Floor Control by choosing Master Data -Routing Data - Define Control Key), you stipulate whether an operation can or must be confirmed (Confirmations key).
    Checking the Quantity to be Confirmed (Confirmations key).
    If the operation sequence is checked for confirmations, then the following quantity check takes place: If you want to enter a confirmation in which the sum of the yield, rework quantity and scrap is larger than the yield of the predecessor, then the system issues an appropriate message (for example, an error message). The predecessor is determined exactly as described in the graphic.
    Irrespective of whether the operation sequence is adhered to, the quantity is checked against the quantity of the predecessor operation (= expected quantity) and a message is issued (the category is set in Customizing). The following cases can occur:
    The confirmed quantity is larger than the expected quantity.
    You are entering a final confirmation and the confirmed quantity is smaller than the expected quantity.
    The message category determines your next entry option:
    After acknowledging a warning, you can continue entering.
    In the case of an error message, the system terminates the input dialog.

  • Process order creation with out BOM

    Hi
    I have an requirement...
    material A is finished good
    i create process order for material A
    but i dont use BOM... with out BOM can i create process order .
    after creating process order cani isuue components against  order ? is it possible please can any one help me in this issue
    but one condition : i craet process order material A 10 KG
    for this FG i used components  materia A used 8 kg  and material B used 2 kg
    is it possibel pls..could any one gude me in this issue
    Regards
    Sesi

    material A is finished good
    i create process order for material A
    but i dont use BOM... with out BOM can i create process order .
    yes, You can create a orderwith out BOM
    after creating process order cani isuue components against  order ? is it possible please can any one help me in this issue
    Yes, You can assign component  manually in component overview screen  or you can issue material directly for order with 261 movement, It will go to unplanned consumption
    but one condition : i craet process order material A 10 KG*
    for this FG i used components  materia A used 8 kg  and material B used 2 kg
    In The component overview screen of process order  assign the Material A with 8 kg ,
    & material B as 2 KG
    Regards,
    Sundaresan
    Edited by: Sundaresan . E. V on Oct 4, 2010 2:41 PM

  • Process Order Close with Inspection Lots

    At month end we need to close process orders that have not had their usage decison made, generally the inprocess inspection UD.  Is there any way to close these POs without having to enter a usage decision?

    > Hi
    > You can activate the inspection completed status
    > activated for the inspection lots with out making
    > UD.
    > Regards'
    > YMREDDY
    Your suggested solution to being able to flag the inprocess inspection lot as being completed without making a UD, to allow the process order to be closed, sounded very, very interesting, but we are not familiar with the file/record/configuration parameter you noted.  Is there any way that you might be able to clarify your answer, so that we can have our technical team figure out how to implement that change?
    Thank you very much.....this has had us stymied since we went live.

  • "missing part list" releasing process order, but the material there is

    Hi dears,
    I’ve a strange problem.
    When i’m going to release a process order, the system give me a “missing part list”.
    The strange is the material indicated  in that list, a component of a phantom, is present in state free in the st. location indicate.
    Does anybody know what can be the problem?
    Thanks in advance,
    Juan

    Hi all,
    the problem was that the material was present in quantity lower than safety stock.
    For this reason, the system give me that advice.
    however thanks for the help.
    Best regards,
    Juan

  • Unable to confirm process orders

    Hi,
    I am getting an error - No open operations requiring confirmations exist for the order.
    In the control key, I have selected 2 (confirmation required) in the confirmations indicator.
    In the confirmation parameters, I have + confirmable operations checkbox ticked.
    Are there any settings I have missed? I appreciate your help.

    Hi
    Please go and check operation
    u have to add operation in order
    do u have recipe for material in order
    Please tell me if u face any problem
    please reward points
    Sunil

  • FM/BAPI to create Transfer Order(TO) with reference to TR or Material Doc.

    Hi,
    I am in need of Function module or BAPI to Create Transfer Order(TO) with reference to Transfer Requirement(TR) or Material Document.

