Cost centre &Internal order

Hi,
How to check for the particular Internal order is tagged to cost centre
it will help full for me
Thanks
Sandesh Rao

Hi Sandesh ,
If cost center is known to you then you can see with which order it is tagged.
To see in which all orders this cost center is being used Go to KS03 Tcode give the cost center number then press enter then first screen of master will come then in menu bar GO to Environment -->where Used List -->select as required .then sys will give you list as according.
Hope this will be helpful to you .
Regards
deepa

Similar Messages

  • SAP Report to track cost by Internal Order

    Hi Expert,
    for audit purpose, I want to track the Cost by Internal Order, please suggest me in sap have any report to track down?
    below format is an example.
    release code   cost center        internal order number   PR number  PO number  SES number  vendor name  desc of item cost of item
    Thanks.

    Hi Pal,
    Many Thanks for your input, as per your recommendation
    Mani as you suggested ME2K was working fine, but anyway we need to drill down further to double of each field.
    As Nico suggested building a query, to view all at a same time is good & perfect to use.
    So please suggest me, what are the tables and fields map to build a query? because Itu2019s very easy for me to assign fast.
    Regards,

  • SAP report which display PO nos based  on cost center, Internal orders

    Hi.
    I am looking for a report in MM which will display the list of purchase orders for a cost center, Internal orders etc.
    The report output should have ALV grid format,The output of the report should have material no or short text, PO quantity, PO Price, PO value. GR qty, GR value,IR qty, IR value, G/L to which consumption has posted etc.
    Reports ME2K, MB5S, ME80FN do not show the G/L account to which GR value is posted.
    Basically I am looking for a existing report which is readily available.

    Hi
    I dont think there is standard report. we have developed custom report one of my previous project.
    YOu can try a abap query using tables EKKO, EKPO, EKBE and EKKN.
    regards
    Srinivas

  • BAPI KPF6 POST PLAN COST FOR INTERNAL ORDER AND COST ELEMENT

    Hi all gurus,
    I would like to use in a custom report a BAPI/Function Module that help me to simulate KPF6 in order to post planning costs for internal order and cost element (layout 1-401).
    So the input should be:
    1) Version
    2) period from
    3) periodo to
    4) year
    5) internal order n.
    6) cost element n.
    7) value
    I found a lot of BAPI but don't know the correct one and how to use it (example how to fill the input value).
    Can anyone help me on that?
    Kind Regards

    In additio  to the previous I found the BAPI_COSTACTPLN_POSTPRIMCOST but don't know if it's the correct one and how to use it (some example fitting the my case will be very appreciated).
    If the quoted BAPI is correct.
    I tested it filling all fields as following:
    HEADERINFO:
    CO_AREA=FFCA
    FISC_YEAR=2008
    PERIOD_FROM=001
    PERIOD_TO=012
    DOC_HDR_TX='blank'
    INDEXSTRUCTURE:
    OBJECT_INDEX=000001
    VALUE_INDEX=000004 (hope this point at Interna Order)
    ATTRIB_INDEX=000000
    COOBJECT:
    OBJECT_INDEX=000001
    ORDERID=ZO53-08IMZ
    TOTVALUE:
    VALUE_INDEX=000004
    COST_ELEM=3224048
    FIX_VALUE= 200,0000
    DIST_KEY_FIX_VAL=2
    The Return table is set to 0. Nothing happens.....I suspect something related to indexstructure or index is wrong..
    Could anyone help me on that?
    Kind Regards

  • TX CNS41 - settled cost from internal order to WBS element not displayed

    Hi PS Expets,
    I have a question regarding transaction CNS41 "Structure Overview" where cost settled from an internal order is not displayed in in the report for a selected project. This is in a ECC version 5.0
    Settled costs from internal orders are posted with transaction type KOAO on WBS elements and when you check report RCNSTFCO you can see that the following transaction types are deselected when executing transaction CNS41:
    delete t_rpsco_m where vorga = 'KOAO' "<   insert
                          or vorga = 'KOAL' "<   insert
                          or vorga = 'KOAP' "<   insert
                          or vorga = 'KOAQ' "<   insert
                          or vorga = 'KOAR'."<   insert
      CALL FUNCTION 'HFPM_RPSCO_TO_RPSCO_LIS_CONV'
    This is implemented according to OSS note 51971 in order to eliminate internal business volume in the project structure when executing a PS hierarchy report.
    But this also eliminate the display of the cost  from the internal order.
    Any ideas or a work around in order to display settled cost from an internal order on a WBS element in transaction CNS41
    Kind regards,
    Anne

    Hello Tison.
    I guess you have the Project created with a BAPI in your system in background. As far as I have seen I'd try the following in ABAP to create Partners in the Project Definition: BAPI_BUS2001_PARTNER_CREATE_M or the corresponding method ProjectDefinitionPI.PartnerCreateMultiple. This should happen in background when the Project is created also.
    Best regards.
    Jens Schmid

  • Can i allocate cost from Internal order to PA?

    can i allocate cost from Internal order to PA?
    if i can .
    please tell me how to do.

