Consumption for make to order

Hi Experts,
I have a requirement ...." When I run MRP for the sale order for the finished product , system is creating palnning praposals for FERT material BOM and next level BOM'S also. But my requirement is  If stocks are there , system has to consume the stocks first of all RM's and HALB materials" .
I have maintained Collective requirements in MRP4 view for all materials , but still system is not considering my stocks .
Plz suggest me how to achieve this .
Thanks & regards
Prabhakar

Hi,
MRP will create dependent requirements for Raw Materials and HALB materials based on the FERT requirement. If system does not find available inventory for Raw Materials and HALB to meet the demand it will create the planning proposal (Planned Order) for lower level elements also.
Go to MD04 screen for the HALB materials and check what is the current situation (stocks...dependent reservations etc...)
Try and revert back.
Regards,
Swapnil

Similar Messages

  • Forecast Consumption in SNP for Make-to-Order products

    We are working on using APO-SNP for Make-to-order products (PlngStrategyGroup = "81" in R/3). We want to achieve normal forecast consumptino on FinishedGoodLevel and generate PlndOrders which shall derive component demand for purchasing (such PlndOrers wont be released to production - they should only function as demand driven on component level)
    What we have done so far: Forecast in APO-DP on Finished good level exists and has been released to SNP. The product gets "ciffed" from R/3 into APO material master with planning strategy group "20" (which is basically "make-to-stock") --> we were hoping this would allow us to use "normal" forecast consumption but nothing happens (FCST is not being consumpted by open Sales orders). Within the product view of such products APO is still "realizing" that this is a make-to-order product.
    Any other ideas / thoughts what could be done to achieve "normal" forecast consumption on FGI level for make-to-order products in APO-SNP ?
    Tks !

    I checked in /n/SAPAPO/RRP3 (Product View), unfortunately only FC exists there
    Seems that the open Sales Orders from R/3 are being created within another segment (the "element" Tab of RRP3 shows 2 segments:
    1) "Make-to-stock" (which contains the FC)
    2) "Make-to-order" (which contains the Sales Orders)
    That might explain the issue I see (FC and SOs are in different planning segment --> no consumption). Reading about planning segments in the help sounds like I need to find a way to bring Sales Orders for Make-to-Order products into the Make-to-stock segment  ... jus a thought .. any idea how to do this ? Does that mean I need to modify the CIF for Sales Order transfer for Make-to-order products ?
    Tks
    Thomas

  • Condition P101 for make-to-order

    For stock transport orders, you can use condition type P101 to pull the standard cost of the shipping plant into the purchase order.  Is there a similar condition type or routine that can be used for make-to-order product where we can pull the value from the EBEW table of the shipping plant?
    thanks,

    Hi,
    For transfering sale order stock to sub-contractor the movement type is 311-E. Here, you have to create the sub-contractor storage location & then transfer the stock (of BOM material) to sub-contractor storage location by movement type 311-E in transaction MB1B. While posting GRN of the upper material, system posts the consumption of the BOM material against the upper material.
    Hope this works.
    Regards,
    Prashant
    - Reward points if answer is helpful

  • Item category determination for make to order item

    Hi experts,
    how can I determine item category(tak) for make-to-order. mean what should I put in ITEM CAT.GRP, USAGE AND HIGHER LEVEL ITEM CATEGORY GROUP. Please advice.
    Thanks in advance.

    Neel,
    Goto VOV4 and create new entry with
    your sales doc type + itm cat group + usage + higher leve item cat = TAK
    Just check your item cat group in material. If you have created TAK without copy then also check your SL assignment with VOV5.
    Suhas

  • Customer return for make to order material

    Dear All,
    I am doing return process for make to order material.
    while doing return delivery, delivery qty has not come.
    when i enter it manually it shows error
    Only 0 NOS of material ABC001  available
    Message no. VL150
    Can anyone tell me the solution for this................
    Thanks in advance.............
    Babs

    Dear Babs,
    Pls go thru following thread:
    https://forums.sdn.sap.com/click.jspa?searchID=20199089&messageID=5745458
    Regards,
    Abhee.

