Cost center wise budget

Dear Sap gurus,
Could you please cost center wise budget confuration and availabulity control in system .
purchase value 100000  Name is Cost center1 if i raise of purchase order (Relevant account assignment items) Cost center given then the system should not allowed based on the po with commitment value accross 100000 and we want decrease the value once invoice is released in like 100000- 10000= 90000  .

Hi,
This issue has been answered several times: you do not have a budget control on cost centres, but you can do a workaround.
a) create statistical ordersand assign them to relevant cost centres
b) budget those orders
c) create a validation in CO not allowing posting to the cost centres without providing internal order
Thus, you will have a budget control on cost centre level.
Regards,
Eli

Similar Messages

  • Cost center wise comparison between FI view and CO view

    Hi,
    I have one doubt regarding comparison of cost center in FBL3N and in in S_ALR_87013611.
    Is there any report in from which I can compare Cost center wise actual spending in FBL3N  versus some reports in CO?
    I would appreciate if someone help me on this.
    Thanks in advance!
    Bhargav
    Edited by: BHARGAV RASBIHARI PADHYA on Nov 17, 2010 6:10 AM

    Hi Bhargav,
    If I am not wrong you are taking about the comparison of cost centres values in Co to Cost centre Values in FI.
    If this is the case, then its a pain compiling the values. Because, when values flow from FI to CO then dont come to one cost centre, they are spread accross various cost centres where they are incurred.
    For Example : You may debit P&S GL account for 10000, but the cost centres involve this expenditure this can be from different cost cetres like from Finance, Marketing, Retail etc.
    Now if you want to compare the cost ccentre values with the FI and COthen you can imagine the work and time involved in it.
    Let me know  if anyone have any different views on this.
    Regards,
    Mallikarjun

  • Vendor - asset - cost center wise report

    Hi Friends.
    Good morning,
    Please let me know vendor,asset  and cost center wise report ( ie for all vendors at a time.)
    Regards
    Srini

    Hi,
    From T.Code: AR02 you will derive your expected report.
    for vendor select dynamic selection and select ORIGN DATA Tab here you will get vendor field.
    Regards
    Viswa

  • Primary Cost Element Report - Cost Center wise Totals

    Dear Seniors,
    Requirement is to have a report which gives Cost Center wise Totals (Net posted amount) for Primary cost elements with the following fields --
    Company Code
    G/L account
    Business Area
    Cost Center
    Accounting Period
    Fiscal Year
    Net Posted Amount
    Debit / Credit Indicator
    Currecny
    Which Table gives me this information ?
    Thanks and Regards
    KVKR

    Hi
    If you are on New GL - Then FAGLFLEXT (Totals table)
    If not - Then GLT0 or tables startng with GLT*
    You can also use reports FBL3N and subtotal on Cost Element/Cost Center
    br, Ajay M

  • Employee wise posting details cost center wise

    Hi
    How to get the employee wise posting details cost center wise is there any standard report to know the details
    Thanks in advance
    Rgds
    Radhika

    hi Radhika,
    U can get the posting results employee wise details and posted wage types using a standard Program....
    Go To Transaction Code " SA38"
    Give the program as : -
    " RPCIP_DOCUMENT_ANALYSE "
    Give the Posted Document.
    Check Select details with Pers. NO
    For giving Payroll Area has selection.
    Select tab " Selection of Run attributes"
    u can give payroll area here. and In period here
    and also since the posting date would be fixed ....u can use that field also....
    GL Account u can get.........
    The fields are the same that you are getting in the layout.....u can select all the fields for display....
    Using tab " Selection for Account assignment "
    u can again filter the data....
    Try this out and revert

  • Relevance of Maximum Plan Value for Cost Center wise SKF plan Data

    Hi,
    Will you please tell me the relevence of data entered as Maximum Plan Value for the Cost center wise SKF data plan i.e. data entered through T Code KP46 using planning layout 1-301 with planning profile SAPALL.
    Regards,
    Partha B.

    Hi,
    Try 0CO_OM_CCA_1.

  • Preparation of cost center wise report

    hello experts,
    I want to know the tcode for cost center wise expenses reports.
    i have tried the ksb1 but it is working only for one cost center at a time.
    i want to prepare the cost center expenses report for all cost center in company in following format.
    cost center
    Amount
    what procedure should i follow?
    Please help.

    You can use KSB1 but create a Cost Center Group with KSH1 to make it easier.  You can also create a group of groups to form a hierarchy so you can analyze at different levels.  Hope that helps.

  • Trial Balance Cost Center Wise

    We have created the Cost Elements, in the system for assigning the Cost Centers to these as and when the transactions are recorded. While we can generate the Cost Reports based on the Cost Centers used for capturing the transactions, there is a requirement to generate a Trial Balance as per the Cost Centers. Is there a standard report that can provide a Trial Balance as per the Cost Centers and thus for a particular Group of Cost Centers.
    Would appreciate an assistance in this regard.
    Thanks in advance.

