Cost Center & WBSE

Dear All,
I have requirement for one project as follows:
I have created one project & planning costs in WBSE/Network,
posting the costs via GR / GI.
These costs are shown on WBSE (Report: S_ALR_87013532).
I want to see these costs on Cost Centers also.
But it is not showing cost on cost center.
What do I need to do?
Sanjay

Dear Sanjay
This can be handled by customizing the account assigment category "P" or what ever used in the PR/PO/GR/GI mandatorly asks for Cost Center also. Then the costs will flow to the cost center also. But this will be real posting and again needs to be settled or else make the WBSE/NWE as statistical.
SPRO > IMG > PS > Material > Control of sales order related production > Check account assignment categories. make cost center mandatory.
Award points if useful
Thanks
Murali

Similar Messages

  • Settlement to cost center posted for statistical WBS element

    We have the following scenario
    Statistical WBS elements with assigned Cost center posted for actual postings
    Network assigned to statistical WBSE and settlement rule on the same WBSE
    On settlement run CJ88  the network costs are transferred from network to Cost Center posted in the WBSE.
    Issue:
    While analysing the active availability control the assigned value is doubled. This happens only of the networks are settled. System considers the Actual values from network + Statistical value from WBSE to caculate the assigned values.
    Simulation details as under.
    SP-SET-02-3  (wbs element)
        COSS 2011 11 0007101000     0001240704 KOAO D INR                 100.00  INR
        NWA 500000002408 0010
            COSS 2011 04 0007101000     0001240704 KOAO O INR                 100.00- INR   S  -- does not contribute to assigned value
            COSP 2011 04 0007101000     0001240704 COIN D INR                 100.00  INR
            COSP 2011 01 0007101000     0001240704 KPPP D INR                 100.00  INR   M   -- does not contribute to assigned value
    Hence the assigned value gets doubled and eating up the budget.
    Anyone encountered similar issues pls share the possible solutions.

    Hi Mohit
    It is against SCN's rules to post the same discussion thread twice. You have already posted a similar question in the below thread. Please refrain from doing this and close one of the threads.
    Initial balance upload of revenue GL accounts with wbs
    Regards
    Sowmya

  • How to change cost center in Asset Master record ?

    Hi SAP Gurus,
    My client is asking me to change cost centers in Asset Master records using LSMW. Currently, the field cost center is in display mode. In order to change the cost center, the field cost center must be in change mode while recording in LSMW. I have changed screen layout rule for Asset Master data. I have selected radio button "Optional" for cost center in screen layout for Asset Master data. But still cost center field is in display mode in Asset Master record. It must be changeable.
    Please suggest me how I can resolve the issue.
    Regards,
    K.S.K

    Hi Saravana,
    We can change the cost center for AuC Investment measure at WBS element level. For that purpose we need to go to AuC Investment measure Asset master record and check WBS element under Origin Tab. Double click on WBSE and then check the cost center under Assignment tab. And also check the cost center in Asset master record for the same. Now you can go to T.Code CJ12 (Change WBS Element) and change the cost center for the same. Once you make changes system automatically change the cost center in asset master record for the same.
    Note: - Now you have to identify all the AuC Investment measure Assets and the WBS Element for the same. Then change the cost center in WBS Element record. And the corresponding changes will be done in relevant Asset master record automatically.
    But before making the change please check with the PS/PM consultant regarding changes in WBS element. Means where it will effect?
    With Regards
    Ravinder Kaushik

  • Change of Cost Center in Asset Master for Investment measure (AuC) Assets.

    Hi,
    We have an asset class 4001 which has been maintained as an investment measure for AuC. I want to change cost center for all the assets that are maintained in the asset class 4001. The system is showing cost center field in display mode in change transaction of the asset AS02 for all the assets in the asset class. I want to replace the old cost center with new cost center in the asset master record. How can I make the cost center field changeable ? 
    Can anyone help me ?
    Regards,
    K.S.K

    Hi Kattula,
    We can change the cost center for AUC with Investment Measure. To do this you need to identify the relevant WBS element assigned to your asset. You can find the WBSE in Origin tab of your asset master record.
    Then go to the change WBS element Transaction CJ12 and change the cost center. Once you change the cost center of the WBSE, the change would automatically get reflected in the correspondind asset master record.
    This would solve your issue.
    Thanks & Regards
    FICO GSupport team.
    RK & IK.

  • Project ID-Cost Center

    How a Project Can be linked to a Cost Center?
    I think the only proper link is at the Work Center-Cost Center(Based on Activity). Is there any other means?
    Thanks & Regards,
    Bekele

    1. Using internal activity as you have mentioned
    2. If Statistical WBSE then thru 'ataual Cost Center' field in the WBSE master data so that actual cost will get posted to the Cctr maintained here.
    3. maintain CCtr in fields Responsible/Requesting Cost Center on the WBSE data and then create settlement rule strategy to create settlement rules with receiver always as Responsible/Requesting Cost Center (in case of expense projects only)
    If you have some specific objective in mind write back in detail.