  • Serial Number assignment in Delivery Note for Make-to-order

    Hi experts,
    In our current design, we have made it obligatory to enter the serial number in the delivery note for make
    to order stocks.
    We are also implementing PP and we would like to capture
    the serial number specified in the production order and
    automatically populate the serial number in the delivery.
    Any suggestions on how I can do this is greatly appreciated.

    Hi Karun,
    Thank you for your kind advice all the time. 
    I have been looking into it but the LIPS structure does not contain the serial number field...
    I have been looking for the routine in the copy control
    but have no luck finding such routine...
    Thanks for your continuous help and assistance.

  • Explanation on use of Strategies for Make to Order/ Make to stock scenario

    Hi Gurus,
    I have a scenario. In the BOM, the final Finished Product was to be made for make to order. There are two semi finished material below that. One I want to use it for make to stock and another for make to order. There is one more raw material at the bottom level which I want for make to stock. So I want to know what are the strategies I can use in the material master at all the levels for this scenario. Can anyone explain how can I do it in SAP?
    Regards,
    Brijesh

    Dear Brijesh,
    This indicator will determine the component how it should get produced either individually or collectively
    Example
    Fert 1 - strategy 20, requirement for this fert Via sales order is 10
    Fert 2 - strategy 40  requirement for this fert Via sales order/demand management is 10
    ROH is used in both Ferts and mainatined in BOM and also set to indicator 2 ( Colletive ) in MMR
    ROH requiement for fert 1 -1 ( BOM )
    ROH requiement for fert 2 -1 ( BOM )
    after MRP system will create only 1 PR for total qty 20
    If ROH is set to 1 ( individually ) then
    after MRP system will create 2 PR's as 10 each
    Hope it answers your query
    Regards
    Madhu

  • Material Training of AC520 (Controlling for Make to Order/Stock Production

    Hi,
    Is there anybody have the documentation (beside from SAP Doc) or training material of AC520 (Controlling for Make to Order/Stock Production ) ?
    I really need it urgently.
    Thanks

    Hi,
    I got the training material for other than AC520. Send me message to [email protected]
    regards,

  • Invoice Correction Requests for Make to Order

    Dear Gurus
    I am creating an Invoice Correction Request for an Invoice which was generated for Make to Order material. I am using Document type RK . I can save Invoice correction Request. But when I generate a Credit Memo it gives message that
    000010 "Create billing document" not allowed (Sys. status Cost, object VB0060000100000010)
    000020 "Create billing document" not allowed (Sys. status Cost, object VB0060000100000020)
    It should not ask for costing here in Credit memo Request.
    Even if I do costing for Line 20 it copies only Line 20 in Credit note  which gives wrong calculation. Because I  cannot change line 10 in Invoice Correction Request.
    Pl can you advise whether costing is required in Credit memo request. If not how can I handle this scenario.
    Regards,
    Neeraj Srivastava

    Hi,
    Just check if you attached status profile to either your sales order header or item.
    Just release that first and try again.
    Let me know if it helps.
    Regards
    Ravi

  • User Steps for Make to Order & Make to Stock

    Hi Sapians,
    Please guide me as to the users steps to be done in product costing for make to order & make to stock.
    Regards,
    Viki
    Moderator: Please, read the rules of SDN before posting. You can search for Wiki material or explore help.sap.com for basic process description

    Hi there,
    Make to order is when you manufacture or procure the material only upon order. Stocks are not maintained for those items in the storage loc. As & when the order comes, a production run is triggered through MRP. After the production, stock is posted as reserved sales order stock. Stock is then made available to fulfill the delivery.
    Other items are make to stock. Usually for fast moving or consumer goods, stocks are always mainatined in the plant storage loc. As & when the order comes, availability check is done. If stock is available to meet the delivery date, delivery is proceesed or a confirmed delievry date is proposed basing on the replenishment lead time in availability check.
    Regards,
    Sivanand

