CONTRACTS FOR SERVICE ACTIVITY MASTERS

We have created contracts (Document type MK) with item category service. When creating a Purchase Requisition for the Service Activity Master, source determination is not done with reference to the contract. The contract number and line item number must manually be entered.
Can anybody maybe assist me in how the contracts functionality for service masters should work?
Thanx

hI,
1. First you have to create a requisiiton for serivces and assign the source of supply in ME51N.
2.Then with reference to this requisition create a contract in ME31K
3.Then create the release Orders in ME21N and specify the service qty in item details.
4.Then post service entry sheet in ML81N with reference to this PO.
5.Then Do the invoice verification.
This is the cycle to be folowed for contract services.
Regards,
Bharat.

Similar Messages

  • Contracts for services without service masters - updating material group

    Hi all
    I have some contracts for services where the services themselves are not linked to service masters. If the material group is updated in the contract at item level, this change is not being applied to the service lines. When the services are pulled through to a purchasing document the original material group / G/L allocation is being used rather than the updated one.
    This issue also occurs if a new contract is set up but the services are copied from an existing contract. The services adopt the material group of the original contract rather than the new one.
    Any ideas on how this can be overcome?
    Many thanks

    Business workaround implemented since was unable to resolve.

  • Open PR, PO and Contract for services.

    Dear All,
    I want to develop a report that gives the open PR, PO and Contract for services.
    When user will enter the service number report will give the open PR, PO and Contract.
    But for services quntity in item overview is always 1 AU.
    I want to compair the quantity in item details (ESLL - MENGE).
    Suppose PR is with 100 Hrs and 3 diffrent PO created for this with 25 Hrs each.
    How Can I compair this.
    Thanks and Regards.
    Prakash

    TNX

  • Purchase requisition for service activity / element cannot be generated

    Dear SAP MM Experts,
    This is a service Creation from the PM order to Purchase Sercive Requisition.
    The Error Message Is Generated :Purchase requisition for service activity / element cannot be generated
    Diagnosis
         Due to the system settings, the system is trying to generate a purchase
         requisition for a service activity or a service activity element.
    No service package has been created for the activity/element.
    As a result, the system cannot generate a purchase requisition.
    The activity/element is created or released, but the indicator for
    generating a purchase requisition is not set.
    Create a service package for the activity/element and then generate a
    purchase requisition.
    regards,
    A S

    Solved From PM side

  • Local contract for service master doesn't picked in PDP

    Dear Experts,
    We are on SRM 7.0 and in using PDP Scenario. Having created a local contract for service master which is released and acting as a source of supply when creating the shopping cart for the service master, however when purchase requisition is being transferred to the SRM system agains the same service master the shopping cart in available in the sourcing cockpit instead of picking the existing contract. Set the option as "sourcing carried without source of supply" , however this scenario works well for material master but not for service master, please advise me on this fix or any limitation in this version.
    Thanks and Regards,
    Venkata Koppisetti.

    Wrong assignment of P org with P grp is the route cause, found the error and rectified which is working fine.
    Thanks and Regards,
    Venkata Koppisetti.

  • Contracts for service

    We're using SRM 5.0, and need to evaluate options for creating Contracts for services, and having PO's sourced against the contracts for services provided over the course of the contract validity period. 
    Any suggestings or resources that explain how SRM can create / manage Service based contracts?

    Hi
    Refer to few links, which will help.
    http://help.sap.com/saphelp_srm50/helpdata/en/1f/fba93e08503614e10000000a114084/frameset.htm
    http://help.sap.com/saphelp_srm50/helpdata/en/39/0f343e47fd6b2ee10000000a114084/frameset.htm
    BR,
    Disha.
    Pls reward points for useful answers.

  • Requirement Date of PR for Service Activity

    Hello All,
    Can any one tell me how to enter the requirement date for service activity?
    Scenario is that I don't have budget in current fiscal year, hence; cannot book my commitment. So, I want to book a commitment in future (for next fiscal year). How can I enter requirement date for service purchase requisition?
    Thanks in advance.
    Warm Regards

    Thanks for you quick response.
    In this case I have to create multiple service activities. Is it possible that I can split service items from one service activity into muliple fiscal years.
    For Example: There are three service items in activity XYZ, I require two items in current fiscal year and one item in the next. Please advise...
    Regards

  • Service specifications screen for service activity becomes grey after PO

    Hi All,
    I would like your views/comments on the following issue:
    I am creating a service activity PS04 , it takes me to the service specification screen,then I am using the single item to create the painting services. The PR is generated for the activity. Till PO is not created for this service activity I am able to add other services as required functionality.
    The issue is that once i create the PO for the service activity PR line item, the whole screen of the service specifications becomes grey i.e not editable . can you give me the inputs why that so?
    In the ideal scenario  & the requirement is that, it should grey out for the service lines of the PR for the lines where PO is created not the whole screen.
    please provide the suggestions / solution to this issue.
    Thanks in advance
    Ramu

    Hi
    Thanks Virendra for your effort in this replication in IDES. I checked the service activity & its settings which are correct and it is not the issue. 
    Do you have any idea of the configuration / user exit in case of PO is created it will not allow the change mode of the PR for service activty generated from projects.
    Thanks in advance
    Regards
    Ramu

  • MRP for service activity?

