Cost center is not updating in IT 0001

Dear Mates,
I've uploaded two sets of data using PP02 T-code where one is Historical data & the other is Current data. Here for Current data I'm facing a Issue  where Cost center & org unit's data aren't getting updated in IT 0001 & its still showing the Historical data in IT0001. This is even spoiling the show & frustrating, where users are unable to do CATS Reconciliation also. for more clarification kindly find below screenshots.
PO13
We have maintained historical data in system where one cost center is assigned from 01.01.2013 to 31.03.2014 & second cost center is assigned from 01.04.2014 to 31.12.9999 with current period, not only cost center's but also Org unit's are also not updating in the system. I've even tried with RHINTE00,10,20 & 30 program's but still I'm unable to get the desired results.
Historical data from 12.11.2013 to 31.03.2014 in IT0001
Current record 01.04.2014 to 31.12.9999 in IT0001
Kindly let me know how to update IT0001.Is there any std program available to update the data apart from RHINTE**???
Ur's
Mohan

Dear Mohan,
Try assigning your cost center to position it will default both your org unit and cost center.
Cheers!

Similar Messages

  • Plant and Cost Center are not displaying in FI doc. for asset scrap ABAVN.

    Hi All,
    When we do asset retirement by Scraping using Transaction Code ABAVN, Plant and Cost center are not appearing in the FI document. But, in the master data the Plant and Cost center are assigned for the particular Asset. 
    When I see the FI document display, the fields Cost Center and Plant are blank.  Business Area and Profit Center fields are getting updated.
    Can any one help me how to get this Plant and Cost Center in the posted document.  Is there any OSS notes for this.  I am using ECC 6.0 version.
    Thanks in advance for your help.
    Regards,
    Rajesh

    Rajesh
    Aditional on me answer.
    The systemtakes not the cost center from the asset you have to assign it in OKB9 or to fill in during this posting:
    Steps
    Click on Simulate, than you see the posting screen:
    Click on the line (pk 40)
    Click on Goto and Additional account assignment and fill in the cost center whatu2019s in the master record of the asset and post
    An other option is to make a substitution to get this information

  • RE: Cost centre is not updating in FAGLFLEXT table

    Dear experts,
    During posting we give PSG and cost centre but cost centre is not updating in GL total table FAGLFLEXT as its statistical, in order to be able to update CC in the GL total table what we should activate?
    please advice.
    Regards,
    Chandu.

    Hi Chandu.
    Sadly, this is the standard behavior of the system. In FAGLFLEXT only arrive real cost object, not statistical. This is explained in oss
    964686 - Transfer of statistical postings in CO to FI
    If you really nead the Cost Center, you can enhace table FAGL and and create Z field for statistical cost center. This is a common solution.
    Arturo.

  • PO created successfully using BAPI. But G/L, Cost Center are not displaying

    Hi,
    I am trying to create a purchase Order type limit order using BAPI_PO_CREATE1. PO created successfully. when I try to see the PO using ME23N transaction,in  the account assignment tab G/L and cost center are blank. In my BAPI, I am populating all the values in item and account internal tables.
    I am debugging all the time and not able to find why G/L and Cost center are not poplulating in PO.
    Pls suggest me how to finish this problem.
    Thankm,
    Ram

    Hi,
    Are you passing the update flag in POACCOUNTX table?
    regards,
    Ankur Parab

  • Cost Center does not exist for a particular period - Solution

    We have encountered an error in the subject,
    COST CENTER does not exist for a particular period
    Solution:
    1) Either extend the Posting period for the invoicing  date
    2) Or enter the Cost Center as PO number in Sales Order
    Please do add your comments if there are different ways to solve this error

