Hi all,
We are performing our Integration test from SolMan. I would like to generate a consolidated report which will give me data same way as the status overview gives for individual test plan.
This will help me to track the progress at the test package level, which inturn is my IT scenario.
Any quick help will be highly appreciated.
Regards,
Smita

Thanks Prabhakar,
I am aware of this, but this gives me details for one test plan.  Even when I use STWB_2, it gives me summary of all the test plans, and for status overview I have to go in each and every test plan.
I am looking for some way out to generate the status overview of multiple test plans together in same screen, for reporting purpose.
Any suggestions?
Thanks,
Smita

Similar Messages

  • Hiding Status column in MSS Status Overview for Personnel Change Requests

    Hi,
    We have MSS implemented in SAP Portal.
    We are using Status Overview for Personnel Change Requests iview for which we have multiple columns displayed with data.
    We need to hide Status column in Status Overview for Personnel Change Requests iview for all the users.
    Can any body please let me know how it can be done.
    Regards,
    Pradeep B
    Edited by: pradeep balam on May 17, 2011 4:01 PM

    Hi Pradeep,
    Preview the portal page which you want to edit, in this case status overview in PCR. In the preview press the CTRL-key and right-click on the column that you want to edit. Here, you will be able to perform your customizations like hiding columns, labels etc
    Hope it helps,
    Prathamesh

  • Initialize visa to use for all tests

    Does anyone know how to initialize VISA to use for all tests then close it at the end of the last test?
    Example:
    The test sequence starts with initialize instruments then testing starts until the last test is to close all instrument handles.
    Thanks in advance.

    Is this a LabVIEW question or a TestStand question?  It actually does make a difference in my answer.
    If you are strictly only in LabVIEW, then you just pass your reference wires around where they are needed.
    What I like to do for TestStand is make an Action Engine to control my reference to an instrument session.  This method also works well with strictly LabVIEW as well.  But is overkill for somewhat simple applications.
    There are only two ways to tell somebody thanks: Kudos and Marked Solutions
    Unofficial Forum Rules and Guidelines

  • Single inspection plan for all Inspection Plan usages

    Hi
    I have to prepare a single inspection plan, than can be used against inspection type '04' and '15' and '01'.
    Please tell me which inspection plan usage I should use, I tried '3' = Universal, but at inspection lot creation the system is unable to find inspection plan.
    Thanks in advance.

    My customer manufactures semi-finished good, some times he can purchase semi-finished from the market. Sample are reserved for future testing as well.
    so following inspection types are required for the same material
    1) GR against PO                '01'
    2) GR against Production    '04'
    3) Sample Management   '15'
    Almost all the time, the same specifications are tested and my customer wants to maintain a single inspection plan.
    I have one option that is to create 3 inspection types using all the above  inspection types and to use the same "Usage" say '5' in customizing of Inspection Type. But I don't know the consequences
    Please give me other solution or highlight the consequences of my solution
    Kindly help.
    Edited by: Chris SAP on May 13, 2010 11:36 AM

  • Looking for Hyperion Test Plan/Strategy document

    Hi
    We have
    HYP PLAN (Prod Cost)
    Fin Reporting (Studio) *
    Interactive Reporting
    Web Analysis
    Apache Tomcat
    Work Sapce (Reporting Portal), ODI
    The planning application forms/reports etc development is complete. Any specific document one would share to do the UAT and/or make Test Plan would be highly appreciated.

    <<A fellow (non-genius) at the Apple store told me that if I take pictures with my DSLR (Canon) and select RAW only, it still makes a jpeg preview embedded in the RAW for the camera's screen view, i.e. an embedded jpeg-preview is part of the RAW standard. True or false?>>
    I'm not qualified to give much advice on the rest of your post, but the above statement is True. RAW files contain an embedded JPG. The embedded JPG is used by Aperture before a preview JPG is created (or if you have disabled preview generation).

  • Turn off status messages for all queries in RSRT

    Hi Gurus,
    I got some help on this issue in a previous question, but I ended up having to fix more queries than I expected.
    Is there a way to turn off the messages for all queries in the system through transaction RSRT?   Right now I'm doing it one query at a time.

    Hi,
    Go to Transaction RSRT, then enter SUPPR_ALL in the tcode box again and hit enter. This brings up the maintain messages screen and it suppress the messages globally
    cheers,
    Swapna.G

  • How do you add totaltime for all test steps in the report

    We are using xml reporting with the horizontal.xsl.  I see the totaltime property in the xml file.  I was able to un-comment some code in the stylesheet to display the module time for pass/fail steps.  I would prefer to see totaltime for every step.
    Alternative is to write some Labview code to extract test step name and associated times from the xml.
    Solved!
    Go to Solution.

    Hello
    If you can able to understand the Horizontal xsl, it is very easy to get show the available fields in the XML in the Report. Through LabVIEW also it is possible to extract the required
    Fields from the XML, you have to design an XML Parser  in the LabVIEW to
    parse the Step Name and it's time
    Attached code (a
    sample) can able to parse the Test Step Names, give the Report XML file
    Path as input, it will parse Step Names.
    What makes me unclear is, how can you use LabVIEW to show the total time?
    AshwiN,
    Attachments:
    Parse Test Results.zip ‏39 KB

  • REASON for ALL SHARE PLAN?

