COPA -update new value field

Hi All,
We have 3 revenue value fields and created new value field to capture total revenues for all 3 revenue value fields.
only new sales orders total revenue value field is populated with revenues.how can we update old sales orders revenue value field information with total value field?
Revenue A + Revenue B + Revenue C= Total revenue
Thanks,
Anusha

Hi Anu
KE4S is one option
Another one is to do KE21n.. but that will be cumbersome.
You can develop a custom program using Bapi to upload the values automatically
Last option is to add those values in report manually or using key figure scheme ker1
Br. Ajay M

Similar Messages

  • Populate New Value field in COPA for Previous periods

    Hi All,
    I have added a new value field to COPA structure and regenerated the Operating Concern. But I dont know how to populate this value field for all the exsiting records. Any help would be appreciated.
    Thanks
    MKR

    I have to manually update all the COPA tables for reporting.

  • Impact of Addition of New Value Fields in the existing Op. Concern-COPA

    Hi All,
    Want to know the steps of adding new value fields in the existing operating concern in COPA?
    What is the overall impact of addition of New Value fields in the running Operating Concern?
    How do we test the addition of new value fields?
    Is the addition of New Value fields to the running Operating Concern advisable?
    Your support and advice is highly anticipated and appreciated.
    Thanks & Regards
    9819528669
    Ohter details are as follows...
    VALUE FIELDS : Defines the Structure of your Costs & Revenues. (Op. Concern 120 Value Fields) 
    1)     The client requires three new value fields to be created. Value fields for :
    -     Other Airport Charges - International
    -     Cargo Commission Cost
    -     Personal Cost (Direct)
    2)     What are the Steps involved in creation of new value fields? The steps are :
    1)     Before creating new value field we need to check whether we can use already existing UNUSED value fields (There are 62 value fields created for the op concern 1000, in production the value fields TBUL1-L7 i.e. to be used (I assume) screen shot1 provided. My predecessor has used value field VV291, VV292, VV380 original description being TBUL3, TBUL4, and TBUL1. I believe he has changed the description in development client and created a transport request ref screen shot 2)
    2)     You can create new value field thru T-Code KEA6 (4-5 characters beginning with VV) u2013 My predecessor has reused the value fields originally created he has not created new one I believe. please provide give your comments)
    3)     Specify whether this field is for Currency or Quantity (currency defined in attribute of op concern and quantity defined by its own field u2013 unit of measure) u2013 My predecessor has configured the three value fields as Currency.
    4)     Describe how the values in this field are aggregated over characteristics. (SUM, LAS, AVG) u2013 My predecessor has aggregated all the three value fields as SUM and they are in Active status.
    5)     After the value field is created you have to add the value field (active status only) to the operating concern by Editing the Data Structure. (I guess this is done in the next step)
    6)     Assign newly created Value fields to the Operating Concern u2013 T-Code KEA0 (In development client the value fields are assigned to the op concern 1000 refer screen shot 3. In the production client also those three value fields exist (does it mean they are assigned? your comments please.) As they have the original description TBUL3, TBUL4, and TBUL1 refer screen shot 4.
    7)     After the Data Structure is defined you need to activate them. (creates plan vs actual database) u2013 Go to the data structure tab and Choose Activate. The status in dev client is Active with correct description but in the production client it is Active with the OLD description. After addition of the value field you need to regenerate the operating concern. T-Code KEA0 u2013 right?
    8)     Condition Types are assigned to Value Fields? Donu2019t know u2013 T-Code KE45 (I think this is NOT required in our case u2013 Please give your comments)
    9)     Define and Assign Valuation Strategy u2013 Cost assigned to Value fields u2013 T-Code KE4U (I think this is also NOT required in our case)
    10)     Define PA Transfer Structure for Settlement u2013 T-Code KEI1 (This step is crucial u2013 I think I have to to include newly created value fields, but am not aware how to do it and what is the connectivity or what happens after this is done)
    Note: My predecessor has created a Transport Request No# KEDK902167 for the value fields created by him.
    3)     Whether my predecessor has performed all the steps for value field creation? How to test it and check that?
    4)     If yes then,  Do I need to perform additional configuration or can I proceed to transport it to Production?
    5)     What is COPA Allocation Structure & PA Transfer Structure? Where and Why It is used?
    6)     What are the different methods of cost and revenue allocations in SAP?
    7)     I have checked the status of the value fields across clients, It is as followsu2026
         Value Field     Value Field For     Description     Development      Quality     Production
    1     VV291     Other Airport Charges International     TBUL3     Exists      DNE     DNE
    2     VV292     Cargo Commission Cost     TBUL4     Exists      DNE     DNE
    3     VV380     Personal Cost u2013 Direct     TBUL1     Exists      DNE     DNE
    #DNE : Does Not Exist (assumed since the description given to value field is not the same as in development client.)

