Cost center and floc link

Hiiiiiii Experts,
I have a query.there is one floc and below that equipments attached to it.There are some electrical eqp and some are mech.We have already cost centers created for mech and elec seperatly.Now if i assign respective cost center to elc and mech eqp, it will work for eqp.But cost center will be assigne to floc.Do i need to create a new cost center for that.Or should i leave it blank.If i wont give any cost center to floc then will the accumalated cost of all eqp below it will be summerized at floc level.
One more thing what sap best practice suugest.Shpuld we assign cost center at floc level or eqp level.
Can u help me out to make the cost center allocation clear in sap pm.
Regards
Brijesh

Hello Brijesh,
There is no issues if you leave blank the Cost center field blank, all the report will work fine and also the cost will be displayed at the below hierarchy.
The problem will arrive when you will create any Order over this function location. At that time you will have to create settlement rule manually.
Regards
Naveen

Similar Messages

  • Link for Cost Center And Work Center.

    Dear Experts,
    Can you Provide me the Link for Cost Center And Work Center.
    Regads,
    Jyoshna

    Dear Experts,
    I got the answer for the Link Between Cost Center And Work Center.
    By using CR03   T Code we can see the Display Work Center : Cost Center Assignment Screen will appear.
    we need to select the costing tab, We can find Cost Center .
    Thanks & Regards
    Jyoshna

  • Cost center and profit center linked to GL account

    Hi All
    I am obtaining the carry forward balance for the fiscal year from the table
    GLT0 but I also need the cost center and profit center details for the GL account,
    which I am unable to get from either GLT0 or GLTPC or GLT1 tables.
    Is there any other way out. Please suggest!
    Regards
    Ankit

    Hi,
    Hope OKB9-Account Assignment will resolve this issue.
    There you have the assignments.
    Regards
    A
    Assign points if useful

  • Cost center and Cost element.

    Hi all,
    I am in an urgent need to understand the relation between cost center and cost element. Please provide me with their individual information as well as the link they share. An existing relationship table between the two, if any, ...then plz mention.
    Thanks & Regards,
    Naresh

    Cost Element: cost element is an individual which carry cost like salaries, wages, power expenses, etc.. These Cost Elements are Two types
    1. Primary Cost Element
    2. Secondary Cost Elements
    Primary Cost Element will carry cost form FI to CO (Cost Centers, Internal Orders, Cost Objects, etc…)
    Seconday Cost Elements carry cost with in CO to different Cost Centers, Internal Orders, Cost Objects, etc…
    Cost Center: Cost Center is an individual which contain collection of costs. For example “Admin is a cost center, it contain costs like Salaries, Power, Rent, Stationary etc,
    With this following report you can retrieve  cost elements given a cost center “controlling – cost center accounting – information systems – reports for cost center accounting – plan/actual comparisons  ”
    Thank you

  • CO, which table decribes "cost center" and "cost center group"?

    Hello experts,
    now I have the transaction KP06. Maybe through customizing the user has built a "cost center group" for some "cost center".
    In which table can I find out the relationship between the "cost center" and "cost center group" ?
    Thanks.
    RD
    Edited by: Marching Dai on Jun 16, 2008 2:05 PM

    Hi Arun,
    Please check this link
    http://www.erpgenie.com/abap/tables_fi.htm
    Please check CKPE --->CO-PC Cost Object Hierarchy: Individual Objects
    CSKA Cost Elements (Data Dependent on Chart of Accounts)
    CSKB Cost Elements (Data Dependent on Controlling Area)
    CSKR Resource master record
    CSKS Cost Center Master Data
    Best regards,

  • Cost Center and G/L Account not defaulting

    Hi Experts,
    We are on SRM 7/ECC6
    I am creating a free text SC...I give the product category and expect that cost center and G/L account will default in the account assignments tab, but they don't and I have to manually plug in these values. I have maintained appropriate SPRO settings where I have linked my product category and G/L account and also marked the default checkbox.
    Kindly suggest,
    Best Regards,
    John

    Hello John,
    In SPRO configuration
    "Define G/L Account for Product Category and Account Assignment Category"
    Maintain the configuration like
    Category ID    Source Syst.    AcctAssCat       G/L Account    Default
    0000030         TRXCLNT750    CC                      15190001         x
    Don't forget to maintain Source System and Default fields for this setting.
    Regards
    Thiago Salvador

