Cost plus and fixed cost project

Project Experts,
I have business requirements to create two projects first with fixed price and second with cost plus. Has any one did this and would like to share there expertise would be great.
Here are details.
For cost plus the business need is to create a project with transactions that applied a markup over the cost percentage. Any one did this do you know how you applied mark up over the cost %
For Fixed cost create a project with transactions that will create an automatic (additional line) with flat fees?
Many thanks in advanced for your time
Aijaz

Hi
I'm not sure I understood the exact requirements.
Anyhow, you could bill and generate revenue for a project based on the project expenditures. Setup the distribution method as WORK. You need to setup the bill rates for labor and bill rates for non labor resources. If you setup the bill rate for non-labor as 5%, the system will apply an additional amount of 5% to the costs of project non-labor expenditures. You could also use the burden schedule to apply a percentage of markup on labor and non labor expenditures. In any of those alternative you invoice will include lines which summarize the RDLs. The amount of each RDL us the calulated billing amount which include the raw cost with the additional markup.
Your additional alternative for billing and revenue is using events, which could be automatic or manually entered. Automatic events are calculated and generated based on the custom logic you might develop using billing extension. You could use that method to generate a fix amount event for the project invoice / revenue. Each event will be included as additional line in the invoice. Note, if you invoice should include the amount of expenditures and additional event based events, the distribution rule should be WORK. If you only need to bill the events, without the RDL's of expenditure items, setup the project for revenue and invoice method as Event.
Dina

Similar Messages

  • Material cost estimate and mateiral cost estimate with quantity structure

    Hi sap guys,
    What is the difference between material cost estimate and material cost estimate with quantity structure

    Hi
    Both are in one way the same.
    Material cost estimate can be calculated as
    1. Material with quantity structure
    2. Material without quantity structure
    You can get more insight into it at the following link
    http://help.sap.com/saphelp_47x200/helpdata/en/7e/cb938143a311d189ee0000e81ddfac/frameset.htm
    Regards,
    Suraj

  • Costing run and premilinary cost estimate

    Dear All,
    Is it possible to run cost estimate and premilinary cost estimate for a product cost collector back dated.  I mean for 01.03.2007. I know  it is not possible. But anyother way out.
    ranga

    Hi Rangarajan
    I think it is possible in future date and not backwards.
    Thanks
    Ashok
    Assign points for useful answer

  • Defferece between cost centre and Master Cost Centre

    Can any body explain defferece between cost centre and Master Cost Centre.
    Appreciate your help.
    Kavitha

    Hi kavitha
                     I dont think there is difference between Cost centre and master Cost Centre.
    It may be Possible that under Cost Centre Hirarchy One Cost Centre is at Top node and other is Child of that Cost Centre.
    Thank YOu.
    Thank YOU.

  • Activity Allocation - Split of costs between variable and fixed costs

    Hi,
    The business is very keen on contribution analysis. Therefore all costs (cost elements) are broken up as fixed and variable.
    I have a utility cost center (boiler) which incurs both fixed and variable costs. The cost center produces STEAM (created as an activity type). The steam consumption at the process order level cannot be entered. Therefore the production cost centers contain only MHR (machine hour) as their activity. Morover because the business wants to look at costs by production process each production cost center provides a different MHR activity type.
    When I compute the activity rate at the boiler cost center for steam, the system correctly breaks up the rate as fixed  and variable. Now, when I try to do an activity allocation (KSCB) from boiler to the production cost centers, the entire costs are being treated as fixed.

    Hi,
    check SAPNET note 541858, this describes the system behaviour regarding fix/variable cost when KSCB is executed.
    Best regards, Christian

  • Variable Cost And Fix Cost Planning

    What are the settings and are they in Product Costing sub module to be able to clearly see the difference in movement of fixed and variable costs for the activity types in the cost of a product. (Product Cost with quatitiy structure CK11N)
    At present, in our settings, even though we have broken the rates as fixed and variable for the actitiy types in cost center planning, there is absolutely no impact in product cost for this. All costs move like variable costs.
    Best Regards.

