Copy Transport Request to other new transport request

Hi Gurus,
              I collected Info Objects, Info Areas, Application Components in on transport request. I want to split Application objects and Info Area into new transport request. So that I can have Info Objects with existing transport request and other objects in new transport request.
            I tried in SE01 to include objects but I am not sure which option I need to select. I want to select specific objects to copy to other transport.
            Appreciate your help.
Thanks
Ganesh Reddy.

Ganesh,
You can delete the Info Objects and info area from the existing transport and collect those in separate transport request by change them .
Go to SE09 and select the Request --> Go to Task and double click --> Go to change mode and delete the info objects and info area ..
Hope it helps ..
Ravi

Similar Messages

  • What is the difference between "new meeting request with" and "new meeting request"

    Hi all,Can anyone tell me that what is the different between "new meeting request with" and "new meeting request" on Outlook?Please help me...Thanks!Tony

    Are you using Outlook 2003? The option “new meeting request with” is only available when it is a public folder or shared calendar in OL2003.
    Tony Chen
    TechNet Community Support

  • One Transport request objects copy into new transport request

    Dear Experts,
    I created a transport request under which i saved my objects. <b>Now i need to  copy  old request objects into new request  or  split that transport request into number of new transport requests.</b>  First of all It is possible or not , if it is possible please tell  me the solution how to do.
    Regards,
    Krishna

    Hello Krishna
    You can
    (1) add object lists of already released requests ("old" requests) to you current request (still changeable)
    (2) merge changeable transport requests together
    (3) split a changeable request into several requests
    Whereas (1) and (2) are supported by standard functions of the SAP system (3) is a manual task involving the following steps:
    a.) Create a new request
    b.) Copy required transport entries (e.g.  R3TR TABL ZMYTABLE) from one request to the new request
    c.) Delete all copied transport entries from the object list of the "first" request
    However, if you are not fully aware of the dependencies between different transport object entries the splitting of object lists may cause hassle when you import the splitted requests into the next SAP system.
    Regards
      Uwe

  • Create a new transport request for note 898614

    Hello,
    I want to set up the service desk function in the solution manager 4.0.
    In the IMG I'm pointed to note 898614. Here the settings are described but not clear anough for me.
    Here are the first two steps:
    1) In transaction SCPR20, activate the following BC set:
    SOLMAN40_SDESK_BASICFUNC_000. Activate this in expert mode with the option "Overwrite everythng".
    2) Create a new transport request (transaction SE09) in the source client (000) of your Solution Manager system. Unpack the file Piecelist_Service_Desk_Init.zip from the attachment to this note. Copy the contents of the file Piecelist_Service_Desk_Initial.txt to the transport request. Use transaction SCC1 to import the transport
    request to your Solution Manager client.
    Unpack the BC sets contained in the file SOLMAN40_SDESK_SP04.ZIP.
    In transaction SCPR20, activate the BC sets. The BC sets contain additional actions.
    Activation must take place in expert mode using the option "Overwrite everythng".
    Then, implement Note 931196 if necessary.
    My question is how do I create a new transport request and how do I import the file Piecelist_Service_Desk_Initial.txt in to this request.?
    If I press the button create in tr-se09 I could choose between 6 differend transports. Which wan do I have to choose?
    And how to import the Piecelist_Service_Desk_Initial.txt  file.
    Kind regards,
    Richard Meijn

    Hi,
    go to SE09 in Client 000 and create a transport request of type workbench. You may use copy&paste from piecelist text file to add objects to your transport request.
    Logon to your production client where you want to use Service Desk functionality and import that transport using transaction SCC1.
    /cheers

  • New transport request for smartform.

    hi to all,
    i want to create new transport request number for already developed smartform..
    for that smartform already transport request is there,its also released.
    as per requirement i modified  something,now i want to move into production.
    how to create new transport request.
    plz giv me reply asap.
    thanks n regards
    murty

    hi anand,
    small modification in my req. is
    for smartform one transport reqst is there,its nt released.
    after some modifications whatever done,after cmpletion of dat,i saved,at that time it's nt asking new  transport req.....,
    i think if alreadsy is there,thats y its nt asking.
    but in properities date n time is there,those r same wenever the transport req.. was created,those r displayed.
    they r asking 2days date n time  wid new modifications of smartform.
    if that previous transport request,can i move into production,is there any problm wid dat.
    or otehrwise my idea is i can copy this form into someoder name,previous one i can delete ,from this i can copy into my previous name,now it must b ask new request.
    i can use this one in my program also widout changing any thing in my driver program.
    plz giv me some suggestions on this thing.n giv me reply asap.
    regards
    satya

  • How can i create a new transport request?

    Dear Experts,
    Some colleagues have to modify a master record, but save time, failing to produce a request no., then, how can i create a new transport request?
    Wilson

    Hi,
    Please let us know about the issue when you create the new Transport request .
    In which system you are creating the request . Hope its in Development  .
    If so , check the entries are enabled in SCC4 > Changes without automatic recording
    Changes to repository objects and cross client customizing allowed .
    Protection level 0
    If these entries are enabled, you must be able to create Transport requests.
    Please check and update .
    Regards,
    Nibu

  • Creating a new transport request.