  • Display descriptions of cost center and G/L account in ME51N/ME52N/ME53N

    Hi Experts,
    Can any one suggest that how to display descriptions of cost center and G/L account in account assignment subscreen- ME51N / ME52N / ME53N.
    Thanks in Advance...
    Siva

    hi
    if the field is required then u have to enter them manually
    so if this are not required then goto OKB9 here give the default cost center for the Gl acct

  • Report Painter Request - Cost Center and WBS Element

    Hi Everyone,
    Currently, my company settles all project related expenses through to a cost center by way of an internal settlement cost element (category 21).  The issue with this is that when the expense gets to the cost center, they lose all visability as to where the expense originated, such as salaries or travel expense (category 1 cost elements).  We can't switch the settlements to the originating cost element from wbs to cost center just because of the additional data/volume that will cause.  My thought was to create a report painter that can run by cost center but also show the wbs's that settle to that cost center and group the expenses by primary cost element (cat 1).  I'm assuming that there is a way to marry a cost center and wbs element by way of the wbs settlement rule but how would that be done for reporting purposes?  I've seen it done before by way of a nightly job that created sets based on the combination of cost center and wbs but I'm not sure how that was done.  Any advise and examples?
    Example:
    Cost Center:  IT
    WBS: A.0017.01.01 (settles to cost center IT)
    Postings made:
    1.  CC IT and CE 552000 "salaries"..............................$20,000
    2.  WBS A.0017.01.01 and CE 552000 "salaries"........... $5,000
    3.  Settlement of WBS to CC (expenses flow through to CC IT by way of CE 985000)
    I want to run CC IT and see that the account 552000 really shows $25,000 and can be broken down by cost object (CC and WBS by the amounts above)
    Thanks,
    Pete

    Hi Peter,
    I had a similar requirement and used report painter report group 1SHK-002 (in library 1VK).
    I took a copy of the standard and ameneded it slightly, I switched the explode so it occured on the cost center not cost element.
    The report runs so that direct costs on the cost center are shown at primary cost level. And values settled to the cost center are shown on the partner object. In your case i guess WBS Elements (Partner ObjType WBS).
    Now in my case I didnt need cost element breakdown on partner level, just on cost center so effectively I have(sorry for text alignment but I hope you get the idea):
    GL1   .............  100
    GL2   .............  250
    + Cost center1 total ....350
    GL3 .............   50
    GL4 ............. 100
    + Cost center2 total.... 150
    Primary Cost Total ..... 500
    X-YZ-1.200 .............   50
    X-YZ-1.400 ............. 100
    + WBS total ............. 150
    IO 1............. 100
    IO 2  ............. 100
    +IO total  ............. 200
    Partner Total............. 350
    Overall total .............  850.
    Its not exactly like your requirement but it might be a good report for you to work with to get what you need.
    Elaine

  • How to get the cost center and division for a given FI vendor document...

    Hello Experts,
    I am currently developing a report wherein I have to show the cost center and division used in the given FI document.
    These documents are vendor related transactions.
    In the file that was given to me by the user, she indicated the cost centers used by the FI documents
    but when I view it via VA03 I cannot theere are no cost centers used in all the line items.So are there
    any FM, BAPIs and/or tables that I can use for my requirement?
    Hope you can help me guys. Thank you and take care!

    Hi
    I am not sure on the requirement. You are developing a FI report and accessing VA03 which is sales transaction. Anyway for getting cost center you can go to table VBAK,VBAP for line items.
    Hope solves ur problem
    Thiru