    Hi Bhuveneshwari,
    Agree with you that TB will include assets andliabilities as well. To clarify further, what is desired is the list of balances Profit Center/Cost Center wise for only those accounts which form part of the P & L, i.e classified as Revenues and Expenses to prepare a funtional Profit & Loss Account. How can we acheive this. One way is to generate the Cost Reports with all the Cost Elements. Also is it possible to generate a limited TB (including only P&L items) Profit Center wise as referred to in your reply ?
    Thanks

  • WBS list ( profit center wise / Cost Center wise)

    Hi All
    I have a query on WBS elements, I needed a list of all the WBS elements, Profit center wise & Cost center wise(is it possible to get cost center wise list)..  
    I am using trans CN43N.  Is it the correct report or is there anyother report I need to execute to get the list of WBS elements(profit / Cost centerwise)
    Regards
    Bala

    It s simple to get that using SE16n..
    Enter table MARC.. PRCTR is the field for profit cener.. Enter ur prof center and execute..you ll get the list of matreials under the profit center
    ALso check ke5z...

  • Retreiving F.01 Report Cost Center wise

    While executing F.01 report GL Code and cost center wise it does match with the FBL3N report by puttiing the same parameters i.e GL Code and the Cost Center.
    Please advice....

    Hi,
    F.01 is for displaying the balance sheet and P&L statement for a company code.
    Cost Centers is a cost object where costs will be stored for analysis purpose. If you want to match the Expenses gl balances with F.01 balances, go to FBL3N and take all the Expences GL accounts and execute.
    The important one is in all GL accounts should be selected for line item display.
    After executing the report change the layout, select the cost center and display subtotals gl wise.
    Thanks & Regards,
    shashi kanth.

  • Cost Center wise profitability

    Hi All,
    We want the profitability analysis cost center wise. Is it possible? If yes, how the Revenue value, sales quantity and the COGS value can be derived for the cost center wise report in KE30.
    Please help me as my client has asked this requirement.
    Regards
    Subbu

    Hi Subbu,
    Cost center wise rofitability is possible in COPA.
    Create Cost center as a characteristic in the COPA structure.
    The client has to  on what basis the revenue and costs will be divided among cost centers.
    It is unusual / Impractical to have Cost center wise Profitability statements as in SAP , Cost centers are used for Overhead  Cost control and Management.
    Enjoy
    Siva

  • Cost center wise trial balance GL

    Hi Friends,
    My clients wants GL trial balance cost center wise. i try the below t.code S_ALR_87012277 - G/L Account Balances , S_PL0_86000030 - G/L Account Balances (New) but system is not showing any data. Please advice any t.code or other soluation.
    Thanks & Regards,
    Pankaj

    Hello,
    Please note that there will not be any traial balance.
    Only expenses flows to cost centers through cost elements. But, none of the asset balances and liabilities will not flow to Cost Center.
    You have to depend on Profit Center for viewing your balance sheet.
    Regards,
    Ravi

  • COST ELEMENT WISE BUDGETING AND AVAILABILTY CONTROL

    Dear Experts,
    I am looking at Cost Element wise Budgeting and Availabilty control in internal Order, Availabilty control also should be Cost element wise.
    Regards
    Deendayal

    Dear Surya Narayana,
    Thanks for your prompt response, well i know that Budgeting is at summary level, want to just explore any other way out, is there any possibilty to link planning to budget as plannig is done on cost element wise.
    you can also send me the details of budgeting and avaiilability control at dayal05 at gmail.com.
    regards
    Deendayal
    Edited by: DEENDAYAL RAMACHANDRAN on Mar 3, 2009 2:15 PM

  • Cost Element wise Budgeting

    hello guru,
      our client want to make the budget on cost element wise. is it possioble or not?  if possible plz guid me how to configuration to be do.
    Rega
    laxmi

    Hi Friends,
    I have an option which i am guessing is in T.Code-7KE1 you can give ur controlling name> give the layout name>version>from period>to period>fiscal year>co.code>profit center>account number>free in Entry down>select in top 2nd buttion period screen (F6) and ENTER so now you can give ur budget cost element wise for each and every month.
    Hope the explanation is clear.
    Have a nice time.
    KUMAR.

  • Value wise restriction Cost Center Wise

    Dear Experts,
    How can we restrict each cost center not raise PR beyond some limit.For example i want to restrict one cost center to buy consumbale not beyond 1 lac per annum so there should be some check at PR level to stop user for creating Purchase requisition if value cross 1Lac.
    Regards
    Vivek
    Edited by: Supergene on Jan 15, 2009 3:01 PM

    Hi
    You can set up budget for cost centre and limit the expenditure on it.
    Thanks