  • Mrp for make to order scenario

    hi gurus,
          I have got a different and challenging scenario in make to order planning. production planning has to be made on sales order basis.for eg : a particular finished product, a sale order of 100 nos is generated. but all 100 nos cannot be produced in single plant. so it has to be distributed to 2-3 plants. one more thing is, for make to order scenario, there is no fixed lot size. based on sale order quantity, planned order is created irrespective of fixed lot size maintained in material master. IF my batch size is fixed, for make to order also based on fixed based size, planned order has to be created.
      Can anybody suggest a better solution for this scenario?
    Thank you all in advance. all useful replies will be rewarded.
    regards,
    senthil

    Hello,
    For MTO, Lot for Lot order quantity is defaulted..
    So your receipt element will be as per your Sales Order.
    Try this:
    In T. Code : OMI4, for Lot Size : EX
    Change the MTO Lot size to "1" Lot-for-Lot with rounding.
    (Which is Blank by default - lot-for-lot)
    Maitain the Rounding Value in MRP-1 Screen or Use Rounding Profile..
    This Helps..
    Regards,
    Siva

  • Use of PIR consumption for advance material order (MTO prototype)

    Hi planing Gurus,
    I am investigating the possibility to use PIR to trigger replenishement long lead time sub level mfg or purchase products in the context of building MTO prototype. I believe I could use planning strategy 70/consumption mode VSFB to handle eventual actual requirements that will be created at higher levels.
    Q1. The parameters Fwd and Bwd consumption in MRP 3 are limitted. For instance, if I set 7 days each the system will only consider actual demand in this timeframe. I am not too in favor to set large value there to manage the fact that actual demand may not occur exactly as planned by the PIR. Is there any way the consumption can be iterative (eg. bwd 7, fwd 7, bwd 14, fwd 14)?
    Q2. Is there another mean to trigger replenishment of long lead time mfg part/purch part in the contexte of MTO prototype and manage consumption.
    Your help is greatly appreciate and speed up my curve to learn SAP PP architecture (I have experience with other mfg systems).
    Francois Paquet

    You had another question
    Q2. Is there another mean to trigger replenishment of long lead time mfg part/purch part in the contexte of MTO prototype and manage consumption.
    FOr this I would suggest even looking at Planning strategy (PS) = 50.
    This strategy are probably the most widely-used strategies in a make-to-order environment.
    Procurement of the long lead items (components) is planned by means of planned independent requirements entered at the finished product level. The system creates special planned orders at the finished product level for these planned independent requirements. These orders are only relevant for production once a sales order for the finished product exists.
    The assemblies are, however, produced or procured before the sales order is entered. Production is carried out up to one level before the finished product level, and the assemblies and components required for producing the finished product are placed in stock to await the incoming sales order.
    Final assembly is triggered once a sales order has been entered.
    Hope this helps you take a good decision.
    Thanks,
    Ram

  • What are configuration steps in implementation for make to order?

    please give the steps for normal production also.