    HI sree,
    ofter creation value field and saving that time reqwest number appeare copy the reqwest number and go through the se01 select that reqwest number select and transport click the truck symbole, and draft a mail to basis guyw.
    Thank You!
    Best Regards,
    pradheep.

  • COPA Re-alignment fro new value field

    Hi,
    I would like to know if the COPA realignment would popolate the values for a new value field for the past transactions.
    Regards
    Venkata Devaraj

    Hi Jayram,
    Thanks for the response.
    Yes I want to either change the mapping for a existing quantity value fields or add another value fields for quantity. I am exploring this 2 options.
    In both cases I want to populate the data for the history records. i.e for the transactions that have been posted till this change.
    Is this possible in COPA.
    Regards
    Venkata Devaraj

  • Transporting New Value Fields in COPA

    Hi All,
    I have created new value fields in COPA and regenerated the Op Concern in Dev. I need help to transport them to Quality and then to Production.
    Basically I need help on the Objects I need to select and pre-cautions I need to take.
    Appreciate your help on this.
    Thanks.
    Sree

    HI sree,
    ofter creation value field and saving that time reqwest number appeare copy the reqwest number and go through the se01 select that reqwest number select and transport click the truck symbole, and draft a mail to basis guyw.
    Thank You!
    Best Regards,
    pradheep.

  • Transport COPA new value field

    Hello SAP Experts,
    I have created a new COPA value field. Now i would like to transport the same to Test (Acceptance or Quality) server, can you kindly let me know how can i proceed with this.
    Your inputs are highly appreciable in this regard.
    Many thanks in advance.
    Regards,
    Pavan Kumar P

    Hi,
    Please read note 131664 regarding the use transaction KE3I to transport operating concern structures.
      In principle you can transport a new value field with a transport of an operating concern - part 'Structures: ABAP Repository objects' in transaction KE3I.
      You need to perform the following steps:
    1. Value field added in source system thro tcode KEA6
    2. Regenerate the environment of operating concern in source system (tcode KEA0)
    3. Transport using KE3I (select: ABAP repository objects)
    4. Regenerate the environment of operating concern in target system.
    Via transaction code KE3I you have the option to transport specific object classes.  If you select 'Structures: ABAP Repository objects' the following settings are transported:
    Cross-client objects in the SAP Repositiory
    - Tables and structures of the operating concern (CE1xxxx - CE8xxxx)
    - Domains and data elements for CO-PA characteristics
    - Master data tables for CO-PA characteristics (without data)
    Cross-client control tables
    - CO-PA field catalog
    - View directory
    Normally we advise customer to add a new value field/characteristic to
    DEV then transport to QAS and then transport to PRD. This ensures that
    the operating concerns in the 3 systems are in sync.
    regards
    Waman

  • New Value Field in COPA

    Hi
    I have created new conditions in SD. These have been assigned to a value field which was never assigned to any conditions. Now this KE4I config is moved to test system and I found that values of these conditions are not appearing under new value field.
    Earlier these new conditions were assigned to old value field and those were coming correctly in billing doc. Still these conditions values are appearing under that old value field.
    Am I missing any step ? Please help
    Raj

    HI,
    Billing document value flow is as per KE4I mapping to value fields.
    There are some value flow analysis tools under CO-PA to check your settings with respect to value flows. Use transaction KE4ST (Simulate billing document transfer -> Value flow (<Ctrl +F7>) to check where things went wrong.
    Hope this helps.