  • KO88 - Error when settling for Cost Center AND Auc for the same Internal Or

    Hi Experts,
    We need to configure Investment Internal Orders that could settle to both Cost Center and Auc, but each assignments with different Source Cost Elements
    We did the following:
    1. Created Auc Class
    2. Created Investment Profile "IMOBIL" and assigned to Auc Class, flagging Auc
    3. Created Allocation Structure "CV" with two assignments:
    01, Source = Cost elements 7000000000 to 7999999999, receiver AUC "by cost element"
    02 Source = Cost elements 4000000000 to 4999999999, receiver CTR "by cost element"
    4. Created Model Order, filling the Investment Profile IMOBIL created in step 2.
    5 Created Settlement Profile ZCV0001, assigning Allocation Strucutre CV, allowing CTR and AUC for receivers, default receiver is "FXA", doc type "AA".
    6 Created ORder Type CV01, assigning Settlement Profile ZCV0001.
    When I post only for Asset Expenses (Source Cost element 7, Assigment 01), the settlement through KO88 correctly settles to AUC, and also creates the settlement rule for cost center (i'm using the strategy to create from Responsible Cost Center).
    But when I post for Asset Expenses (cost elements 7, receiver AUC) AND General Expenses (Source Cost element 4, receiver CTR), KO88 generates an error KD506, saying that for Assigment 02 - AUC I didnt define a settlement cost element.
    1. Assignment 02 is not AUC, is CTR;
    2. I flagged "by cost element", so I don't need a settlement cost element. And also, I was able to post to AUC when the source posting was only for cost element 7.
    Did you face any problem like this?
    I cannot find out what is the missing configuration, or if it is a program error...
    Kind Regards
    Mayumi Blak

    Hi Ajay
    I already created Source Structure and assigned to my Setllement profile (so I assigned Allocation Structure AND Source Structure).
    I don't understand when you say that I need to assign the Source Sutrcture in each rule....because the Source structure is in the Settlement Parameters valid for both rules...
    When I post to Asset Expenses only for the internal Order, the 2 rules (CTR and AUC) are created when I run KO88 (but only AUC rule is settled). This is OK.
    The problem is when I post for both General Expenses AND Asset Expenses, the system is not recognizing that I have 2 source structures, neither is findind that for CTR AND AUC the Settlement cost elements are the original cost elements.
    I'm thinking about changing message KD506 to warning, do you know if this can help?
    Kind Regards
    Mayumi Blak

  • How to write a validaton rule for Cost Center and plant in PO

    Hi,
    I need to write a Validation Rule for Cost center and Plant in Purchase Order to get the error message if the Plant and cost center combination didnot match.
    But i am not sure in which transaction code do we need to write this validation. Kindly help me by giving T.Code or path to do validation at PO level.
    Thanks
    Sunil

    >
    Sunil Pal Raj wrote:
    > Hi,
    >
    > I need to write a Validation Rule for Cost center and Plant in Purchase Order to get the error message if the Plant and cost center combination didnot match.
    >
    > But i am not sure in which transaction code do we need to write this validation. Kindly help me by giving T.Code or path to do validation at PO level.
    >
    > Thanks
    > Sunil
    Check OKC7
    Regards,
    Indranil

  • PM Order Confirmation using Personnel's Cost Center and Activity Type

    Hi All,
    Is it possible to have PM Order confirmation (IW41) using Cost Center and Activity type from Personnel instead of default from Work Center?  If it is, can it be done with some configuration or user exit?  Please advise.  Thank you.
    Dai

    Hi friend,
    Order confirmation will be done for order operations.While doing confirmation we post the actual work done by the repective work center and respective activity type assigned to the same workcenter.
    But these activity types are assigned to cost center for cost calculation.confirming the respective operation in maintenance order through workcenters gives the report of planned work and actual work done by the respective workcenter.
    We cannot confirm the operation using costcenter and activity type directly through transaction IW41.
    If you want to develop new confirmation screen and making confirmation of the respective order operation with only costcenter and activity type fields, you can do it .
    Regards,
    Pardhreddyc
    Edited by: Pardhreddyc on May 17, 2011 12:45 PM

  • Cost center and plant in asset master creation compulsory entry config

    where we configure that cost center and plant entry is complusory while creation of asset master.
    is it   asset accounting
                   master data
                           Define screen layout for asset master
                                     Define Screen Layout for Asset Master Data
    as in our system in config    cost center and plant is optional        but while creation of asset master it becomes compulsory field

    Hi,
    Yes, it's defined in the layouts for assets master data.
    Regards,
    Eli

  • COPA derivation for thecombination of Cost center and Cost element/GL accou

    Hi Gurus,
    In COPA derivation using KEDR i am trying to make a derivation for the
    combination of Cost center and Cost element. Here i got following problems
    • While posting FI document using t.code FB50 system not automatically
    updating the fields Cost center and cost element in Profitability
    segment. Hence system not posting COPA document. How can i make this
    derivation? Is there any note should i apply regarding these.
    • How can i create cost element as characteristic.
    • If i configure derivation for the combination of Cost center and cost
    element will it be posted with copa document for postings or automatic
    postings from MM,HR and FI
    Pls provide me solution at the earliest.
    Thanks and Best regards,
    Dhanumjaya.Ranga
    Mobile: - 919940093579
    Mail : [email protected]