    Hello Friend,
    OKO7 is the tcode to settlement profile - here you can choose segement for allowable settlement object.
    KO88 is the tcode of settlement of internal order.
    Thanks
    ravi

  • Costing on Internal Orders with different plan versions

    Hi,
    Is it possible to carry out Costing on Internal Orders using different plan versions?
    I would like to carry out more than one costing on Internal Order so that I could compare different versions. Maybe there are other parameters (other than plan versions) which can be used for executing different parallel costing.
    Best wishes,
    Karol

    Hi Karol,
    In Release 3.0, the following new planning functions are available in order planning:
    <b>Copy plan versions</b>
    In Release 3.0, you can plan order costs for internal orders in different versions. In contrast to earlier releases, you can now
    1. change versions
    2. copy versions
    3. Here you can select :
                                 the planned values to be copied: annual or total values
                                 whether the planned values in the target version are to be retained or overwritten compare versions using the information system
    Planned values are not revaluated in the target version (for example, when you change the value date).
    Overhead and settlements are not copied and, if required, must be repeated in the target version
    Regards,
    Hemachandra K S
    <b>Please, donot forget to mark the answer as Helpful, Very Helpful or Problem solved.</b>

  • Production order variance settlement to cost centers/internal order

    Hi,
    I am looking to configure the settlement of production order variances to cost centers/internal order. Is there a way to do this in the settlement profile. Would appreciate your help.
    Thank you,
    Ram

    OKO7 will allow you to configure the Settlement Profile by selecting valid receivers.
    This should be done with/or by FICO.
    Then test, test, test
    award points if helpful
    Althea

  • Whether OPM Costing considers Internal Orders???

    Hello Girish,
    Let me introduce myself. I am aditya. I am a fresher in OPM.Infact i wanted to ask Whether OPM Costing considers Internal Orders and if it is yes then ho
    Please reply me ASAP.
    Regards
    Aditya

    Yes aditya,
    OPM Costing considered all (Internal Order and Sales Order too) Because OPM has sources like Purchasing and Order Management

  • Report with Cost Centre/Cost Element/Internal Orders required

    Hello SAP Gurus
    I need to run a report in CO where the output displays actual line items for Cost Centre, Cost Elements and Internal Orders in a single report. Is anyone aware of any SAP Std reports that provide this information. So far I havent found any
    Thanks
    Prakash

    Hi,
    You can use this one S_ALR_87013602 for totals, but, of course, it does not split between cost objects. For line items, you can build simple SQVI based on COEP table.
    Regards,
    Eli

  • Cost center &internal order

    Dear guru's,
       We are implimenting asset module newely.previously we are using Zreports based on cost center and internal order.but now we need to make mandatory filed for dep accounts,this gl's amount should be papulated in that report.so how to do this configuration can any one tell me.
    Thanks
    Ravi

    Dear Paul,
         If i give cost center and internal order in asset master while doing AFAB system giving error  like
    " Field Cost Ctr is a required field for G/L account 1600 3300501
    Message no. F5808
    Diagnosis
    The value for field "Cost Ctr" in the interface to Financial Accounting is an initial value but you are required to make an entry in the field selection for G/L account "3300501" in company code "1600" linked to the field selection for posting key "40".
    System response
    Error
    Procedure
    It might be an error in the configuration of the G/L account field selection. The initial application, used to call up the interface must otherwise define a value for field "Cost Ctr". If this is the case, contact the consultant responsible for the application used to call up the interface or get in contact with SAP directly "
      Can you suggest me.
    Thanks
    Ravi