    Hi,
    Please try any of the below,
    1.Look at function group L03B (Transfer order processing)
    2.Use L_TO_CREATE_TR
    3.BAPI_GOODSMVT_CREATE set:
    GOODSMVT_ITEM-STGE_TYPE_PC = destination storage type or GOODSMVT_ITEM-STGE_TYPE_ST = destination storage type
    4.Look at fm L_TB_VERAENDERN. This isn't RFC, but you might copy fm into ZL_TB_VERAENDERN and set RFC on.
    Hope this helps.
    Thanks,
    Harini

  • Process order settlements not flowing into BI for Inventory

    Hi,
    I built a cube for inventory based on the standard extractors to generate MAC values. I have three MAC reports, each for daily, weekly and monthly. The reports give the right values at the at the month level , but  whenever there is a settlement for process order done, BI does not pick the settlement value and this makes the MAC value shoot up at the daily and weekly level. I tried to a find an extractor for this settlement and could not find any. Can someone please help me with this ? Is there any datasource for settlement of process order?
    Thanks

    Hi,
    Both Tomas and Debraj have provided good tips.  Let me elaborate on this. 
    From SWU3, access Maintain Runtime Environment -> Schedule Background Job for Missed Deadlines by double clicking on it and execute it. You could maintain the interval until next deadline check.  You could keep the number low.
    Also, if you have the event queue turned on, some times the work items will stuck in the queues and took a long time for them to be available.
    Best Regards,
    Jennifer Cha
    GRC RIG

  • Secondary Costs Manual Allocation but with a negative debit for the sender

    Hi,
    We would like to do a manual allocation for secondary cost (the sender objet is a cost center and the receiver objet is other cost center). The only way we know to do this, is using transaction KB15N, but with this transaction, system credits a sender object (for example, a cost center) and debits a receiver object (for example, an new cost center). Is it possible to do this allocation but having a debit (a negative debit) for the sender object and a debit (a possitive debit) for the receiver objets? We do not want to have credits, because the credit does not work properly for the cost splitting.
    Thank you really very much,
    Ariana

    Hi,
    If I put the receiving cost center in the sender side and the sending cost center on the receiving side with a negative value, the problem is that the credit is done for the receiving cost center. For the kss2 we have not problems because all of the costs are on the debit, but for the receiving cost center when we run the keu5 we have problems because keu5 transaction does not take properly costs on the credit (it does not consider costs on the credit as negative costs on the debit).
    Does anybody know how can we solve this problema?
    Thank you really very much,
    Ariana
    Edited by: Ariana Landaluce on Jun 23, 2009 8:45 AM

  • In Purchase Order Line item Maintaining Serial Numbers for Material Codes

    Dear Gurus,
    We have a business process in legacy system for Purchase Order like in PO line item, Material code with description, Quantity, unit of Measurement, Serial Number Start and Serial Number End is maintained, for example for Material code when we enter the data AXMLN00001 in Serial Number Start column, if the Qty 500 is maintained, by default system will calculate AXMLN00500 in Serial Number End column. 
    We understand that in standard SAP we donu2019t have this option of maintaining Serial Number Start and End in Purchase order Line item. Please let us know how this can be mapped and is it advisable to create two Z fields in EKPO table or else can we make any development.
    Suppose if this is not possible in SAP for PO then in Banks if we want to place a order for Cheque books how we can maintain Start and End Serial Numbers to print in cheque books.
    Also client is not agreeing to maintain manually Serial numbers in item text.
    regards,
    Dhanu

    Aamir,
    When the PO Item was created say for example Material had Valuation category "Y" and latter you wanted to change the category to "Y". Now system would have check for all open PO's etc...based on this you must have set Deletion Indicator to this Line Item to allow valuation category change in material master. Now when this Item got created in the table level (EKPO), system updates the valuation category "Y". Currently this valuation category is not active so it would not allow you to perform removal of deletion indicator as program cannot automatically nor you have an option to manually update the valuation category to this Item.
    Regards,
    Prasobh

  • Update required quantity for material component in Process Order.

