Cost Element Report for all cost objects

Hello,
Is there any standard SAP report where it can list down all cost elements, and their line item/total postings done to various CO Objects in one shot.
We have CE/CCTR, CE/IO, etc, but if we can have one report which can list all cost elements and postings done via it to different cost objects - cost centers, internal orders, WBS, etc, might be very handy to us.
Thanks
Balla

Hi Balla,
Please use S_SL0_21000007 for your requirement.
It gives cost element postings to different cost objects.
regards,
makrand

Similar Messages

  • Cost Center Report for each Cost Center

    Hi everybody,
    I am using SAP R/3.
    I have 90 Cost Centers (and Variants) and want to print a report for each one. But I dont want to key in all 90 Cost Centers (or select all Variants).
    What opportunities do I have? And I would like to have a kind of report were I can change the layout.
    I use this kind of report (no standard):
    Y_HGS_46000001 - Actual : month/cost center
    The problem: We have more than 500 Cost Centers in our system. So I can't use "range".
    Markus
    Edited by: Markus Schreiter on May 27, 2008 4:12 AM

    @ Karl:
    I defined variants for:
    1. "All Cost Centers"
    2. "Business Divisions"
    - Production
    - G&A
    - Selling
    - Non-Operating ...
    3. "Business Groups"
    - NSW Lab
    - WA Lab ...
    4. "Each Cost Center"
    With No.1 I now have the opportunity to run a report with all CCtr.
    Markus

  • How to find the origin costs(primary CE) for Assessment cost elements

    Hi All,
    How can we trace the Orgin costs(cost senders) for Assessment cost element.
    I have to create Co report where user wants the Costs senders(primary cost elements) details for Assessment cost element.
    Our cycles are defined as senders -  cost center and receiver's are Internal orders.
    so for assessement cost elements what are the primary cost senders.
    Is it possible to trace the primary cost elements details for Assessment cost elements.
    Regards,
    Raj

    Hi Chirstian,
    Thanks for the information.
    I have done the same as per your advise.
    I am trying to pull all the primary cost elements which are posted with my sender cost center's.
    All the cycles are defined as share in % = 100%.
    But unfortunately all the debits are of primary cost elements is not equal to credit amount of my Assessment cost element.
    The figures are very far and couldn't trace the difference amount. Is there any other report in SAP or how i can define in report painter to meet this requirement.
    Thanks & Regards,
    Raj.

  • Cost element report prob. with auxiliary account assignment

    Hi,
    WBS is statistical.
    Orders are auxiliary account assigned to WBS.
    When running cost element reports, cji3 ; settlement cost elements are not showing there for the order.
    Kindly suggest.
    Thanks,
    Harsh.
    Edited by: Harsh Saxena on Dec 8, 2010 2:12 PM

    NOT RESOLVED

  • Interface for all cost object related transtions with third party system

    Hello Guru's
    I have one required for Functional Specications i.e,  i need to create interface for all cost object related transtions with third party system for this purpose i need to create FS. any body please guide how to do..

    Hi sreedhar royals
    You need to check controlling tables you need to interact. (CSKS, COAS,....) then ask your abaper and project manager to guide you.
    Regards

  • Cost Analysis Report - For a range of process orders

    Dear all,
    Is there a standard report available to get the cost analysis for a range of process order? COR3 --> Go to --> Cost --> Analysis. Here I can see the cost analysis for one report. But I wanted to get the cost analysis report for a range of process orders. Please help.
    Thanks
    Nagarajan

    Dear
    You can use cost analysis report like
    1.S_ALR_87099932 - Variances Between Costing Runs
    2.S_ALR_87099931 - Price vs Cost Estimate
    3.S_ALR_87099932 - Variances Between Costing Runs
    5.KOC4
    Regards
    JH

  • Secondary cost element report

    Hi experts,
    i just looking for secondary cost element reports ?
    regards,
    Sanju M S

    HI,
    Go to T.code : S_SL0_21000007 and,
    Go to bellow link
    http://wiki.sdn.sap.com/wiki/display/PLM/SettlementandCostElementReports
    http://help.sap.com/saphelp_46c/helpdata/en/a9/ab76ce414111d182b10000e829fbfe/content.htm
    Thanks,
    Raviteja

