Hi
I am new to the logistics module and have just started  learning the PM and CS modules. I was just trying to figure out a query raied by one of the clients regarding a report which will generate the "cost per mile".
Actually the client wants to calculate the cost incurred on the fuel used to run their vehicles. These are fueled from a particular fueling station and the client wants to do a feasibility check on  the cost incurred on running the vehicles.
Kindly help me with this. The client is actually looking for a standard SAP report for cost per mile.
Thanks

Hello,
Also refer this [ THREAD|Re: error in Fleet management customising] and [link|Error when recording measurements in IFCU]
Regards
Nav
Edited by: Desire_Naveen on Nov 4, 2009 12:35 PM

Similar Messages

  • CO - Cost per case report

    Hi All,
    Is there any standard report in SAP in which we can get the Cost per case and weighted average?
    Case could be like pack of 12 bottles. If the production is 12000 bottles then the cases will be 1000 and cost per case will be 1000 X cost.
    Thanks,
    Syed Abid Hussain

    Hey,
    To my knowledge such a report does not exist in standard.
    In this case a custom report should be written.
    If the report should be related only to the total value (moving average or standard price), then you only need to take into consideration the MARM, MARA and MBEW table or using logical database MSM (creating a query).
    Regards,
    Koen

  • Custom SAP report used to display an average standard cost per material.

    Hi All,
    I need to implement a report with the following functionality,
    This is a custom SAP report used to display an average standard cost per material.  Standard cost data is stored in SAP at the Material/Plant level.  This report will gather the individual Standard Costs at each applicable plant (restricted by selection screen input and additional logic specified in more detail in the u201CReport Fieldsu201D section) for applicable Materials (restricted by selection screen input; if not specified all materials should be returned) and calculate an average standard cost for each material.  The corresponding Currency and Base Unit of Measure will also be displayed.
    Additionally the relevant u201CCommodity Code/Import Codeu201D information should be displayed for each material returned.  This attribute is also stored at the Material/Plant level.  To determine the value of this field for each relevant material, the report logic must retrieve the values stored for each plant.  If all values are the same, the value can be output to the report.  If not all values are equal, a message u201CNot Consistentu201D should be output.  It should be noted that if all values are u201Cnull,u201D a null value should be returned in the report.
    Can any one provide me with sample code for the same??
    Thanks Debrup.

    Hello,
    Also refer this [ THREAD|Re: error in Fleet management customising] and [link|Error when recording measurements in IFCU]
    Regards
    Nav
    Edited by: Desire_Naveen on Nov 4, 2009 12:35 PM

  • Manage Item Cost per Warehouse

    Previous posts have confirmed that it is not possible to change the Manage Item Cost per Warehouse option once any inventory transactions have been posted.  One entry posted in Feb 2010 (below) even offered a link to other "Irreversible Ticks" (although that link is now broken).  This limitation is required in order to preserve the relational integrity of the system, within its design architecture.
    Manage item cost per warehouse
    If a database has been in operation for several years with company-level costing, and business changes now force tracking costs by warehouse, I see no option other than creating a new database with the per-warehouse option, then loading items, inventory, GL, etc.  Unfortunately, all history (GL transactions, document history, change log, etc.) is no longer available in that database.
    Is anyone aware of SAP plans or tools to support any other alternatives to this kind of business change?
    Thanks, Dave

    Hi Dave,
    I am afraid creating a new database is your only option.
    For old data, you may still keep access for certain reports. All open items has to be imported to new db. It is a kind of manual archiving. Your database performance will gain a lot though.
    Thanks,
    Gordon

  • Cost Per hour, Costs per route not updating in S114 structure

    Dear PM Guru's,
    i am using MET unit system for vehicle consumption analysis. After completion of measurement documents and material issuance through IFCU, i checked the MCIZ report , but there i could not find the value of Costs per Hour, Costs per route information. I am requesting you all please guide me where i did the mistake either in "Configure measurement document updation" or calculation method?
    I am eagerly waiting for replies.
    regards
    JKM

    Its not possible to give any specific section where it might have gone wrong. Suggest you to check the complete configuration under Settings for Fleet Management. Also check the configuration in IMG - PM & CS - Information Systems - Configure Measurement document update

  • Maintenance cost per production output

    Dear All
    I have to create report based on Maintaince cost per production output
    and this report is company code wise and Fiscal year period wise ,
    now i got two different cubes from where i can get that cost
    1) 0PM_C01 for Maintenance Cost
    2) 0PC_C01 or IC_C03 for Production output in tonnes

    Hi,
    If the selections used for the query are available in both the cubes,ie company code and fiscal year, then just create a multi cube over it containing both maintenance cost and production output. Map it to the correct fields from the cube and create a report with formula to calculate maintenance cost per production using maintenance cost from  0PM_C01 and production output from 0PC_C01 or IC_C03.
    Regards ,
    Shyam.