    I have unlimited 4g HTC Thunderbolt and now you stopping me from getting the upgrade. HAHAHAHA Funny. This is how you treat your customer??

    How are they stopping you? I am sure they will allow you to upgrade. You may not like the options, though. If you currently have unlimited data and want to keep it, you will not be allowed to get a DISCOUNTED upgrade. You can, of course, upgrade at full price if you would like to keep your unlimited data.
    If you do not want to go on the Share Everything Plan, you can add tiered data(starting at $30 for 2GB/month) in place of your unlimited data.
    You have 3 options when you want to upgrade, and I am sure Verizon will not "stop" you from doing any of the 3.

  • Required Unit test Plan for Data migration

    Dear All,
    I am looking for unit test plan Draft documents/templates which covers
    1. Testing tools
    2. Methods
    3. Error handling
    4. Reviews and approvals
    The project is a Oracle 10g data migration from one schema to another schema.
    It will be a greate help if anyone can forward the same to me.
    Thank you.

    Hi Vaishali,
    You may wish to refer the links below...
    https://service.sap.com/instguides --> SAP NetWeaver --> Release 2004s --> Upgrade
    https://www.sdn.sap.com/irj/sdn/developerareas/bi
    latest on upgrade tp BI7.0
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/2e8e5288-0b01-0010-2ea8-bcd4df5084a7
    Upgrading BW 3.X to SAP NetWeaver 2004s BI (PDF 2.6 MB)
    Front End Migration strategy
    Here's the migration strategy: Rolling out the New SAP NetWeaver 2004s BI Frontend Tools
    Presentation
    http://csc-studentweb.lrc.edu/swp/Berg/Articles/PM_2006_upgrade_NW2004s_Bjarne_Berg_v12.ppt
    Here are the frontend requirements:
    Troubleshoot the SAP NetWeaver 2004s BI Frontend Installation
    Here are the backend requirements in the product availabilty matrix:
    https://websmp110.sap-ag.de/~form/handler?_APP=00200682500000001303&_EVENT=DISP_NEW&00200682500000002804=01200615320900001250
    Migration of Web Teplates
    832713 - Migration of Web templates from BW 3.x to Netweaver
    Assign points if this helps.
    Regards,
    Anil

  • Quotation status overview Unit Basic Materual determination

    Hello,
    We employ the technique of the material determination between the copy of a quotation to an order.
    The alternative articles have all like basic unit PCE and sales unit M2.
    The conversion ratios are not the same ones for each article.
    For example for 1st article 1 m2 = 100 PCE, for second article 1 m2 = 25 PCE.
    But the selling price in M2 is the same one for all the articles.
    The material entered has the same basic unit and sales unit M2.
    The completion rule for quotation is u201CB Item is completed after full quantity has been referencedu201D
    When I create an order in reference with the quotation, the entered article is replaced by an article for example 1st list.
    The quantity in the quotation is 100 m2 and the quantity in the order is 5 m2.
    The item is automatically completed because the quantities calculated for the status of the item in the offer are false.
    In the flow document the quantities are 500 PC in the base unit of measure or 5,00 M2 in the document unit of measure.
    In the status overview for the item the status is u201CFully referencedu201D with 500,00 M2 referenced and 0,000 M2 open.
    The system tries to convert in the basic unit but they are not the same ones between the entered article (M2) and the alternative article (PCE).
    How to solve this problem?
    Thank you in advance.
    Best regards
    Frédéric Blaise
    e-Kenz S.A.
    MM01 Create material
    _ 6309006001 base unit M2 sales unit M2
    _ 6301311601 base unit PC sales unit M2 conversion 1 m2 = 100 pc
    _ 6301313601 base unit PC sales unit M2 conversion 1 m2 = 25 pc
    VB11 Create material determination
    _ Material entered 6309006001
    _ Alternative materials 6301311601 and 6301313601
    VA21 Create Quotation
    _ Item material 6309006001 quantity 100 M2
    VA01 Create Order with reference to quotation
    _ Material 6309006001 changed to 6301311601 and quantity is 5 M2.
    VA23 Display quotation
    _ Status overview 6301311601 Fully referenced 500,00 M2 referenced instead 5,00 M2

    Hello Frederic
    For Material Determination to work properly, I think both the original material and the substitute should have the same Base Unit Of Measure, which is not the case in your example. I think that is  the issue here. You may have different sales Units and conversion factors, but the Base should be the same I guess. Try to address that issue.
    Secondly in the condition record, You can maintain 'Susbstitute UOM',  maintain it with PCE and/or M2 and see if it helps.. I don't think it would.
    See the OSS Note which explains how sales units work in material determination.
    826249 - Manual product selection: VRKME sales unit
    Hope this helps.