    Hello.
    I need update component qty from Z dialog program.
    The famous BAPI_PROCORD_CHANGE doesn't deal with COMPONENT structure but only HEADER. Then I tried to combine it with an enhancement.
    I see that in WORKORDER_UPDATE~BEFORE_UPDATE I can't change values in IT_COMPONENT.
    Anybody have used enhancement for this purpose and how can I transfer my calculated values to order?
    In addition I check ENHANCEMENT-SECTION   CO_BT_ORDER_POST_02 SPOTS ES_SAPLCOBT  to do it.
    What syntax our developers should write if it's possible?
    Thanks
    Alex Davidov

    Kumar.
    What should be copied? The header batch or some/all of the characteristics of the header batch to a new batch for the component?
    Anoop

  • Error while posting a sales order created with reference from contract for

    Hi,
    I am posting a sales document( Type: WA)  created with reference from contract document(  type wk2) for delivery.  The item category in the sales order of the Item is WAN. On posting this document for delivery I am getting the error as "Item category WAN is not defined".  Please help me out how to resolve this issue.
    Thanks
    Jayant

    Hi Jayant,
    I think its value contract releated error,
    You suppose to check material item category group through T.code-MM02 into sales2 tab and maintain VCIT,
    and do item category assignment through T.code- VOV4.
    plz.maintain like that,
    WK2 -          -VCIT-         -           - WAN(contract item category),
    wk2  -          -        -VCTR-          - WAN((contract item category),
    you should also maintain same against your standard Sales Document type and for Standard Item category into VOV4,
    WA(standard docu.type) -VCIT-                             -                -TAN(your standard docu.type item category),
    WA(standard docu.type) -         -VCTR(item usage)-              -TAN(your standard docu.type item category),

  • Set up Tolerance Limits with Date and quantity for GR

    Hi Experts,
    We would like to set the GR Tolerance Limits with Date and qty.
    how to set the Tolerance Limits for Date and quantity..??
    if we created PO 100qty and date 01-05-009.
    if we receive the goods on 20-04-2009 and 50qty...
    For GR .. Migo should be give error message..
    where can i set this Tolerance Limit Configuration.... can u please explin me..
    Thanks in Advance,
    Anthyodaya .

    hi,
    You can do one thing...
    Activate the SLED check...
    BY this when the date goes earlier or late from the expected date, then system show you the messages like:
    1. Earliest delivery date is DD.MM.YY..
    2. Expected delivery date was DD.MM.YY...
    In std sap system, the second message is already error message...so when get late delivery then it'll not be possible to maintain the GR...
    For the qty varinace, activate the quantity variance either via over/under delievery tolerances..or
    Via SPRO settings...
    SPRO >> MM >> LIV >> Invoice block >> check for qty tolerances and make the settings as per your requirement...
    Regards
    Priyanka.P

Maybe you are looking for

  • Missing drivers after upgrade to Win 7 in HP pavilion dv9500

     I upgraded my laptop to Windows 7 32 bit and everything works except from 2 base system devices listed in device manager that need work. What should I do?

  • Do not execute - Maintenance Order ??

    Hi, There is an option before Release of MAintenance order called 'Do not execute ' , can we click that option if anyone have generated wrong maintenance order by change or by doing worng scheduling of Maintenance Plan. I think this option is for the

  • Any way to protect table cells? Prevent table modification?

    I have Pages word processing document that contains a two-column label (it's a grading rubric, if you care). The left column labels the data. The right column contains numerical scores and a few cells that sum these up to create subtotals and a grand

  • Add multiple entries to dropdown list without using data dictionary

    Hi, By default when we use a data dictionary element for dropdown list, all the possible values are listed in the dropdown. However when no data dictionary element is used for the dropdown list, it behaves like a parameter with a single line. I would

  • Unlock SELECT FOR UPDATE

    I have to do a "SELECT FOR UPDATE" query to modify a CLOB column. The problem is that i want to release this lock BEFORE i commit or rollback de transaction. How can i do it? Thanks