Consolidated List of Dependent requirements

Dear friends
I have entered three months PIR (for nearly 200 products) FGs in MD61. I need to take a print / list of dependent requirements (child requirements) separately to send my internal material supplying departments for their planning. any tcode available to take consolidated dependent requirement monthwise? or we need to go for ABAP. Kindly advise me.
Thanks & regards
V.Senthilkumar

Dear anand
Thanks for your reply MD46 is giving the stock coverage days and plant stock. Actually I need generate a dependent requirement quantities with plant stock for a given planning period.
MD47 t-code is for product group, in our case product groups are not used, we are going by PIR based planning.
Still my problem is not resolved
Regards
Senthil

Similar Messages

  • List of dependent requirements of planned order for a component

    Dear guru ,
    I search a list of dependent requirements of planned order for a component
    What do you suggest ?
    Thanks.

    Hi Cristano,
    Go to MD04 transaction, enter comopenet and plant. Then from the list select the Planned order and click on the Order Report from the bottom tool bar available below the list.
    You can see the componets details for that planned order.
    Thanks and regards
    Murugesan

  • How to Find dependent requirements generated for a period

    Pegged Requirements for the PR's Generated after MRP Run

    Hi Archie,
    We can find out the list of dependent requirements from RESB table.
    We can pass the pegged requirements in RESB and fetch the dependent requirements and purchase requistions created for the same.
    The Planned orders within a particular period can be fetched through table PLAF and the same can be given in RESB and fetch dependent and purchase requisitions.
    If you feel my answer is clear and useful, kindly award me with points.
    Regards,
    Prashanth.

  • Planning of Dependent Requirements for BOM Components in Make to Order scen

    Hi Friends - I want to execute a full cycle Make to Stock Scenario with Materials planning using MRP.
    The scenario will include BOM Components with Routing.
    The process flow I want to execute -
    1. Create a Sales Order for a Finished Product (Product should have a BOM for Production)
    2. Do the product Materials Planning for the Sales Order through MD50
    3. Get all the dependent material requirements (both for products as Planned Order and also for BOM Components - all the BOM components should also be planned)
    4. Convert Planned Order for Product to Production Order
    5. Convert Planned Orders for BOM components to Purchase Requisition
    6. Confirm Production Order
    To execute this I have done the following
    1. I have created a Material Master data for Finished Product (FERT).
    2. I have assigned Item Category Group - NORM, and General Item Category group as NORM
    3. I have assigned MRP Type PD in MRP 1 View and Strategy Group 20 (Make to Order Production) in MRP 3 View.
    4. Now created a Universal (Type 3) BOM for the product with one material component.
    5. Now also created a Routing for the Material with two operations having PP01 a control key.
    6. Now created a standard sales order for the product.
    7. Executed the MD50 for the Sales Order Item.
    Now where do I find the BOM components for this material in the Sales Order?
    After executing the planning Run MD50 I am only getting the requirements for Product only. I can't see any dependent requirements for the BOM components.
    How do I make sure that the BOM components are also planned while the product is planned?
    I have checked the component Stock Requirement List - there are no requirements generated from the Sales Order Product BOM.
    Pls help me on this. How to do this so that the raw material components are also planned?
    Thanks
    Purnendu

    Hi Dhaval, Sandeep, Ashok - Thanks a lot for your replies.
    I have checked the Planned Order Created through Planning Run.
    If I click on the Components Tab I am getting following message
    No material components were determined
    Message no. 61027
    Diagnosis
    Until now, no BOM explosion has been carried out or no BOM has been created for this material yet.
    Procedure
    Either explode the bill of material for this material, or
    create the components manually by processing the planned order in change mode.
    If I try to explode the BOM through Header Menu - Edit> Explode BOM
    I am getting the same message.
    If I click on the Bill of Material Tab - I am getting the same above messge.
    Ashok - I have tried both the Selection Method -
    Nil - Selection by Order Quant.
    1 - Selection by Explosion Date
    But with no effect.
    Waiting for your advice.
    Thanks and warm regards
    Purnendu

  • MRP Planned order generation for Order reservation excluding Dependent Requirements