  • Using Primay cost element instead of secondary cost element for expenses tr

    Hai  SAP Guru
    WE are developer company, so when a land is acquired we create the project under business development with nomenclature "BD/LG/01" with  corporate  profit centre linked to it (as we are not sure if the project takes of due to various issues.)
    When the project commences we create another project structure with nomenclature "BE/LG/01u201D  with new profit centre.
    So when we transfer the cost lying in u201C BD u201D  project to u201C BE u201C project by giving settlement profile, the cost get transferred using secondary cost element. when we see the statement through CJI3 report the cost would have get transferred but when we
    see the report through Finance Profit Centre report the cost would have not transferred.
    So in order to get the report in profit centre, can we use primary cost element instead of secondary cost element, if we use the primary cost element what the consequence and what care needs to be taken for settlement.
    Thanks.

    Thanks.

  • Which PnL GL Accounts should have cost elements created for??

    Dear Sap FICO Experts,
    I am confused that which profit and loss GL Accounts should have cost elements created.
    Some suggested that Price Differences, Cost of Goods Sold, Revaluation of inventory and change in WIP GL Accounts should not  have Cost elements created, and some have the other opinions. Kindly let me know the reason if you suggest that for particular accounts, cost elements should be created.
    Best Regards.

    Hi
    As per my knowledge not all P&L accounts are created as cost elements.
    All expenses realted GL accoutns are created as cost element category 01
    All revenue related GL accounts are created as cost element category 11
    Al sales deductions related GL accounts are created  as cost element category 12.
    The above given are some of the categories of cost elements we can create in SAP.
    Thanks & regards,
    Anantha Prakash

  • Analysis report for standard cost in CK33N

    Hi,
    Analysis report for standard cost
    Using variant Z003 in CK11N.
    Planned cost 3 is the output used for planning and this is adjusted by making changes to the BOM throughout the process
    In CK33 you compare the 2011 cost for the product with the proposed cost for the next year.  For some parts it works and for others it splits the lines,  though the calculation is still correct.
    Regards,
    T.Harish Kumar

    Hi Revital,
    I believe the last option is correct.
    Thanks,
    Gordon

  • Report for Landing cost

    Hi SAP Guru's,
    Do we have any standard report for Landing Cost in the procurements, please suggest.
    Thanks,
    Reddy

    Hi Manish,
              We need to get one report with the total cost of material procurement which includes the excise, transportation and insurance.
    Thanks,
    Reddy.

  • Settled costs don't display in hierachy and by cost element report!

    Hi Experts,
    After doing project settlement, I check in hierarchy cost report (S_ALR_87013533) and by cost element report (S_ALR_87013543) and found that: Costs which had been settled did not display anymore!!
    It's not my expectation because I want to see the total actual cost of project.
    Please help to advise.
    Thanks and best regards,
    Khoa Huynh

    Hi Sreenivas Kadiam,
    So you mean that only when we settle project cost to CO production order, in Project cost report, balance will be zero is the standard behavior, am I right?
    Because when I settled the project cost to AUC, the total actual cost of project still display in Project cost report.
    Thanks and best regards,
    Khoa Huynh

  • Change value in cost element report

    Dear Experts,
                           Is dere any option to change value in the cost element report ie S_ALR_87013543...If it is possible please let me know......
    By
    AS

    Hi,
    I don't think that Price Change Functionality would be possible in any of the PS reports.
    Regards,
    Harsh.

  • GL/cost element report

    Hi Friends,
    Please let me know that which tcode or link i must use to check the cost coming from various GL/Cost elements
    Rgds
    Rahul
    Edited by: rahul m on May 9, 2008 12:47 PM

    Hi,
    Pls check following transactions to execute hierarchy reports and cost element reports.:
    CJE0: Execute Report: Hierarchy Report
    CJEB:Execute Report: Hierarchy Report in Background
    GR55:Execute Report: Cost Element Report
    Reward  if useful.
    Regards,
    Amit

  • Standard cost element reports are not available

    Hi everyone,
    I noticed that there are no standard cost element reports available in our SAP application. Is this because they are not imported or is this caused by another problem ?
    Help would be greatly appreciated and points will be rewarded
    Kind regards
    Message was edited by:
            Björn Demol
    Message was edited by:
            Björn Demol

    can you tell me how did u resolve this issue
    Regards
    Bilal

Maybe you are looking for