    Hi Murali
    Thanks for update
    I explain my req clearly
    For me segment is Distribution channel field (EXPORT and DOMESTIC)
    If GL account is 1000-2000     always                      Export
    If GL account is 2001-3000    and Cost center is     X then Export.
    If GL account is 2001-3000    and Cost center is     Y then Domestic.
    Based on above REQ i am making derivation using KEDR T.code.
    These postings should work for all modules postings such as MM, HR also.
    Actually this should work automatically and after saving the transaction we should have copa document also.
    But problem is in source fields of derivation we have GL account (HKONT) and Cost element (KSTAR). I am making derivation using either of these.
    But after posting document system not giving COPA document.
    I found the reason is  at GL postings we are giving input to GL account (HKONT) but we took in KEDR source field as GL account (SAKNR). GL account (HKONT) is not updating GL account (SAKNR) field in PSEG screen in Fb50. Even i try with cost element (KSTAR), GL account (HKONT) is not updating this in PSEG screen in fb50.
    If GL account (HKONT) updates either GL account (SAKNR) or cost element (KSTAR) at the time of posting FB50
    Or
    If we have the field GL account (HKONT) as source field in KEDR i hope my problem
    Get solved.
    If you want further info pls give me your mobile number then i ll call you

  • Cost Center and GL account in Sales Order / Delivery

    I have a requirement where we want user to specify what cost center and GL account should be used while posting goods issue.
    Currently GL account and Cost Center is automatically determined based on OBYC configuration.
    Is there a way  user can populate Cost center and GL account at Sales order or Delivery document level and what ever they have specified will be used for Posting Goods Issue.
    If user doesnt specify anything then standard OBYC determination should take place.
    I looked at OVF3 transaction which can default cost center (though no GL account) but its not useful in our requirement.
    I also looked at OKB9 transaction but not sure if we can use it either.
    Again we want user to enter Cost center and GL account at either SO or Delivery document level and then that should be used for Post goods issue.
    Thanks in advance.

    Hi,
    In delivery under tab GOODS MOVEMENT DATA
    After valuation type column COST CENTER & G/L Account column available
    Now with the help of FI consultant make it change mode so user can maintain  also I observe that if delivery created without reference to order then that fields are in change mode means user cn maintain data for this but if with reference to order it is disable mode
    Check in t-code OMJJ FIELD SELECTION FOR MOVEMENT TYPE
    Put movement 601
    Then select movement type and double click on filed selection (from 201)
    Then go to additional account assignment and for cost centre make it optional or requirement
    or Else under field selection enjoy for movement type 602 indsert field KONT0 and KOSTL and check
    If this can not work there is option field selection for G/L account check that with FI
    Kapil

Maybe you are looking for

  • [Sol 10 11/06 SPARC on Sun Blade 2500] Could not determine boot disk?

    dear all, I have a problem during installation of Solaris 10 11/06 Sparc on Sun Blade 2500. After I choosing "Initial Install" at "Select Upgrade or Initial Install" stage, appears the following error message : "Note : Default install is not possible

  • ITunes lost all the names of my audio files

    I can appreciate that there are some people who need to have organisation forced upon them because they are incapable or too lazy to do it for themselves. I personally hate apps which take control of my computer or file system and put things where I

  • How to use my Declarative Component in query component ???

    Hi everybody, I want to change inputDate in query component to my declarative component for Date fields. I did not find any way except implementing the Model of Query component so read "Web User Interface Developer’s Guide for Oracle Application Deve

  • Searching for movies in Cover view mode.

    In the prior version of iTunes when in album/artwork view for Movies, I could type a few letters of the title and it would seek out and find it.  In the new version that does not work.  Any suggestions?

  • Performance Appraisal-Move the document from Part Appraiser to Appraiser

    Hello After the 2nd level manager (part appraiser) has rejected the document, it should be sent back to the 1st level manager review the notes and make changes before resending it back to the 2nd level manager. When the second level manager receives