    In our Project we have a requirement like for FG stage & SFG1 stage are M.T.O So after sales order are punched through  MD50 we have created Planned orders against sales orders,But dependent stages like SFG2 & SFG3 which are pure M.T.S so only Dependent requirements will get generated.Suppose for SFG1 i have partially converted planned order to Production order then for component SFG2 we get Partial Quantity as order reservation.Now requirement is if i run MRP for SFG2 system need to generate demand only for order reservation excluding Dependent requirements.Is there any possibility where we can generate demand only for order reservation.As system will create Planned order for SFG2=Dependent requirement + Order reservation

    Hi Uli,
    Suppose i have Sales order--100 kgs for FG
    B.O.M levels
    1.FG-----M.T.O
    2.SFG1---M.T.O
    3.SFG2---M.T.S
    4.SFG3---M.T.S
    5.ROH
    So if i run MRP via MD50 system would generate planned orders for FG & SFG1 level as they are M.T.O specific
    Now my requirement list would be
    FG-100kg planned order
    SFG1-100kg planned order
    SFG2-100kg dependent requirement.
    Now suppose i have partially converted SFG1 planned order to production order
    SFG1--100kg planned order to 30 kg production order
    Now my requirement list would be
    FG-100kg planned order
    SFG1-70kg planned order & 30 kg production order
    SFG2-70kg dependent requirement & 30kg order reservation.
    Here my requirement is if i run MRP for SFG2 in MD02 as these stage is M.T.S system should provide 30 kg planned order & if we see down the line it would be like
    Now my requirement list would be
    FG-100kg planned order
    SFG1-70kg planned order & 30 kg production order
    SFG2-30kg planned order & 70kg dependent requirement.
    SFG3-30kg planned order
    ROH-30kg Purchase req
    Client requirement is like these..

  • Dependent Requirements report required

    Hi All
    I'm searching for transaction which will generate a report with total of dependent requirements for a given FG material list:
    Do you know if there are such type of transactions in SAP?
    Kind Regards
    Andrey

    Hello!
    We had the same problem, and our solution was making this report in ABAB. In ABAB you can call structure MDEZ and filter it by "MRP element"= DepReq.
    Other solution, rather temporary, is report based on table RESB (using e.g. transaction se16/se16n, SQVI, or ABAB). In that table field BDART='SB' means requirements coming from DepReq. The problem is, that RESB table can be huge, and searching in that way can take a lot of time.
    Best Regards,
    Marcin

  • Need a Pegging module for dependent requirements.

    Hi
    Need a Pegging functional module for dependent requirements.
    There is MD_PEGGING_NODIALOG ,where we need to pass the planned order number.
    Please advise how to get the pegged requirements for dependent requirements or other MRP elements other than planned order.
    Thanks
    Prasad

    Hello,
    Function module MD_PEGGING_NODIALOG works with data structures of MRP list or current requirements/stock list. For a given material, you first need to fetch the relevant structures by the help of following FMs; BAPI_MATERIAL_MRP_LIST and BAPI_MATERIAL_STOCK_REQ_LIST. You can loop at the structures exported by these FMs and run MD_PEGGING_NODIALOG with the corresponding parameters of the MRP element you require. You can run MD_PEGGING_NODIALOG with any MRP element you like as in MD04 and MD05 transactions.
    Regards.

  • Dependent Requirement Reduction

    Hello All,
    While posting the backflushing, I mant the system to automatically reduce the dependent requirement for the materials ( for MRP) .
    Plz help me with any settings which will clear the reservations automatically while backflushing

    Hello All,
    Thanks for your replies.
    The scenario is, My PIR is 100 KG for a Finished Good ( FG). A planned order has been generated for this PIR, also it generated a planned for 100 Kg of the FG's component.
    Now I have converted the planned order to process order and confirming it for 10 Kg, by backflushing 10 Kg of  the component.through COR6
    Also I'm doing GR for 10 Kg through MB31.
    Now in the MD04 list, the PIR has been reduced to 90 Kg. ( as per strategy 11).
    But even after the next MRP Run the Raw material dependent requirement is showing as 100 Kg.
    But I expect the system, aslo to reduce the dependent requirement. Please suggest any solution for this.
    Regards
    Mahesh

  • Dependent requirements for Top level materials planned in MRP

    Hey Gurus,
    A top level material 20350 has a component 30397 and both of these materials are planned in APO.  We have another top level material 30399 (but this material is planned in MRP) and the component 30397 (is planned in APO) will the dependent requirements from material 30399 be populated in APO for material 30397?
    Sincerely,
    Kris