  • BW Analysis authorization issue on cost center range

    Hello BIW security experts
    I have a problem where I created an analysis authorization on a cost center range and it looks like the interval is not working. The report is just a list of cost centers (demo to users to prove that analysis authorizations work in order to skip 2 managerial cost centers.
    . Cost centers are numeric. Example:  2000100. In the drop down list they appear as such.
    . I want to have the following cost center range: 1000000 to 1000771, 1000773 to 2000771, 2000773 to 9999999.
    Thereofore 1000772  and 2000772 should not appear in the list.
    . In the analysis authorization I have put the 3 ranges above on 3 separate lines. 'BT' is the operator. The cost centers have been selected from the drop down list.
    Results:  I get only 1 record from the report....  2000772. (which is one I want to exclude..
    Steps tried to debug:
    . When I put a list of cost centers in the analysis authorization on separate line with the 'EQ' operator, then the report works.
    . I tried putting ' ' delimiters since cost center is a char field but it fails.
    . I tried adding leading and trailing zeros to fill up the char(10) but no luck.
    . I tried creating a hierarchy with the interval and put it in the hierachy auth. tab and it does not work either. It gives the same number of records than the first step.
    . A hierarchy with single values work.
    I do not know what else to try..
    Thanks.
    YB.

    Good morning
    Here it is from RSECVAL
    ZCC_TEST     0COSTCENTER                    I       BT        1000000                                                      1000771
    ZCC_TEST     0COSTCENTER                    I       BT        1000773                                                      2000771
    ZCC_TEST     0COSTCENTER                    I       BT        2000773                                                      9999999
    ZCC_TEST     0COSTCENTER                    I       EQ        #
    ZCC_TEST     0COSTCENTER                    I       EQ        :
    ZCC_TEST     0INFOPROV                         I       CP        *
    ZCC_TEST     0TCAACTVT                        I       EQ        03
    ZCC_TEST     0TCAIPROV                         I       CP        *
    ZCC_TEST     0TCAKYFNM                       I       CP        *
    Thank you for your help.

  • Error in creation of Cost center

    Hi All,
    Trying to create Cost Center through KS01, however I am getting an error as "No compnay Code assignemt to the Contrilling area TS". can anyone please explaine me on the process to chek this error.
    Bharath

    HI Bharath,
    Please check the spro seeting for this error.
    spro -> enterprise structure - > Assignemtn - >controlling - > Assign Company Code to Controlling Area.
    Please check whether the required Company code has been assigned to the Controlling Area. If not please assign the required and check or the same.
    Please note: A company code can be assigned to one controlling are only
    Regards,
    Madhu Sudhanan

  • HR PNP Logical Database Using Cost Center selection: error!?

    Hi all,
    I'm using PNP logical data base and using the selection-fields available through HR Class Reports (a copy of PAY_DEF) but what happens is if in selection-screen I fill the personnel number say 1000, i get the payroll data I'm trying to get, but if i use the search field cost center of that exact person i get nothing. Does anyone has a clue on what i might be doing wrong? Because all the other search fields work, company code, HR area, everyone, but cost center, and I'm positive that i use the right cost center.
    Thanks in advance,
    Paula

    Even though nobody answered me, i finally found the solution for my problem. so and because someone might need it here it is:
    Go to Spro->Personnel Management->Human Resources Information System->Reporting->Adjusting the Standard Selection Screen and then:
    1st Create Report Categories and
    2nd Assign Report Categories
    Since not all rep. categories on the 1st assignment is explicit on how will sel screen appear i advice you to go to the 2nd point, and execute some of the programs that appear there, and that might look alike to what you are looking for, and if you are so lucky as to find one exact use the same report category in your program, if its very alike, well, copy the Report Category into one of your own and change it the way you need it to be.
    Hope this be helpfull for someone.
    Paula.

  • 1_CO_PA_AFS_CCA(cost center accounting) DS enhancement

    hi friends,
    i'm trying to extract COPA : Profitability Analysis data using 1_CO_PA_AFS_CCA(cost center accounting) to custom cube directly(i.e Data source to custom cube without any staging in between datasource & cube).
    In ECC6.0 (tcode: CK40N and then  costs ), per material wise i want to extract labour costs, deprecision, power & fuel, sub contract charges,other manufacturing costs along with this i want to extract i field information "costing lot size".
    I want to extract "costing lot size", but data source doesn't have this field. Is it possible to enhace DS.
    If yes, how to do that?
    Thanks,
    naresh

    Hello Shruti,
    Can you give more explaination about the problem
    Thanks & Regards,
    NK.A

  • BI-IP Authorizations: Accessing own Cost Center only

    Hi,
    We are currently implementing BI-IP in our company. We have created the ready-input templates and we are prepared for roll-out.
    There is still one concern though which I haven't resolved. I am currently looking for an AUTHORIZATION that will let users access their respective COST CENTERS only. For example, if I am part of the Marketing Group, then I will only be able to access the budget of my respective cost center.
    Can anyone lead me to the right AUTHORIZATION OBJECT in BI-IP to implement this restriction.
    Your reply is much appreciated. Thanks.
    Regards,
    Ramon