  • For Vehicle ...BOM vise materail cost per unit

    Hello Experts
    ON BW i need to create a report for Vehicle on  material cost per unit vise (BOM vise). ...... I need your help.
    With Regards

    Its not possible to give any specific section where it might have gone wrong. Suggest you to check the complete configuration under Settings for Fleet Management. Also check the configuration in IMG - PM & CS - Information Systems - Configure Measurement document update

  • Hoe to split a shipment Cost per Distance

    Hello
    I have the following scenario:
    2 Deliveries in a Shipment Document with the same route.
    I have created a condition record for distance. For example: USD 1,00 per Mile and I have 1000 MI in my route so the system will calculate USD 1000
    But I need to split these 1000 USD for each delivery, for example USD 500,00 for each one.
    But when I am creating the Ship Cost the system is doubling my ship cost creating a document with USD 2000,00 being USD 1000 for each delivery.
    How can I make to the system split my freight per distance?
    Thanks
    Marcos

    Hi,
    If I understand your problem correctly, in your calculation base for the condition type defined, you could maintain as "Shipment Cost Item" (cost determined for a Leg), and you can distribute the cost to each delivery in a shipment by maintaining cost distribution as "Delivery".
    Hope the above helps.
    Thanks.

  • Managing item cost per warehouse.

    Hello,
    I have a client who recently migrated from SAP Business one 8.81 to 9.0 PL8. And now they want to manage items cost per warehouse.This is because although the cost and quantities are okay at company level, at warehouse level there are now some negative values as they have been in operation for over 3 years. In the setups, I found out that the manage item cost per warehouse check box settings was not ticked. How do i ensure that this check box is ticked and what procedures do i take to make this happen. The client has more than 2,000 items and about 30 warehouses.
    Most of the recommendations in the discussion  forum talk about creating a new database, After creating it, how do you go about it. what are the procedures involved?
    Kind regards,
    Maureen

    Hi Maureen,
    This setting one time setting and you can not change once Transaction is posted in System. Please also check below link.
    https://help.sap.com/saphelp_sbo882/helpdata/en/45/07edb6ae742461e10000000a1553f7/content.htm
    Please also check below links.
    Manage Item Cost by Warehouse Function
    changing Manage Item Cost per Warehouse
    Manage Item Cost per Warehouse and Warehouse for Damaged Goods
    Hope this help
    Regards::::
    Atul Chakraborty

  • Asset Balances & Cost Line items Report

    Hi,
    I am looking for a Report which would combine Asset (S_ALR_87011963)balance report and Cost line item Report(CJi3) for Projects.

    Hi,
    The flow is like this ( if u r using timesheets for confirmation):
    CAT2 : Timesheet: Enter Times : User enters the time.
    CATS_APPR_LITE  : Approval of timesheet
    CAT5  : Transfer to Projects.
    This will post cost to Projects.
    Another way of getting the Actual cost is Confirmation using CN25 or CN29.
    Regards,

  • HP OfficeJet Pro 8600 - The Really High Cost Per Page

    On February 6, 2014 I bought an HP OfficeJet Pro 8600 all-in-one, including the OPTIONAL tray 2.
    I use it in my home office with five computers.  One is a new Apple MacBook Pro OS 10.9.5, another is a three year old HP Laptop on Windows 7, and another is a five year old Dell Desktop still on Windows XP.
    I bought the printer to . . . print.  I thought I might be a nice convenience to write business correspondence and print an envelope, without the need to change paper, or otherwise touch the printer until I was ready.
    The printer is advertised, even in the user manual and box, to be capable of 1200 dpi printing, even though it uses the below average PCL Print Driver and not Post Script.
    The printer works fine, but the HP driver and utility software must be written for a different printer.  If I put HP Inkjet 20# paper in tray 2, and #10 envelopes in a locked tray 1, I can print at the "best print setting" which still isn't great.  But it works.
    If I put HP Premium Presentation Paper 32# paper in tray 2 ($8.00 per 100 sheets), and the same quality #10 envelope in tray 1, the printer software loses it's mind.  It performs the same on all five computers.
    When I try to print a business letter and envelope the print driver and HP utility grays out tray 2, and it grays out the "best" print setting.  In short the only choice is NOT to use HP brand papers, or remove tray 2, print the business letters, and then remove the 8.5X11 HP Premium Paper, install envelopes, and print again.  Not what I had in mind.
    I've been in touch with HP as the printer is still under warranty.  They offered a replacement, that will have the same printer an utility problems, or to buy it back at $175.
    I bought the original printer for $249, tray 2 for $125, and 5 XL print cartridges for $149.  That is a total of $588.  If I sell it back to HP check out the cost per page.  At $588 - $175 = $413/2742 total pages = 15 cents a page!  Owch!!!
    There is nothing wrong with the printer as such.  The problem is the HP Utility and Driver.  When did HP stop using a traditional warranty, and give pennies on the dollar, when they clearly have a software problem, they refuse to fix?

