Hi, I was just wondering if there is a way to correct overages and shortages after a delivery has been received and put away. As we are very new to SAP, during a plant to plant inventory transfer, we made the mistake of confirming eight delivery orders in spite of the the fact that there were several discrepancies such as overages and shortages on several Item #'s. We have documented all the discrepancies and would now like to go into the system to make the adjustments. Is there a simple way to do this? Any help would be appreciated, thanks.

Hi,
One best way to adjust the overage and shortage of materials afterputaway is doing PHYSICAL INVENTORY.You can post the differences according to the overage and shortages of the material. I hope this will clear your issue. Thanking you.

Similar Messages

  • Open Orders (Confirmed and Un-Confirmed)

    Hello BW Gurus,
    I am looking for Standard BCT that can give me True Open Order "quantities" and "Amounts". The extractor 2LIS_11_V_SCL seems to give open order qty for "Confirmed" Schedules only. I am looking to get the "Net Open Orders" based on "Planned Goods Issue Date".
    Any ideas on how to achieve this?
    Thanks in advance.
    Srini

    Hi Lily,
    But these extractors comprises of all orders thus, it means open orders,confirmed and not confirmed, delivered and not delivered, and orders that are already invoiced.
    In my case, we need to have an open orders report meaning confirmed and not confirmed and where invoiced orders, delivered, and etc should not be included at all.
    Any idea?
    Thanks
    Sheila

  • Report  showing list of order confirmations and open/close reservations?

    Hi
    Can we have any standard report having list of  order confirmations and open/close reservations in SAP PM ?
    Regards
    Pooja

    Hi Pooja,
    Try IW12, Display Document flow, if you are looking for a combined report of Order confirmations and Material status.There are various other reports related to order confirmations and Material status seperately. For material status you can use IWBK.
    Better place to post PM questions is in Enterprise Asset management Forum.
    Warm regards,
    Srinivas Potluri

  • Order confirmation and Order changes

    Hello Guru's,
    I am having following issue, please let me know ur inputs on the same how to handle below situation.
    There is Customer Vendor relationship under one system and under one company code.
    Customer orders goods from Vendor and this Vendor supplies goods against this PO. These are nothing but plants in reality.
    1) There is no issue when creating SO against the PO raised..
    2) Once the SO is created how to send sales order confirmation and how to add the confirmation line in PO?
    3) When the sales is changed and changes made at the time of sales order creation wrt to PO from customer: how to send these changes to customer and update his PO also.
    Please let me know if anyone has gone thr' such situation. This should happen via ALE IDOC only.
    Best regards,
    Prasad

    Hi Kris,
    It's ok.. as I knew the process.
    The problem I had, when I change sales order and trigger ORDERS05 and ORDRSP idoc then it shows changes but also it shows all the sales order data.
    The requirement which I have is as below:
    1) If the sales order is changed then send only changed data and update the PO at customer side which is in same system.
    i.e. let us say sales order is created and confirmation also send via ORDERS05 and ORDRSP. Now when SO is changed for quantity and price, then I want to send only these quantity and price changes via idoc and update PO accordingly.
    This also applies for back order processing or supersession, where date or item itself can be changed or added.
    Please come back if knows further.. Awaiting for ur reply.
    I am interested to know what steps I have to follow and even if any routine I need to write to capture these changes.
    Best regards,
    Guru

  • When I upload an app, it asks for my password, then says it's incorrect.  When I reset it (after 3 tries) and put in the new one, it still says it is incorrect.

    When I upload an app, it asks for my password, then says it's incorrect.  When I reset it (after 3 tries) and put in the new one, it still says it is incorrect.  What am I doing wrong?

    I assume that you meant that you reset the password three times. Did you receive any verification that the new password was accepted?
    Sign out of you account, restart the iPad and sign in again. Settings>Store>Apple ID - tap the ID and sign out.
    Restart the iPad by holding down on the sleep button until the red slider appears and then slide to shut off. To power up hold the sleep button until the Apple logo appears and let go of the button.
    Go back to Settings>Store>Sign in again.

  • Guide me config steps for REceive and put away materials

    Hi ,
    I am new this module.
    Please guide me all cofiguration steps for Receive and Put away materials in MM system.
    Thanks,

    HI,
    read sap help and search on Google.or in forum
    [http://help.sap.com/saphelp_46b/helpdata/en/fd/45b7ee9d6411d189b60000e829fbbd/frameset.htm]
    Regards
    Kailas Ugale

  • Userexit for Qty Changing after TO Confirmation and before PGI

    Hi Experts,
    I am seeking help for a scenario as below.
    1. The delivery has a situation where after the Transfer order is confirmed and before the PGI is done, I have to put a check of Qty for non-stock items (they are not relevant for Transfer order) based on the confirmed Qty of the normal items.
    I want to find the proper user-exit / form for the same.
    Currently I am thinking about using Program MV50AFZ1 ( FORM userexit_save_document) assuming that this will be called when we click the PGI button.
    Please suggest if this is the correct place or is there a better user-exit for usage.