  • Test  scenario and test plan

    Hi  All,
    Can somebody explain what is a test scenario and test plan with an eg ( For eg FB 60). and what are the essential things one needs to incorporate for test scenario and a test plan
    Appreciate your help.
    Thanks
    SM

    Hi,
    I am giving you the information on test plan and test scenario below. Please note that this is with reference to Solution Manager.
    You create a test plan for a project in the SAP Solution Manager if you want to reuse the project structure created in the Business Blueprint for a process-oriented test. You can select all the test cases and transactions which you have assigned to the project structure, for the test plan. These test cases are performed by testers; they can call assigned transactions and run test cases in them.
    Test Scenarios are nothing but the end to end business processes which are to be tested.
    Hope this helps.
    Rgds
    Manish

  • Test plan, Test scripts

    Hi friends,
    Please any one tell me, what is the Test plan, Test scripts, Test Scenarios and the procedure to create all.

    Test plan: How do you want to test, when and where and who will do the testing.
    Test scripts: a document which will contain all the test cases / scenarios.
    Test scenarios: will list the scenarios to be tested, in a logical order, expected results, actual results, defects, tested by and status.
    Procedure to prepare them: Just a word document. You should know the processes and the requirements to do this.
    Ravi Thothadri

  • Test Plan Progress report parameter

    I'm trying to use the Test Plan Progress report but the Test Plan field is always empty therefore I cannot render the report.
    The TFS is 2013 update 4 and I tried also with the report downloaded from MSF for Agile Software Development 2013.4 template. The cube is processed with no errors.
    Any ideas?

    Looking further I noticed that the MDX query that is populating the report parameter is not returning any data.
    Could this be a breaking change for the report from the last TFS update?
    Below is the query generated by the report:
    WITH
    MEMBER [Measures].[ParameterCaption] AS
    IIF([Test Plan].[Test Plan Name].CURRENTMEMBER IS [Test Plan].[Test Plan Name].[All],
    "All (No Filter)",
    [Test Plan].[Test Plan Name].CurrentMember.Member_Caption
    MEMBER [Measures].[ParameterValue] AS
    [Test Plan].[Test Plan ID].CurrentMember.UniqueName
    SELECT
    [Measures].[Point Count Trend],
    [Measures].[ParameterValue],
    [Measures].[ParameterCaption]
    } ON COLUMNS,
    ([Test Plan].[Test Plan ID].[All], [Test Plan].[Test Plan Name].[All]) +
    Extract(
    [Test Plan].[Test Plan ID].[All],
    [Test Plan].[Test Plan Name].[All],
    [Team Project].[Project Node GUID].[All],
    [Test Case].[Area Hierarchy].[All],
    [Test Plan].[Iteration Hierarchy].[All]
    ) +
    Filter(
    CrossJoin(
    [Test Plan].[Test Plan ID].[Test Plan ID],
    [Test Plan].[Test Plan Name].[Test Plan Name],
    StrToMember("[Team Project].[Project Node GUID].&[{4dad3f77-6199-41eb-af5a-a95f93b6af18}]"),
    StrToSet("[Test Case].[Area Hierarchy].[All]"),
    StrToSet("[Test Plan].[Iteration Hierarchy].[All]")
    [Measures].[Point Count Trend]
    [Test Plan].[Test Plan ID], [Test Plan].[Test Plan Name]
    } ON ROWS
    FROM [Team System]

  • Test Plan generation in SOLAR_TESTPLAN

    HI
    Is the test plan generation in SOLAR_TESTPLAN by default a transportable object?. If i save it as a local object i wont be able to transport it to other clients, but i want to create the test plans independant of the client systems. Please let me know if there is an option
    Thanks

    Hi
    You create a test plan for a project  if you want to reuse the project structure created in the Business Blueprint for a process-oriented test. means You organize tests after you have created a project structure in Create Business Blueprint,Configured, and want to test these configurations by process.
    then only you can select all the test cases and transactions which you have assigned to the project structure, for the test plan.
    When you create a test plan for a project, the default test plan structure is based on the structure of the Business Blueprint that you have previously created for your project.(hope i clear you that how it get sync).
    and yes you required to save the Test plan as tranportable package obeject directory, this is needed only for the optimizing transports.
    please check this [Transport testplan|http://help.sap.com/saphelp_smehp1/helpdata/en/69/38d2872daa11d5b37d0050dade3beb/frameset.htm]
    Thanks,
    Jansi

  • PCR: Status in the Status Overview table is not updated

    Hello,
    In MSS, a manager can look at a status of submitted Personnel Change Requests (PCRs).  The status field always displays "open".  It doesn't get updated. 
    I saw a few notes on this issue.
    Note 1004470 ISR status overview: Status change incorrect
    Symptom: The system does not refresh the ISR status overview for a request in the WebDynpro iView although the status of the request has changed.
    Solution Implement the attached correction.
    Later execute the QISRSTATUS_REP correction report contained in Note 947790.
    But the note 1004470 is already applied because we are on SAP_APPL version 17. Will the report help me out? I'm not a core abaper/hr consultant. So, if someone could help me explain what the report does, i run it.
    Also, can any one point out which data source (name of the RFC/workflow/others) fills up this data?