  • COPA - New value field defined as "Last Value"

    Hi experts:
    We have defined a new value field that it is integrated as a 'LAST VALUE' instead of 'SUM'. However, when posting different entries the amount continue to sum instead of showing the last value. The new value field has the same behaviour as a sum value field. In KE30 all entries are summarized and in table CE3XXXX I can see all entries summarized.
    Now, I have to entries (100 + 125) for the same characteristics and the value field show the total amount 225 instead of the last value 125.
    Thanks in advance for your help
    Best regards
       Jose

    Hi,
          The 'last value' is typically used for no of employees or some similar value where the last number is really important. In such cases it does not make sense to use this field in KE30 reports and take the sum of these values.
        In such cases only the last entry posted is important from reporting purpose. Also this type of value fields are important in planning.
    regards
    Waman

  • COPA  new value field transport

    Hi
    Is there any way to trnsport only the single value field in COPA to other instance?
    Regards
    HK

    Hi,
    If Value field is assigned to Data structure then you need to regenerate operating concern in KEAO. you cannot transport single value fields in COPA. All value fields which are assigned to Data structure are  picked during transport.
    Regards,
    Sreekanth

  • New Value Field

    Dear Friends,
    We are planning to add new value field in current copa structure, for this I need know :
    1. As soon as we add new value field current operation conern gets deactivated ?
    2. If there is only one server for development and production then as soon as we create value filed in development, what would be the impcat in production client ?
    3. If server is same than transport of value field is required ?
    4. If required then opernation concern shuld be re-generate after transport ?
    5. If server is same then operating concern has to be regenerated in every client ? i.e. dev, testing, preprod, prod.
    and what ever impact would be in this case and also if we have different server for dev nad product. Kindly let me know about you expert comment.
    If there is any risk while regenerate operating concern, also please let me know.
    Thanks
    Ravi

    Hi,
    Activation of Operating concern has two aspects- Cross client and client specific...  for your questions.. if you have operating concern in the same server it is enough if you activate only client specific one..
    On each change of u r datastructure i.e changes to characteristics and value fields u need to generate.. till then it will be in Inactive mode..
    In terms of different systems generally u can transfer the active operating concern on addition of new value field.  However sometimes it may be required to activate specifically..
    Regards
    Sudhakar Reddy

  • New Value Field Transport

    Experts,
    How shall I transport a new value field I have created. Also, I have assigned this value field to one of the operating concern...
    I understand it has to be transported via KE3i. After that needs to Select Operating Concern..after that I am confused what to select ??
    Please advice
    Amit

    Hi,
    If Value field is assigned to Data structure then you need to regenerate operating concern in KEAO. you cannot transport single value fields in COPA. All value fields which are assigned to Data structure are  picked during transport.
    Regards,
    Sreekanth

  • Impact of adding new value fields in ongoing operating concern.

    Hi All,
    Want to know the steps of adding new value fields in the existing operating concern in COPA?
    What is the overall impact of addition of New Value fields in the running Operating Concern?
    How do we test the addition of new value fields?
    Is the addition of New Value fields to the running Operating Concern advisable?
    Your support and advice is highly anticipated and appreciated.
    Thanks & Regards
    9819528669

    HI,
    please search in SCN forum before you post:
    Re: Adding a ValueField to an existing Operating Concern?
    Best regards, Christian

  • Issue in Creation of new Value Field in CO-PA

    Hi,
    I have a query in CO-PA Value Field Linking.
    In my Development Client,
    1. Created a New Value Field (No Transport Request Generated)
    2. Linked to the above to new Conditon type created in SD. (Tranport request was generated) i.e. in Flow of Actual Values->Transfer of Billing Documents->Assign Value Fields
    However then i try creating a new Value Field in my Production Client it throws a message 'You have no authorization to change Fields".
    Is this an issue with authorization or i need to transport the Value field too from Development to Production client.
    Please Advise.
    Thanks in Advance,
    Safi