    The Post contains a solution

  • Getting Cost Center Does not exist error when executing BAPI_ACC_GL_POSTING

    Hi Champs,
    I am getting Cost Center Does not exist error when executing BAPI_ACC_GL_POSTING_CHECK.
    But when I checked for the particular Cost center, it is mapped to the same company code the program has got executed.
    Example:
    Cost center 1000/150402 does not exist on 17.11.2009.
    Cost center 1000/150402 does not exist
    Cost center 1000/150402 does not exist on 17.11.2009.
    Cost center 1000/150402 does not exist on 17.11.2009.
    Please let me know if you have any guess on this. It is very critical issue for me.
    Thanks for all your help in advance.
    With Best Regards,
    Ravi kanth Yechuri

    Use 0000150402 not 150402 .
    Rob

  • Costs in Cost Center are not zero after Revaluation at Actual Prices

    I executed:
    1. KSS2 - Splitting  (I use a Cost Center ABC and all Cost Elements in the configuration)
    2. KSII - Price Calculation
    3. CON2 - Collective Processing
    4. I see the report KSB1 of the Cost Center ABC, but Costs are not zero after revaluation.  For example
    Cost Element 61:                        $   1000
    Cost Element 62:                        $   2000
    Activity Allocation  98:               $ -2800
    Revaluation at actual price 98:  $ -100
    TOTAL:                                      $ 100
    Total must be $ 0.00
    We work with thousands of product orders in a month.  Is it possible that the problem was for rounding?
    Thanks in advance for your help.
    José Luis

    Hi Ajay,
    I checked OKEQ configuration, it's equal that you mentioned.
    I have seen that Revaluation registers are using other Exchange Rate.  In OB08 Exchange Rate P is 2.80 ( 1 USD --> 2.80 PEN)
    How ever those revaluation registers are using ERate of 2.14 (1 USD --> 2.14 PEN)
    Why revaluation registers use other Exchange Rate?  Is this the problem that Cost Center is not zero?
    Thanks in advance for your help.
    José Luis

  • Cost Center does not match with the profit center

    Hi Gurus,
    Can you resolve my issue?
    "Cost center does not match the respective profit center of the sales document for freight revenue - Doc Type: RV ( Billing Doc Transfer) Normal Document"
    I request you to all, kindly solve my issue.
    Thanks with Regards,
    Bala

    It appears that you have assigned a cost center to freight cost element and the profit center assigned to the cost center is different from the one derived by the document. As result this message.
    Check the derivation rule for profit center
    Regards
    Rakesh Pawaskar

  • Manual Reposting of Costs (KB11N) does not update Profit Center

    When I do Manual Reposting of Costs on KB11N, the system does not update the Profit center with the value but it does update the Cost center.
    Please Help
    Thanks,
    Sindane

    Hi,
    Please check whether sender as well as receiver cost object is assigned to profit center. If this is done PCA document gets generated and update is made in respective Profit center.
    Bye,
    Ramesh

  • Cost center field not getting updated to the second level dso

    Hi Experts,
    Data is going from one DSO to other high level DSO where in the source DSO there is cost center filled for a Purchase order but it is not in the target DSO. Target DSO fetches data from 5 DSO's and this is one of them.
    Please suggest.
    Thanks
    Sudha

    Hi Sudha,
    As you say that the load from source DSO to Target DSO is the final load, so question of overwrite does not come into picture.The only point which I feel is that the data might be getting resticted somewhere...
    Is there any routine in the transformation for that field available which will be restricting the load from the source DSO to the target DSO. Is there any start routine available..Please check all these things...
    Hope it Helps,
    Thanks,
    Amit Kr.

  • Profit center wise not updated

    Dear Sapguys,
    In production transaction data its not updated with profit center and business area now i want updated, please guide me Hpw to update
    Regards
    Hanuman

    Are you posting to cost centers and business areas while posting your transactions. In field status group make cost center and business area as mandatory fields. simulate your transactions and post it. Check the respective accounting documents in fb03 with document number. let me know if you want detailed explanation. I can help you.