    Try with USEREXIT_SAVE_DOC_BEFORE_PREP in program MV50AFZ1 which is called before the deliveries are saved
    G. Lakshmipathi

  • Order confirmation and email confirmation not have same information?!?

    I just place an order online, I don't know why the order confirmation email does not have the same information as the original order confirmation.  
    After I hit the button to place the order, the order confirmation page clearly showed:
    -  the installation appt on July 23, 2015 8:00 AM - 9:00 AM in green color
    -  the order summary include "$350 Visa prepaid card" in green color
    -  the estimate bill is 154.92
    But in the email confirmation, it provided  total different thing:
    - no where on the email order confirmation  said about $350 Visa prepaid card.
    - the installation appt somehow change to July 28, 2015 8:00AM - 5:00 PM (<- move to 5 days later with an 8 hours window to expect people to take whole day off  from work to get installation?)
    - the estimate bill become 241.22 (<- move up 86.3)
    Does the email confirmation have the wrong information or Is it normal that Verizon automatically make change to the order after it submitted? Bill increase, date install change and no more prepaid card?

    Note the bill estimate on the email may have certain extra charges, hopefully all correct.  You will need to check when you get actual bill.  Things like install fee (if not waived) and partial month charges.  I don't remember if other taxes and fees are also included on one but not the other. YOU ARE NOT TALKING TO VERIZON ON THESE FORUMES.  The forums are mostly peer to peer.

  • Order confirmation and scrap gene in SL

    In Production Process - Two type sof scrap generate
    1. planned - which is maintained in BOm and update with 531 mvt type
    2. Unplanned - which is booked in scrap field while doing Confirmation. Suppose my Order material Y broke on the way/while doing maching etc , it is booked in the field Scrap while doing confirmation. ( No where found in Inventory)
    here case 2 , that scrap mat F(physically happned during prod process) is also sold . So an alternative method mentioned was with 501 will update scrap material F and ref made as Prd Order Number(order mat Y).
    It is fine , some how it meets the business req.BUt now they want with ref to confirmation But confrimation field is not avilable in Display screen for 501.
    I know 501 is not for this , but for the business [purpose it was mapped like this .
    551 will update o cost centre and not in INV
    So kindly help me to upload the scrap with 501 with Production confirmation and not with Production Order

    Dear,
         Raise Dummy production order i.e with out material in CO07 T-code, put total qty as 1,if u want to settle the order put settlement rule if not simply come back and go to Component over view and put Material (Srap Material ) and give required qty in minus sign
    EX:-10qty. put item categery as L
    save the order and do conformation in co11n the stock will build in inventary
    Regards
    Ravi

  • Need help on sales order confirmation out put type

    Hi Team,
       Please help on this issue.
    In our sales document types order confirmation is happening through the inboud idoc, user requrement is once order is confirmed immediately sales order confirmation output type should send sucessfully, but the problem is
    Inbound idoc is using the sales order and blocking at the same time RSNAST program is using this sales order for sending the output type but not able to send due to the sales order is blocked by inbound idoc.
    Could you some body help me on this how can we proceed on this.
    thanks & Regards,
    MK.

    Check the Dispatch time of the Output type in transaction code :NACE.  You need not execute RSNAST00, if the despatch time is set to 3 ( Send with application own transaction ) or 4 (Send Immediately).  The output will trigger automatically after the sales order is saved.

  • Process Order Confirmation and Pallet

    Hi,
    Would appreciate if you can pitch in to get information on below requirement.
    Say for eg., for the 1000 CA of header quantity in a BOM, one (1) Pallet (PAL) is required and assume the pallet's are back flushed.
    - if you confirm 1000 CA, then SAP post 1 Pallet
    - if you confirm partial pallet, like 800 CA - then SAP posts 1 Pallet
    - but, if you confirm partial pallet, like 400 CA - then SAP posts 0 Pallet,
    I believe that's the nature of SAP design in rounding up / down. However in this unique circumstance of a Pallet, everyone would always like to Round up rather than round down.. so, in the example above confirm 400 CA should also post 1 Pallet.
    I couldn't find a solution in SAP with it, and I guess a user-exit might help to round up, but not sure which user-exit at process order confirmation will help.
    Any pointers would be a great helpu2026
    Thanks in advance,
    Nitin

    Is HU enabled for your location? if that case, you could post by pallet.