    Kris
    As Datta has mentioned the dependent demand will not reflect for the component material in APO. We had the same scenario as yours and this is what we did
    We modified the Planned order integration model filter criteria by adding custom logic in the BAdI CIF_INT_MODEL. The logic was to query the BOM tables in R/3 and find out all parents that have SNP relevant materials as components and include these parents in the list of materials for which planned orders are to be CIF'ed from R/3 . The BAdI will be invoked when you run the IM generation .
    You also have to CIF the BOM to APO . Once the PDS and planned orders are available in APO , the dependent demand will be created automatically. ( If you do not want to modify the BAdI then you can write a query and identify the parents and add them to the integration model manually)
    Thanks
    Saradha

  • Dependent requirement in REM

    Hi Guys,
    Greetings!
    In REM scenario, I made the posting of Finish material with the semifinish short, for which system created the backlog for Semifinish which appear in stock/requirement list as DepReq REM Finish Material/NProc, now in next MRP system created the PR for that material but the dependent requirement for that backlog is also appearing.
    Please suggest how that DepReq get consumed?
    Thanks,
    Hrishi

    HI
    You need to claer those post processsing records thru MF47 after doing MFBF with those materials which are short in stock before MRP run.
    Check and revert
    Regards
    Anupam Sharma

  • Mandatory drop list w/dependent field displays error on refresh

    ADF Business Components 10.1.3.42.70
    JHeadstart 10.1.3.3.81
    all,
    i have a drop list(field 1) that is on a mandatory field and whose initial value is null. i have another field(field 2) which my drop list is dependent on. then i have a third field(field 3) which is dependent on the drop list field. when i try to insert a new record, i select a value for field 2, the page refreshes and i receive a "Selection Required" error message for field 1. this only happens when the group is in table layout and field 1 has a dependent field.
    Here's the test case(if you take a default generation from the hr schema employees table w/dropdown lists; jobid(mandatory), managerid, and departmentid should all have dropdown lists assigned to them):
    1. add managerid as a depends on item for jobid
    2. add jobid as a depends on item for departmentid(or any other field)
    3. run the page and click on the add row button
    4. change the managerid field value
    you should get "- Selection required" error. this is a big problem for us right now bc the depends on is required in our application and we can't figure out a workaround. can someone take a look at this?
    thanks in advance,
    paul

    Paul,
    The only way to fix this is by making the "depends on" items optional instead of required, and delegate the required check to the ADF BC layer.
    I'll try to explain why:
    - a depends on item must have the immediate attribute set to true, so validation of the item and execution of the valueChangeListener will take place in the JSF Apply Request Values Phase. In the valueChangeListener, after updating the underlying model attribute, we directly jump to the render reponse phase, to skip other validations
    - If there are multiple items with immediate="true" on the page, then they will all be validated "in sequence" in apply request values phase. So, the first drop down list is validated before the valuechangelistener of the second item fires. If the end user enters data "normally" in sequence, this is usually not a problem, however, in your use case the user first enters a value for the second "depends on" item, and then you get the validation error on the first depends on item.
    So, to fix this, change the table item template and remove the required property
    Steven Davelaar,
    JHeadstart Team
    to prevent validation of other items

  • Copying Simulative Dependent Requirement

    Is anybody knows how to copy simulative dependent requirement of LTP to Operative Planning.
    I found a T-Code : MS66 , but it looks like not working !
    Is anybody can give me some help , it is urgent , thanks

    Hi Prasobh and Tajuddin ,
    Many thanks for your kind helping , but i am still some confusion.
    My scenario for example :
    I have Finsh Goods: <b>I001</b> and the BOM is <b>I00A + I00B</b>
    1.I have forecast for I001 , let's say 100KG
    2.I transfer SOP to Demand Management , use T-code:<b>MC88</b>
    3.Run MS02 for I001 then use MS04 to check result . LTP generate PlOrd for <b>I001</b>
    4.I go to <b>MS04</b> check result for material <b>I00A</b> and <b>I00B</b> , LTP generate <b>simreq</b> for both.
    5.Now i want to transfer the simreq of I00A and I00B to Operative Planning(MD04) use <b>MS66</b>
    I am not sure is that logical ? i meet problem on step 5 , that's means when i go to MD04 to check material I00A and I00B , the simreq not display in the list.
    Thanks again for your kind help !