    Hi
    Can MRP generate service PR for a service activity?
    As per my knowledge it's not possible through MRP.
    But my boss is insisting me to use MRP for service? Does it really make sense?
    If yes, how can it be done?
    Thanks

    MRP is relavant only in the context of material components assigned to project network activities as stock items. It's strictly a tool used to make sure that your materials to be kept in stock are procured in a timely manner. I am not sure you can justify a service in the context of "material replenishment".
    What is the business justification of an MRP run for a service?

  • Deletion flag for service activity numbers

    Hi all,
    How to set the deletion flag for the service acitivity numbers in the AC03/AC06.

    If the Service Entry Sheet is to be cancelled then go to ML81N and Select PO / SES and Click on "Change" Mode and Go to Menu Service Entry Sheet --> Set Status --> Revoke Acceptance.
    The Procedure is Same for Cancelling the Release.
    For Deletion of SES Press Shift F2 or Menu Service Entry Sheet --> Delete & Save.

  • Control key PS05 for Service activity in Network Profile

    Hi,
    I am creating a network profile in OPUU in which in activitie tab -> Services -> I am using control key "PS05" tos g plan and procure external services through Services.
    but it is giving me error - The control key "PS05" is not valid. Message no. CS070
    Can you please guide me in resolving the error?
    Wtih Thanks and Regards
    Ratna

    Hi
    Go to OPSH - Choose PS05
    The fields "External Processing" and "Service" - You can try to play around with these fields
    Br, Ajay M

  • The net price is calculated incorrectly for service items in contracts

    The net price is calculated incorrectly for service items. Iu2019m creating a contract for services, transaction ME31K (without service master). At the services level Iu2019m adding u201CConditions Supplementsu201D:
    -     PRS (gross price) =1000 EUR
    -     Z999 (discount) = -100 EUR
    -     ZPRS (cost) = 1500 EUR
    The gross price is calculated correctly = 2400. My problem is with the net price, with this example the net price is just 1500 this means that is just considering the condition ZPRS.
    Where can I customize the net price determination to considerer all price conditions?
    Thanks in adavnced

    Hi,
    In the service industries area, SAP uses two calculation schemata,       
    MS0001 for contract/master services (Z999 must be added to MS0001) and otherwise, MS0000. Assignment    
    occurs according to the Customizing settings defined under     
    'Materials Management -> External Services Management -> Maintain        
    Conditions for Services -> Conditions: Schema for Services'. If you want 
    to use another calculation schema for contract/master services, you must 
    define this with an own entry under Maintain Conditions for Services ->  
    Variable Calculation Schema for Services', for example, in the form 'K   
    WK value contract MSxxxx service schema', if a corresponding schema      
    MSxxxx has been defined first.       
    If Z999 is a header discount for the service outline level, it must be added to MS0002.
    Like the standard  discount condition type ZA00 the Z999 must have Cond. class   A  for Discount or surcharge in the condition type setting in the customizing, and no access sequence should be assigned to it.
    Please read the notes 798798 and 353482.
    Regards,
    Edit

  • Framework contract/order for Services

    Dear All
    Can I make a Framework Contract(Services) and then corresponding Framework PO doc type FO so that I can do MIRO directly for Framewrof PO without GRN.
    Also is it possible that I make a framework contract for services and directly do MIRO against the contract without creating framework PO??
    Regards
    SK

    Hi Satish,
    The Note 175510 should clarify this for you:
      "The combination:
      GR:              set
      GR-non-val:  not set
      IR:              set
      GR-based IV: not set
      is not supported by SAP in this connection.
    Regards,
    Purnima.

  • Value Contract for a material group

    It is possible to create a contract on value basis for a particular material group without material masters.
    Thanks
    Sanjeev

    Hi,
    You can create contract value basis for a particular material group without material masters like for example creating contract for service where you can use item category D but you should use always account assignment category U ( contract without stock material ) & later in creating contract release order or call-off WRT contract, you can change account assignment category U to account assignment category K or as required.
    Regards,
    Biju K

  • Determination of Source for services in SRM rel 4.0

    Hi
    We have requirement to have list of vendors determine automatically in shopping carts for services.
    In this release 4.0 if you have contracts in R/3 this determining of vendors works for non-service/material items but not for service.
    I log a call with OSS and they say this is not included in SRM4.0 due to different backend structure for services.
    If we don't upgrade to SRM 5.0, how could we get SRM to give users list of vendors which have contracts for selected shopping cart services in R/3?
    I will give points for answers
    ty, Z.

    Hi Zuzanna Breda,
    You can replicate your contract created in the backend R/3 system as a Vendor list.
    If you click on Source of Supply and go into preffered vendor you will be able to see the option vendor list over there which is nothing but the contract and the items.
    You can create vendor list in the SRM system or can replicate the contracts for services/material as a vendorlist.
    You can also define an output type for the contracts so that any changes or while creating a new contract in the backend system it gets automatically replicated into SRM
    There are standard function modules to create the vendor list.
    Cheers
    Sandy