    Hi there @Oceankey , welcome to the forums
    I understand your Officejet 8600 is no longer copying an entire page from the scanner bed.
    I am unsure of which troubleshooting steps you have tried for this problem however, I would suggest updating the firmware (if needed), power resetting the printer and to ensure the printer is plugged in directly to the wall outlet, avoiding power bars and surge protectors. This ensures the printer is receiving full power and may help greatly.
    Getting the Latest Firmware and Product Updates
    Press the Power button to turn on the product.
    With the product turned on, disconnect the power cord from the rear of the product.
    Unplug the power cord from the wall outlet.
    Wait at least 15 seconds.
    Plug the power cord back into the wall outlet.
    Reconnect the power cord to the rear of the product.
    If the product does not turn on by itself, press the Power button to turn it on.
    If the troubleshooting does not help resolve your issue, I would then suggest calling HP's Technical Support to see about further options for you. If you are calling within North America, the number is 1-800-474-6836 and for all other regions: click here.
    Have a wonderful day
    R a i n b o w 7000I work on behalf of HP
    Click the “Kudos Thumbs Up" at the bottom of this post to say
    “Thanks” for helping!
    Click “Accept as Solution” if you feel my post solved your issue, it will help others find the solution!

  • Order cost plan in report CN41N

    Hi Gurus,
    Would appreciate if any one of share what is  'Order Cost Plan" in report CN41N.
    Infact, the values displayed in Order cost plan column neither coincide with either Project Cost Plan nor Actual cost displayed.
    Looking forward to hear and thaks in advnace.
    Thanks,
    PSR

    Hi PSR,
    Order Cost Plan in CN41N is PM Order Plan Costs figure.
    If you create PM Order and assign WBS Element/Project Def in Additional Data Tab of PM Order after planning Material services system will consider WBSE as Costing object and Plan and Post cost on WBSE. It will appears in CN41N in Order Cost Plan column.
    Please check
    Hope this will help you.
    Regards,
    Swapnil Kharul.

  • Key figures in Cost elemnt based report

    Dear All,
    I have created a Cost Element based Report for the Project using report painter. In this same report, I want to pull a key figure(the key figure is 'remaining forecast planned costs") which is coming from cost forecasting report (Report 12CTC1 from transaction CJE0).
    The issue is this 'key figure' is not available for report made in report group 6P3(report group for cost element based report). Is there anyway I can pull this particular key figure in my report.
    Thanks in advance !
    Regards,
    Mahendra Dighe

    Also if you're using HR data, the employee data is time dependent, so that for each employee number there are any number of records. This may be causing the aggregate reporting condition that you mentioned. In BW it's important to recognize that the master data also can play a role in how many records are returned. The infoprovider is not the only source of additional records. For example:
    Employee has three records in the time range.
    Salary infoprovider has only one.
    Results will contain THREE records, one for each employee record, all with the same salary record. On an aggregate basis, the salary results will be multiplied by three.
    Time dependent master data can be a source of much confusion. For some HR reporting, I have created a 'most current' employee master data record that is not time dependent, and is loaded daily. I then use that for data models such as salary or other separate infoproviders.

  • Key figures in cost element based report

    Dear All,
      I have created a Cost Element based Report for the Project using report painter. In this same report, I want to pull a key figure(the key figure is 'remaining forecast planned costs") which is coming from cost forecasting report (Report 12CTC1 from transaction CJE0).
      The issue is this 'key figure' is not available for report made in report group 6P3(report group for cost element based report). Is there anyway I can pull this particular key figure in my report.
      Thanks in advance !
    Regards,
    Mahendra Dighe

    Also if you're using HR data, the employee data is time dependent, so that for each employee number there are any number of records. This may be causing the aggregate reporting condition that you mentioned. In BW it's important to recognize that the master data also can play a role in how many records are returned. The infoprovider is not the only source of additional records. For example:
    Employee has three records in the time range.
    Salary infoprovider has only one.
    Results will contain THREE records, one for each employee record, all with the same salary record. On an aggregate basis, the salary results will be multiplied by three.
    Time dependent master data can be a source of much confusion. For some HR reporting, I have created a 'most current' employee master data record that is not time dependent, and is loaded daily. I then use that for data models such as salary or other separate infoproviders.

  • Vendor - asset - cost center wise report

    Hi Friends.
    Good morning,
    Please let me know vendor,asset  and cost center wise report ( ie for all vendors at a time.)
    Regards
    Srini

    Hi,
    From T.Code: AR02 you will derive your expected report.
    for vendor select dynamic selection and select ORIGN DATA Tab here you will get vendor field.