    Hi,
    Below is the requested info:
    Make-to-Order (MTO) Production
    Purpose
    The planning strategies explained in this section are designed for the production of a material for a specific individual sales order. In other words, you do not want to produce finished products until you receive a sales order. This means that make-to-order strategies always support a very close customer-vendor relationship, because your sales orders are closely linked to production.
    The same relationship exists between the sales order and production that exists in a make-to-order environment. Make-to-order is also used in the following environments.
    Production using variant configuration
    Assemble-to-order
    Prerequisites
    Choose a make-to-order strategy, if:
    The materials are segregated. In other words, they are uniquely assigned to specific sales orders.
    Costs must be tracked at sales order level and not on material level.
    Make-to-order strategies should always be combined with lot-size key EX (lot-for-lot. Rounding values should not be used. If you maintain rounding values, they have no effect due to the make-to-order properties of these strategies.
    Process Flow:
    There are extensive options that enable you to procure components especially for specific sales order items.
    You may, however, want to use a different planning strategy to procure components without sales orders. This allows you to keep your replenishment lead time to a minimum. You can do this by:
    Planning on the basis of the finished product (see Planning Without Final Assembly (50) or Planning with a Planning Material (60))
    Planning at component level (see Strategies for Planning Components)
    Using consumption-based or Kanban-controlled components
    Customer stock can exist on any BOM level. See Stockkeeping at Different BOM Levels for more information.
    Because production is closely linked to sales orders, this results in a customer section in the stock/requirements list.
    Unplanned goods receipts (such as returns) cannot, as a rule, be used for other sales orders, even if they are in working order, unless they are adapted to meet a customer's needs.
    In the basic make-to-order strategy, Make-to-Order Production (20), no specific product structures are required. This means that it does not matter if the material has a BOM or not. The material can be produced in-house, or it can be procured externally. No planning is involved in this strategy.
    Planning Without Final Assembly (50) and Planning with a Planning Material (60) do require a specific product structure (i.e. a BOM, which means materials are always produced in-house). These planning strategies assume that you want to plan procurement (production or purchasing) of your components by planning the finished products. This means that you need to have a fairly stable demand for your finished products. If, however, you can plan more easily at component level than at finished product level, see Strategies for Planning Components.
    Configuration Settings:
    Create material master by maintaining general item category group- 0001(make to order)
    Availability check - 02
    Transportation Group - 0001
    go to va01 and raise sales order
    item category:TAk
    Schedule line category : cp
    Requirement type KE
    Requirement class 040
    Check TOR and avalability check
    special stock : E
    VOV7
    of TAK
    billing relivence : A
    Pricing :X
    go to mb1c
    maintain stock with a special stock indicator E
    mavement type 61
    Special stock E
    specify sales order number line item number and saveit
    go to VL01N main data
    Go to VF01
    save it
    Thanks
    Ram

  • Schedule Line for Make to Order Item.

    Hello
    In make to order scenario,  there are 2 schedule lines for the MTO item in create mode of Order. 0 confirm quantity on the req
    When I save the order, i can see only one schedule line with confirm quantity 0.

    Hi,
    Make-to-order production is controlled by the requirements type. The requirements type is
    determined on the basis of the MRP group and the strategy group in the material master record.
     Create material by specifying item category group as 0001 = Make u2013 to u2013 order (Normal item)
    In MM01 Basic data tab, General item category field [0001] = Make u2013 to u2013 order, 0002 for configurable
    material
    Make u2013 to u2013 order checking group for availability check should be [02] = Individual requirements in Sales:
    General/Plant tab.
     Go to VA01 and raise the sales order by specifying this material that we created in the previous step
    Item category is TAK
    Schedule line category = CP
    Requirement type = KE [Sales order Header  Procurement  Requirement field]
    KE = Individual customer order without consumption
    (For standard items item category group = NORM)
    System determines requirement type 041-order/delivery requirements. This requirement type points requirement
    class where we can control whether the system has to carryout TOR, Availability check, and Product allocation
    functions.
    Hope this helps.
    Regards,

  • Sub-Contracting for Make to Order

    Hi all
    We are having Make to Order Scenario. We have created a sales order and some materials for BOM have to send for Sub-Contracting Process.
    I have created a PO with Acct Assignment "E - Ind. cust. w. KD-CO"  and Item Category as "L".
    But as per Standard SAP Acct Assgnmt "E" and Item Category "L"  is not possible.
    Consider the Header material is "X "  and Component is "Y".
    I am having Material "Y " in Sale Order Stock. Now when i do MB1B using 541 mvmgt type the system is not allowing me to post .
    please suggest me this scenario how to proceed. 
    <b>For a Make to Order scenario how to do Sub-contracting Process.</b>
    Regards
    Kumar

    Hi,
    For transfering sale order stock to sub-contractor the movement type is 311-E. Here, you have to create the sub-contractor storage location & then transfer the stock (of BOM material) to sub-contractor storage location by movement type 311-E in transaction MB1B. While posting GRN of the upper material, system posts the consumption of the BOM material against the upper material.
    Hope this works.
    Regards,
    Prashant
    - Reward points if answer is helpful