    Dear SolMan users,
    Is it necessary to create a new transport request when a tester reject the testing so the developer must make some changes angain or can use the change request already created at the begining of creating changes in the system.
    Thank you
    Petr

    Hi,
    The developer will be creating a Transport Request in Development System.
    The tester will just check the functionlaities in Quality server. What is the use of a Tester creating a Transport Request? Any scenario you can explain?
    Regards,
    Rajesh Kumar

  • Problem in adding function group inlcude in new transport request

    Hi friends,
    This is regarding the issue while moving the function group developed for BAPI object to production.Include having the suffix UXX in main program of function group I am not able to change and then save in new transport request,but the same is possible in R/3 4.7 version.
         Can you please help me out to get it done in ECC 6.0.
    Regards,
    Rajesh Akarte

    Did you try to do: Put cursor on transport number-select include icon-say select freely selected objects-I usually say dev class and can highlight and select the object and save. Please reward points if helpful.
    Message was edited by:
            Tom M.

  • Creation of new transport request

    Dear all,
                 I modified the already existing smartform,when i saved  the changes it saved but it didn't show any transport request.For this situation i need to create one new transport request number  for already existing smartforms,may i know how to create the transport request for already existing SMARTFORM.
    Thanks & Regards
    murugeshrajeev

    Hi,
       Go to Smartforms TCode and there GOTO-> Object directory Entry -> Lock overview and there you will find the Change Request assigned to the smart form. If you want to change the existing change request there are two ways.
    a) Go to TCode se09 and then go to the Change request and there delete the smartform which is existing in the Task. And then go to Smartforms TCode and then change it and save it.
    b) Release the existing request and then create a new request.
    Hope this will help you,
      Regards,
      Venkat.

  • How to assign a new  transport request for  a program saved in $tmp mode

    Hi  all,
    How to assign a new  transport request for  a program saved in $tmp mode?

    Hi,
    delete the object fro the package $tmp.
    go to change mode, save it.
    while saving it will ask for teransport id.
    thanks
    vinod

  • How to Copy Service request Notes to the new Service request

    Dear Experts
    I have to write code for copying the service request's notes filed value to the new service request when User clicks on copy button.
    Fields in the Heard are getting copied when user copies to a new service request. But notes filed are not getting copied.
    Please suggest the available options for coding / configuration to achieve this.
    Regards
    Hanu
    Edited by: Hanu Madhava on Dec 14, 2011 12:05 PM

    Hi,
    The thing is like this....
    i have a released request in which we have more than 1200 objects, in that i dont need 10 objects.
    so when i create it as copy of transport request, i just deleted those 10 objects and saved.
    Now, if i transport the new request how many objects will go? 1200 or 1190?
    in the new request i am getting the old request under Comment: Object List Included.
    is it necessary to transport the old request?
    i need to transport only 1190 objects.
    Regards,
    Satish Reddy.
    Edited by: Sathish Reddy on Jan 28, 2010 2:18 PM

  • How to ceate Transport Request Number for importing transport files

    I'm trying to create Transport Request Number for importing transport files.
    I've copied the two transport files (K903281.QB8 and R903281.QB8) into subdirectories usr/sap/trans/cofiles and usr/sap/trans/data, respectively. Now, I want to import the transport files using transaction management system (STMS). Before using STMS, it seems like I need to create Transport Request Number, but I don't know how to create it. Could you please let me know how to create it?

    Sanjeev and Sajay,
    Thanks for your answer. I was able to import the files successfully as transport number QB8K903281 by using standard STMS transport function after manually adding new transport on STMS. My trouble was from my ingrorance of how to let STMS recognize transoprt number for transport files copied from outside SAP. Again thank you very much.
    Tetsuya

  • Problem in extended Transport control while setting up transport request.

    I created a BDC program which will create a database table upon executing..
    The problem is the program worked well since yesterday, But today when i executed it , it is showing a information message when creating a new transport request .
    Extended transport control is not active:
    Cannot specify target client
    Since it s a recording ,and all the windows are processed using an OK CODE, this info box comes all of a sudden .I dont kno what went wrong , coz it was working fine the previous day.
    i could not create a new workbench request even after ignoring that info message.
    Pl suggest me what could be wrong.

    This message has a long text, please read it.
    Check with your system administrators, if they have changed anything regarding the transport process.
    In addition, instead of using "fragile" recordings, try using function modules like DDIF_TABL_PUT.
    Thomas

  • Can i transport PO Release strategy in a request

    Hi Gurus,
                     I have done po release starategy in dev can i transport the release strategy in a request to quality client or should i do the same setting again in quality server.
    Regards,
    Dheepak

    hI
    1- Release classification is a master data which you can not transport and need to maintain in each client.
    2- Goto Txn -- CL24n in Qly or PRD
    3- Enter release class and class type then enter ,there you will get all your strategies select the strategy you want to maintain and details there you can maintain the values.

  • Request owner approval in Transport Workflow (DEV to QTY)

    Hello,
    I have set up the transport workflow between DEV and QTY systems on ERP6.
    I need to allow developers and consultants to approve their own transport proposals in order to facilitate transport to the QTY system.
    Currently, when an user releases a transport request and creates a transport proposal, the approval message is sent to the TMS Worklist.
    Therefore, only administrators can approve transport proposals.
    How to allow users to approve and import their own requests through the Transport Proposal Inbox in Transport Organizer (SE10) ?
    Thanks in advance.

    Hi Serguei,
    Please check whether you have specified &_WF_INITIATOR& as excluded agent.
    Please remove &_WF_INITIATOR& as excluded agent.
    With Best Regards
    Julia