    Check in Cost component structure for cost component for the attributes.
    For Activity cost type attribute you must select the control parameter as fixed and variable costs radio button.
    Laxmiprasad

  • Costing sheet and standard cost estimate

    Hi
    I am trying to use Costing sheet for overhead calculation .
    But in costing run I am not getting the overhead amount calculated .
    I created the costing sheet and assigned that to valuation variant .
    Where from the actual / Plan values being picked up for over head calculation .
    More over I need to understand on what basis the %age for overhead can be calculted to be aborbed to material cost .
    In costing run I am having ZERO values for overhead .
    I have followed the following steps
    Costing Sheet: Components
    Define Calculation Bases
    Define Percentage Overhead Rates
    Define Quantity-Based Overhead Rates
    Define Credits
    Define Overhead Keys
    Define Overhead Groups
    Even then the Production overhead is not being calculated at the time of Cost Run
    for standard cost estimate .
    regards

    Do you enter overhead  group in the material master.
    Key that groups together materials to which the same overhead is applied.
    Procedure
    In costing with and without quantity structure, and when costing production orders and run schedule headers, you can apply percentage overhead charges by means of an overhead key if you:
    Assign a costing sheet to your production order or run schedule header, or to the valuation variant for the cost estimate
    Enter overhead charges in this costing sheet that use the overhead key field
    Assign the overhead key to an overhead group
    Enter this overhead group in the material master record of the material

  • K/834 no standard cost estimate and ke435 costing key 000 does not exist

    Hi ,
    scenario as under we have following type of materials
    normal Material that has cost estimate
    Configuarable material
    Material without cost estimate -prices are updated thru MR21 (as some legacy system calculated the price)
    There are many company codes and use one or more above  category of material. further we have common Material type and valuation class.
    we need cost component split to get updated in COPA and for that i create 2 costing key one for normal and other for normal one and developed an enhancement (KEPC) that check whether material is configurable or not. based on that it assign 001 or 002 costing key
    it went well but failed for material that has no cost estimate and got error K/834.
    To tackle same we insert further logic to check for normal material whether cost estimate exist, if yes then assign costing key 001 else ignore it. configurable material logic remain as it is. it working fine for normal and Configuarable material but normal material without cost estimate resulted in error KE435.
    need to know:
    -at first place why system  generates K/834 error for enhancement - earlier we were using assignment rule (KEPC) where we use valuation class and assigned costing key 001, it worked for normal one and ignore configurable one and normal material without cost estimate. I haven't changed costing key rule and exclusive error is not marked .
    - any other way to tackle besides resetting message class from error to warning or changing Materila type or valuation class as that is not acceptable due to other complexity.
    Regards,
    Atul

    Hi,
    It resolved thru enhancement
    Regards,
    Atu

  • Costing BOM and Mixed Costing

    A product which is manufactured in-house has more than one production version.  Each production version has its own BOM and Recipe.  To calculate a blended standard cost, we will use mixed costing functionality and assign ratio to each production version.  However we want to copy the BOM usage 1 (production) to BOM usage 6 (costing) and make changes only for costing purpose.
    Hence each production version will have a BOM for production and equivalent BOM for Costing as follows:
    Production Version/Procurement alternative
    BOM for Production
    BOM for Costing
    1
    Usage 1 / Alternative 1
    Usage 6 / Alternative 1
    2
    Usage 1 / Alternative 2
    Usage 6 / Alternative 2
    If a process order is created with Usage 1 /Alternative 1, how does the system know to compare actual cost with procurement alternative with Usage 6 / Alternative 1 for the purpose of variance calculation?
    Thank you,
    Siva

    Hi
    Welcome to SDN
    You dont have  option to specify the Valuation type in BOM i.e. in the BOM of B, you can only specify A as the Input material... You cant specify C1 or C2
    Hence, as a result, costing uses only the average price of C1 and C2 which is maintained in the Mat Master as a PLanned price
    MIxed Costing as well as Split Valuation for Material B makes no sense in this case....
    If you still want to have Mixed Costing & Splt Valuation in this case - You need to create one more material for Mat A i.e. Separate Mat codes for C1 and C2.. however, it will have its own challenges during MRP as to which material should be ordered, etc
    br, Ajay M

  • Difference between master cost centre and sender cost centre

    Hi All,
    could you please tell the difference between master and sender cost centre.
    I want this information very urgent.
    Thanks rakesh

    Hi!
    The master CT is a default Ct in your system.
    In this case the logical pair for master is the "child" cost center -> primary and secondary cost centers..
    The sender CT is a different thing logically -> this will be credited while posting. The sender is the one who claims money.
    To this type the logical pair is the receiver cost center. While posting the receivers cost center will be debited.
    Hope this helps!
    Best regards,
    Zsolt

  • Cost Updating and Standardized cost difference apportion

    Dear All,
    1、 Cost updating:Standardized cost or average cost change is updated across all sub-inventory simultaneously, but the update should exclude the inventory that lends stocks (we do not want to update the cost of lending stock).
    2、Standardized cost difference apportion:Standardized cost difference apportion is operated manually without system support (we want to do the apportion when stocks are delivered).
    I am stuck up with these question ..
    please let me know the solution or the workaround to achive this
    Appriciate your help
    Thanks
    Satyam