  • After Syncing Content and Putting ATV on standby - No Content is there

    I Synced all of my TV shows to ATV last night and put ATV on standby before going to bed. When waking up this morning and turning ATV on I noticed there were zero TV shows and ATV said that I needed to open my ITunes -- Once you sync content, isn't it saved on the ATV harddrive?
    Please help. Thanks.

    If you are syncing then yes the data should be on the hard-drive. If just streaming then need ATV open.
    Also ensure what settings you have for TV syncing. If for example you have it set to 5 most recent unwatched shows but you had watched them in the past, then they won't sync and require iTunes open to list to stream.

  • BAPI for Purchase Order Confirmation and update EKES table

    Hi all,
    I have a requirement to update the PO confirmation soon after successful creation of PO in an IDOC.
    I have used BAPI_PO_CHANGE function module which didnt serve the purpose as it cannot update confirmations.
    I tried using ME_CONFIRMATION_UPDATE where I was able to add a confirmation entry in EKES table but that is not being reflected in ME23N transaction when I display the PO.
    Please help me out on this.
    Thanks & Regards
    Pavan

    NB: Never use a standard update FM (check attributes of ME_CONFIRMATION_UPDATE) its often only a SQL statement collector without any check, logging of changes or database consistency, if you perform a where-used you should find it is never called alone but with a bunch of other update FM after checks and other update preparation.
    Get back to the BAPI and table parameter POCONFIRMATION, also use BAPI_PO_GETDETAIL1 to get current data for the call of BAPI_PO_CHANGE.
    Regards,
    Raymond
    PS: If it is not in 197958 - BAPIs for purchase orders: Missing functions, you should be able to do it

  • Process steps of Production oder after Order confirmation

    Please provide me the ideal Processes in Discrete after GR
    ie)
    1) Create Pro oder through MRP or Man
    2) Release
    3) Print
    4) GI against Pro Or
    5) Order Confir
    6) Goods Receipt
    After the 6th step, whether to do TECO or Close, Settlement,Mark dele indi ,etc,.. please provide some detail

    Hi,
    We can CLSD the Order without TECO.
    But after CLSD, there will not be any posting and settlement possible.
    If your product is fully delivered then, in my view TECO is not required.
    If you have not completed your Prod. Order then puting TECO you can consider your part Production during settlement.
    For your information, after TECO also, you can load the costs on the Order.
    That's the reason for all the orders generally put TECO, settle, then Close (CLSD).
    Regards,
    Siva

  • Inspection Lot display after Order confirmation

    Hi All,
    My requirement is to display Inspection Lot no under assignment tab in display prod. order after GR.
    How to get Inspection Lot no?
    what are the settings to be done?
    Rgds,
    Yogesh

    Hi
    The Inspection lot no will be displayed in Prod order only if insp type 03 (In Process Inspection) activated in QM view of Material Master for a material when the prod order is released.
    For Insp type 04 (GR after Production) we can see the insp lot in QA32. It can not be displayed in Prod order.
    Regards
    Brahmaji

Maybe you are looking for

  • BT HH5 online connection issue (NAT)

    Hi, I found out that I was getting a moderate NAT type on my PS3 (NAT type 2) which didn't let me play GTA online at all. A friend of mine also had the same problem and he has HH5 aswell. I've tried to port forward my ps3 and GTA online and it would

  • GT784WNV not working in Bridge Mode! Fed up with lack of Customer Service

    I don't even know where to start but I am this close to just cancelling Verizon and switching to cable internet.  If you want to skip the rant, jump down a paragraph. I recently moved from a house a few miles away in which I had a solid DSL connectio

  • Safari Crashes and then will not open yahoo.mail or gmail

    Safari Crashes and then will not open yahoo.mail or gmaill Is anyone else having these, or similar problems. i cannot log-in to my yahoo.com or onto gmail. The issue started yesterday. The message states that it cannot secure the connection. Any sugg

  • Programs have trouble with retina display?

    I'm about to buy a MBP 15" with retina. So far I have read some posts about incorrectly displaying programs like PS elements and CS6 programs. Does Lightroom 5 also have this problem? I'm mainly buying the laptop for my photography hobby.

  • AP crashed on exit

    I turned the preference for Photo share on but was not connected tomy referenced images so I exited AP.  Imight of looked at a couple of other projects but Ap wasnt opnen for more than ten minutes.  My parcial crash reportis as follows   Thanks for a