  • Sender Cost Center may not be the same as Receiver Cost Center

    Hello every body
    I am trying to create a report that shows the hours that an employee has spend on an activity in a project.
    Key Figure:
    Hours
    Characteristics:
    Sender Cost Center (Employees Cost Center)
    Receiver Cost Center
    Activity code
    What happens is that in some cases the Sender- and Receiver Cost Center do have the same value (are the same) in a row. The task in front of me is to exclude these rows from the query result.
    One way to resolve the problem is to make a variable for each object; use replacement path and bring the values of their key into query as keyFigures; subtract one from the other, and use a condition that only allows values different from 0.
    The problem is that the key value of the Cost Centers are not always numeric values (e.g. M10110). These values can not be a part of a subtraction.
    I can resolve this issue by deleting the data in the cube and make a key Figure in update rules with values 0 (sdr. and rec. have different keys) and 1 (sdr. and rec. have same keys).
    Does any one knows of a way to accomplish the result I need in BEx, so I can avoid deleting every thing in the cube?
    Best regards
    /FZA
    Message was edited by: Fariborz Zangoui

    Hello Roberto
    Thank you very much for your help.
    Some times it is difficult to search the forum if you do not know what you are looking for (in this case 'virtual key figure').
    Best regards
    /FZA

  • R/3 Cost center hierarchy not shown in BW

    Hi,
    we have an issue regarding the transfer of a certain cost center hierarchy into the standard info object 0COSTCENTER. We have several hierarchies in place in the R/3 system and we transfer each of them daily via info packages into BW.  When you look into the info package you can press button "Hierarchies from OLTP" and afterwards you can choose via radio button the dedicated hierarchy to transfer for this specific IP. Since last night one of the hierarchies is "disappeared" it's not shown any longer in the list (and therefore the IP crashed) and pushing the refresh button doesn't help. I am very surprised as this is not a new hierarchy (I just know that it has been changed in R/3 yesterday). What I have seen so far is that there is another hierarchy with a different technical name but with the same description. I know this shouldn't be a problem... Anyway, any hint is appreciated.
    Regards,
    Oliver.

    Update:
    The issue has been resolved. I learned that only top nodes of cost center hierarchies can be selected on the BW side to be transferred (A top node is a group that is not present in any other group as a sub-group.). The hierarchy in scope of the transfer has been removed form any other hierarchy in R/3 and now it works.

  • Profit Center  is not updating in Vendor line item

    Hi Experts,
    For my GL postings in F-43, F-41, F-53 ,F-54 and F-28 the 1st line item corressponds to Vendor or Customer, the profit center is not updaitng the values and shows nill. We have given check in Exit and Substitution but its not updating in BSEG structure as its functioning like loop.
    Pls advise, how to resolve it.
    thanks & reagrds
    sankar.

    Hi Bharathi,
    thanks for your prompt reply.
    But as per my Client requirement, we need to pass the profit center values to the vendor/customer line items also.In such case, what' s the solution?
    Pls advise.
    regards
    Sankar/Brahma

  • Error~ PR G/l Account & cost center is not appearing in PO while copying

    Dear All,
    I am converting PR into PO, while creating PR I  have assigned account assignment cat as "K"(cost center ), so i assigned Cost center and G/L account , After this I tried to convert this into PO, but in PO again it is asking for G/L account & cost center  onemore time,Earlier it wasn't .
    May be some where the setting got changed but I am unable to find where exactly this setting got changed.
    Please anyone could help in this.
    Regards,
    Nagaraj S

    well thats really wiered
    can u do one thing in your quality system create one PO and pleas but  make sure the data in the po sholud be same as that of PR but this PO will be created without the reference of PR
    i want to check if system is able to find the G/L account automatically which ideally it should find
    in case the g/l is not picked automatically then in that case check the valuation class in material master and the g/l which is maintained in gbb or not and make sure the g/l is a cost element
    if the g/l comes automatically then check the PO document type settings in the those 2 folder at the left poriton of screen in IMG>>olme>>POdefine document type