    Hi Abhishek,
    Further to discussion on the subject,
    Find enclosed link which elaborates the accounting
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/08/513e4243b511d182b30000e829fbfe/frameset.htm
    In a nut shell u can consider that cost elemnts are providing u the documentation  for Financial reporting & legal entries of a company.
    Cost centres are cost collectors for different expense/revenues generated within the organisation with repsct to controlling part (Internal documenation) of the compny for better controlling the business scenarios.
    Further cost centres are used for product costing.
    Ramesh

  • Cost Center and res cost center

    Hi team,
    When i am going to settle the cost of PM Order , COst center pick from Equipment sonly. Then what is the use of assignemnt of cost center in work center.
    thanx in advance

    Hi,
    How do I call you? SAPPM is not appropriate!...
    You are attaching one cost center to your work center that supplies required resources (activity types) to perform the maintenance - in IR01. That cost center is to maintain the rate of the resource (Activity types) ie. Rs.500 / Hr or day - in KP26.
    Whenever you are utilizing a resource from a work center, system refers the cost center / activity type combination to determine the cost. Based on no. of hours or days utilization, the planned cost / actual cost are determined from the Wctr, Cctr, Acttypes.
    These are so called Source of cost center.
    After completing the order, the cost incurred are with the maint. order. Now we need to settle to a cost object, it may be a cost center / WBS / Contract / PSEG etc.. depends on your business requirement. You may use a cost center as a Cost receiver / cost object to observe your maintenance cost of an Equipment / Func loc / or its group.
    As a whole, the work center / cost center is used to determine the cost (Source). Equipment cost center observe the cost of maintenance(receiver).
    Hope this description gives required clarification . If not, Revert back.
    Babu

  • Retraction of Cost center Costs- Primary and seocndary cost.

    Hi ALL,
    I've configured the cost center retractor for cot elements, and it works fine.
    However, I've noticed that it does NOT retract the secondary costs from BI to ECC.
    Is that the way it's supposed to work? How can I can get it to retract secondary cost element costs from BI back to ECC.
    Thanks

    Hi,
    Either IP or BPS will not support retraction of secondary costs.
    Please refer
    For BPS
    http://help.sap.com/saphelp_sem320bw/helpdata/en/99/97157967e3440a94d199538959cd0b/content.htm
    Retractors
    In BI Integrated Planning, no new retractors are shipped.
    In BI Integrated Planning, you can only use some of the retractors that are used in BW-BPS: you can use any retractors that work according to the pull principle (COPA and Public Sector) without changing them. Other retractors cannot be used directly in BI Integrated Planning; retraction is only possible using BW-BPS.
    Regards,
    Ravi

  • Archiving cost centre and product costing

    Dear Experts,
    we are going to implement for our client archiving the controlling data.
    so I am looking for material and expertise views and advises to proceed further.
    so can you help me that where do I start in this reagard.
    Thank you for your help
    thanks,
    Anil

    hi
    you can get the best practices for COPA from help.sap.com select the best practices and select the country and it will give you the building block

  • Product Costs Split is required, that is fixed and Variable costs

    Hi All,
    In a Sales Order screen (VA03), if we check the Costing, by clicking on EXTRAS -> COSTING, we get Total Costs, Fixed Costs  and Variable Costs.
    Can someone please help me in getting these costs, I have used Table KEKO,
    In KEKO (filtered based on Material, Plant, Sales Document, Item) and executed it, taken the resultant ProdCstgNo (KALNR)
    In KEPH used that KALNR, as a result I am getting 4 records, However 2 records are not correct, and 2 are correct. 
    In correct ones I have to add few costs to get FIXED COSTS and few costs to get VARIABLE COSTS.
    My question is, which filter should I use to get the correct record (probably just one record) ?
    Can I in some table get the summed up VARIABLE COSTS and FIXED COSTS, rather that I have to add them seperately ?
    Please help, will award points promptly. Thanks

    Hi,
    In KEKO (filtered based on Material, Plant, Sales Document, Item) and executed it, taken the resultantProdCstgNo (KALNR)
    In KEPH used that KALNR, as a result I am getting 4 records, However 2 records are not correct, and 2 are correct.
    The table you mentioned CKMLKEPH is used for Material Ledger actual cost components.
    Regd,
    Khan.

Maybe you are looking for