    Hi Ramon,
    authorizations for transaction data in BI (and therefore in BI-IP) are not based on authorization objects. You have to make the cost center InfoObject authorization relevant and then create so called Analysis Authorizations for it. Please see the online help:
    http://help.sap.com/saphelp_nw70/helpdata/en/66/019441b8972e7be10000000a1550b0/frameset.htm
    BTW, you can upload the cost center authorizations from SAP R/3 or ERP.
    http://help.sap.com/saphelp_nw70/helpdata/en/59/fd8b41b5b3b45fe10000000a1550b0/frameset.htm
    Regards,
    Marc
    SAP NetWeaver RIG

  • Add Option of choosing values from list in "Person Responsible" field of Cost Center Master

    Dear All,
    Could anyone advise me how can I add the option to Choose Values from list to field "Person Responsible",
    in Cost Center Master Data ?
    The Technical Name of this field is VERAK, and currently it is an open field.
    I would like to allow the user to choose values from existing list.
    Thank you!
    Orly

    Hi Orly,
    You have take it to your ABAPer, who will have to modify the attributes of CSKSZ-VERAK field in CSKSZ structure. ABAPer will have to define it with foreign key and introduce the name of the table, which will be used for deriving the available values. No standard table exists for it, but you can either create your own Z-table or take it from users table (USR02) if you have the necessary information there. Of course, this action would account for modification of standard SAP structure.
    Regards,
    Eli

  • Update cost center

    Hi All,
    Greetings,
    I need your valuable suggestion urgently.
    The Business user would like put additional business rule to populate the cost center based on transaction id.
    Currently All the cost center by default are populated ‘000’ for all the Transaction Id for GL Customization.
    Now business wants to update cost center '000' to something '123' based on TXN CODE ID.
    Here Transaction code will be used with business rule to create Journal Entry.
    Please guide me/ answer me to the following questions.
    1. can we replace (update) the cost centre code.
    2. Incase we update the cost centre will there be any other impact like finance, GL etc.,
    3. Any additional information to be considered before replacing the cost centre code.
    As the matter is most urgent. I request you to reply on priority basis.
    Thanks in advance.

    Hi,
    Thanks for your valuable information.
    Actually i am a technical guy and new to the functional.
    Could you please provide the steps to update the cost center for subledger.
    Thanks in advance.
    Edited by: 983909 on Feb 5, 2013 5:58 AM

  • Is there is a way to have a link from purchase order to cost center report.

    Is there is a way to have a link from purchase order to cost center report.
    I am meaning kind of:
    Standard way to customized this link?
    or
    User exit to have this link in place
    or
    Any other solution
    Thanks

    For me it does not make any sense from going from PO to cost center report.
    However, if you want to see the purchase order cost incurred with a cost center, execute KSB1 report. Within the layout, bring "Purchasing Document" field, where you can see the purchase order number in cost center line item report.

  • Assignment of Cost center to G/L account

    Hi,
    While Posting, I am getting the following error  " G/L account requires an assignment to a CO object"
    Where Do I assign the cost center to the G/L and why doesn't the system automatically pick the cost
    center?
    Regards,
    Ally

    First, if G/L account was created in FI, you can only create primary cost element in CO.
    Secondary cost element can only be created if no account exists in FI.
    Second, if you created the primary or secondary cost element in CO, you have to assign CO account assignment.
    You can delete cost element in CO (KO04) if dependent objects found.
    Third, when you create cost element in CO, documents would be also created in u2018Cost center accountingu2019 and u2018Profit center accountingu2019 when posing in FI. If no cost element exists in CO, no related documents would be created in CCA and PCA.

  • COST CENTER CHANGES FOR OPEN PO REQUIRE BEST APPROACH HOW TO DO IT

    Dear All,
    we are changing the cost center for open PO's kindly tell us the best approach how to do it for all open PO's line items for open PO's are 4000.
    we will totally block the old PO's and change the PO's with NO GR and IR immediately, but what and how to do for if there are GR, IR, or one of them their. and also what if IR and GR differences are thier, kindly provide all the best possible approaches.
    below are the scenarios.
    Open PO without GR/IR
    Open PO only with GR
    Open PO only with IR
    Open PO with IR/GR without difference
    Open PO with IR/GR with differences
    Service entry sheet
    kindly provide me all the best approaches to achieve this task. keep in mind beside reversal of GR or IR any other approach.
    qsm sap
    Edited by: qsm sap on Feb 15, 2010 12:08 PM

    Hi,
    Open PO without GR/IR
    Open PO only with GR
    Make Acct assigment as changeable at time of IR in SPRO for Acct Assigmet 'K' ...so that u can change the cost Center while doing MIRO. if u do not want to go with mass change.
    Service entry sheet
    You can change Cost center while Doing SES. No issue
    for others... reverse the IR as one option.
    Regards,
    Pardeep Malik