    Thanks Phaneendra for the response.
    The creation of Value field did not create any tranportation request. Will this too be transported if i transport the Operating Concern.
    Please Advise.
    Thanks,
    Safi

  • Wrong updation of value fields

    hello,
    In a sales return invoice, the cost is getting updated in value field cost of free goods rather than value field cost .
    Please guide me in this .
    Thanks

    Hi Muscan
    What is the condition type in SD Pricing procedure for Cost during sale return? (Check your Sales Order - Pricing tab)
    See assignment of that cond type to val field in KE4I
    Regards
    Ajay M

  • Maintaining operating concern after adding new value field

    Hello,
    I added a new value field to our live operating concern,maintained the data structure throguh KEA0(Maintain operating concern).The changes are transported from Development to Quality,Changes were reflected in Q system.After testing in Q system transports were pushed to production system.The new value field is added to the operating concern. When i check the log for KEA0 in production system it displayed one message like:
    Field VV088 was added to the reference structure
    Message no. KE782.You probably either  changed the operating concern or SAP-EIS aspect, and added the field VV099 to the definition.
    The added a CO-PA value field:
    In this case, the field is added to the definition or the summarization levels. This invalidates all existing levels. Consequently, you need to activate them again and fill them with data.
    In production system maintaining operating concenr or KEAO is only in display mode.Is it needed to regenerate the operating concern once again in production, how to do it. Is the message talking about the KEDV summarization levels.?
    thanks
    rahul

    Hi,
    No no ....KEDV is nothing to do here....that is creation of summarization in CO-PA.
    Since you added new value field you necessarily have to Regenerate the operating concern...
    Use Tcode KEA0...go to Environment tab...there the status of Cross client part  and client specific part both will be in RED....now just click on the Cross client (candle button)...now the system would regenerate the operating concern...once it is over do the same for the client specific...
    Beware when you do regenerate the operating concern no body can enter any transaction in that server since it is cross client table ...hence better do it after business hours.
    Hope this helps!
    Running KEDU with rebuild is relevant only when you already have created summarization and called up the same in the CO-PA report "options" tab. If you did not created the summarization you are nothing to do with KEDU.
    Next: The new value field has to be transported to PRD and hence even in PRD we have to do the regeneration manually.
    Regards,
    Velumani
    Message was edited by: Velumani Arunachalam
    Message was edited by: Velumani Arunachalam

Maybe you are looking for

  • Lock-ups on 7day old MBP

    Ive been having issues since day 1 with my 2.4ghz C2D 17"MBP with highres screen... Ive used fan-control software to put my fans up to there max speed with the lowest temp thresholds, but, im still having problems. Under Windows XP (bootcamp) when I

  • IPhone 5 iOS7 - Sending text to multiple recipients.

    I have recently upgraded from my trusty iPhone 3GS to an iPhone 5 with iOS7. The phone is locked to the UK O2 Network. When abroad multiple recipient text could be sent incurring a European Text Message Cost of 6p per recipient. So far so good. Idid

  • Cannot fix failed updates Code 80072F78

    I have W7 VM with failing Windows Updates that MUST be repaired. After spending some time trying to fix the problem I have no other choice but asking for help. The messages are in French but I guess it will not create any problem for getting it... St

  • Add fields in Additional Data Tab

    Hi I want to show some additional characteristic fields which are not showing in Additional Data Tab. Can anyone tell me how can i show the additional fields. Which transaction should i use to show the addtional fields. Regards Harshini

  • Error trying to insert xml into Oracle table

    Hi - I am trying to (a)read a row from emp table and output the results in xml format and (b) insert this row to another emp_new table (same structure as emp). When I run it here is what I get: OUTPUT IS: <?xml verions='1.0'?> <Employee> <Emp num="1"