  • Tagging employee cost to Internal Order

    Hi All,
    My client wants the Employee costs to be tagged to Internal Order(IO) and interfaced to FI.
    This is possible for IT0014 and IT0015 using Cost Assignments where in we can specify the Order - defined in FI(same as internal order).
    But my cleint requires it for IT0008 as well. Is it possible? If yes, how?
    Secondly is there any config requred on posting side for IO's, Apart from the master data config for IO on FI side.
    Appreciate your help.
    Regards,
    Swati

    Hi All,
    My client wants the Employee costs to be tagged to Internal Order(IO) and interfaced to FI.
    This is possible for IT0014 and IT0015 using Cost Assignments where in we can specify the Order - defined in FI(same as internal order).
    Is there any config requred on posting side for IO's, Apart from the master data config for IO on FI side.
    My client requires cost assignment fature for IT0008 as well. Is it possible? If yes, how?
    Appreciate your help.
    Regards,
    Swati

  • Function Modules for Actual, Plan, Budget Cost over internal orders

    Dear All,
    I need a function module for getting the Actual, Plan, Budget Costs for the internal orders assigned.
    I want to fetch the cost related to internal order which is assigned to project C projects in PLM.

    hai tehre are no such funcion moduels
    u have to select from bpge and bpja tables
    and sum up them
    afzal

  • Assignment of Production Order to Internal Order

    Can a production order be assigned to an internal order so that the manufacturing costs can be seen in the internal order?
    My scenario is such that I want to manufacture sheet metal dies. The various costs involved are design costs, procurement costs and manufacturing costs. The design costs and procurement costs will be captured in the internal order. I want to capture the manufacturing cost through the production order.
    Now the problem is how can I see the total of all three costs in the internal order?
    Thanks in anticipation.
    Sumeet

    As I know,
    You can assign internal order as a settlement receiver. Since production order itself is a cost receiver.
    Why connot you use internal order instead of production order. You can do GR/GI to internal order.
    One more option is you can use cost centre/internal order as a receiver, maintain a minimum price (1unit=1$)in production material and when you settle all the cost will be settled against the cost centre/internal order.

  • Org Charts not pulling through complete internal order numbers

    Hi Team
    Can u please help me to overcome my issue
    Here is my issue -
    Can someone please investigate this issue - the internal orders are not pulling through to the Org Charts correctly.
    As per this screen shot, Michelle Morgan is on internal order 4000035.
    However as per this next screen shot, this information is not pulling through completely (it is only showing 40000).
    I.e  one employee the cost centre / Internal order on R3 is showing as one number and on portal it is shown as a different one

    The only reason to resettle the orders is that the "settlement rules" were revised in the current fiscal year .  In the current fiscal year , the settlements for each settled period (closed period) are reversed and then resettled in the current  open period using the revised settlement rules. However, the issue involves these same orders had costs in the previous fiscal year and were settled originally in that previous fiscal year with the old settlement rules. This is a closed fiscal year and all periods are closed.  
    Any thoughts on a system approach to effect the settlement rule change crossing two fiscal years rather than manual entries for prior fiscal year settlement rule impact as a  two step process the first step being the current fiscal year resettlements and the second step the manual entry for previous year impact ?

Maybe you are looking for

  • How can I remove sensor spots from video?

    I have a badly spotted video. There is a tutorial that shows how to accomplish spot removal with CS 5 Extended <Smart Object Video in Photoshop | Russell Brown at Photoshop World 2011 - Orlando | Adobe TV> , but this does not seem to work on my progr

  • NO AUDIO OUT PUT DEVICE

    I DELETED MY AUDIO OUT PUT DEVICE   BY ACCIDENT  COS I HEARD STATIC IN THE SOUND AND NOW I HAVE NO SOUND THE LITTLE SPEAKER SYMBOL HAS A  RED CIRCEL N AN X IN IT SAYING NO AUDIO OUT PUT INSTALLED  IT  CAME WITH MY LAP TOP N IM TOLD ITS A FREE DOWN LO

  • Dynamic to Static URL

    Dynamic to Static URL's what is the best program to use to do this? Because I dont' want to make hundreds of static pages, is there a easy way to show this properly and get better indexing at the same time. I have heard of wordpress, but don't know i

  • Photo limit

    Is there a limit on number of photo's ATV2 can handle?  It does not display my whole library, probably shows 20k of my 60k photos.

  • InCopy Installation Issues 32-bit

    I built a 32-bit and a 64-bit Version of InCopy CC with the Package Installer. The 64-bit Version installs fine, but I'm having issues with the 32-bit installer package: The installer starts and after a short time the progress bar just rolls back and