  • NPROC:Dependent requirement not getting generated

    Hi Experts,
    We have an issue wherein we have Depedent requirement for a HALB material against FERT material requirement.But, the MD04 screen of HALB material doesn't show any Dependent requirement.
    Infact, the MD04 screen of the FERT material shows NROC in the MRP element data for the given period.
    NROC: It means that there are some errorneous components which were created by doing GR before a GI.
    I had tried executing MF47 transaction(which is COGI equivalanet in REM scenario) for clearing the errorneous components.But, i got the error as "Deficit of BA Unrestricted use". So,it means that it shall use my current stock for post processing the error componenets, which ideally shouldn't been the case as the stock was already consumed.
    Then, i found out that the BOM of FERT was not maintained.
    So,just wanna know that coz BOM of FERT is not maintained & the HALB needs to be defined as a component in the BOM of FERT in this case?
    or any other solution is there so that Depedent requirement for the HALB material reflects in MD04 screen.
    What we want: The recurring NPROC requirement which is coming for the year 2009, 2010 should permanently vanish from MD04 screen.
    Thanks,
    Rishi
    Edited by: Rishi. N. Khanduri on Jan 28, 2010 3:08 PM

    Harendra,
    Are you using "NETPL" as processing key for MD02? After 3 or 4 days is the dependent requirment getting created automatically or is it after MRP run again?
    Please provide more details,
    Regards,
    Prasobh

  • Dependent Requirements Planning

    Hey Gurus,
    I have a situation in which I have two materials that are planned with Independent requirements but also have dependent requirements against them.  these two materials are 6001116 and 6001771.  I have set the MIXED MRP indicator to "1", planning strategy "40" and MRP Dep. requirements as "1".
    6001116 is not planning the dependent requirements and is only being planned by the independent requirements.  6001771 is planing both the dependent requiremnets and the independent requirements even though I have set the MRP Dep. requirements to "1".  The only difference between these two materials is that 6001116, is a made in house product and the 6001771 is a purchased product. 
    I can't think if anything else that would control this to put me in this situation.  Do you guys have any ideas for me or things that I should check to make sure that this is working correctly?  I thought it was only the Dep requirements indicator that controlled the planning of independent reqs.

    Dear,
    You donot want dependent requirements
    to be created" for your components when MRP is run
    There are three Options:
    First Option:
    For the all respective components in MRP 4 view Input "1" for MRP Dep.Reqts
    Second Option:
    In the Basic Data 1 view maintain the X-Plant Matl Status maintain "01"(Blocked for Procurement/Whse)
    Third option,
    You can set the MRP type in material master as 'ND' (not planned) (MM02 > MRP1)
    Then Planned orders/Purchase requistions will not be created for the components
    Regards,
    R.Brahmankar

  • MRP: how to segregate the planned orders by dependent requirements

    Hello SAP Guru's,
    I would like to know if this is possible to make the MRP work is this way:
    - generate global planned orders (by date) for several dependent requirements, for inhouse production;
    - AND generate individual planned orders for each dependent requirement, for external procurement;
    For the moment, it is grouping the quantities of all the dependent requirements to generate a unique planned order by date.
    But we would like to get separate planned orders for each dependent requirements that are externally procured.
    Do you think it is possible to do so? and if yes, how?
    Thanks in advance for your help on this subject.
    Regards,
    Rudy

    In MD04 the demand n supply that is seen is considered as plant segment. In some cases when you plan demand n supply for a given storage location separately it is called as SLoc segment, also if you're working with MRP areas then its called mrp area segment, likewise for project & sales order.
    In short it is just a way MRP would do its planning. In normal cases, the demand n supply is in plant segment, so in this segment the least resolution that you can work with is a day, so all demand on a given day is clubbed together and a supply proposal is made (depending on the lot size).
    If you want further split on a given day, then MRP needs some way to identify the difference & this is provided by the special stock segment such as project segment. To see how it works, if you're working with PS module, ask your PS colleague to create a demand for the material from different projects for a given day. Then in MD04 you will see each project demand show up in different segment & when you run MRP, you will see the results.
    I guess more than me writing quite a lot out here, a simple test at your end should help clarify... good luck