Any one can let me know how to update the cost price for the particular material
i tried in CK 11 N and CK24
Thanks
Guru

Hi,
When you run the standard cost of a material for particular plant (T Code CK11N) , ensure that material is costed without errors. When material is costed without error, save the standard cost. Once the standard cost is saved, go to CK24. Enter the material number, plant and company code. Click on marking. On doing the same, it will take you to different screen where you have to activate the company code. On activation, it will display the green light for the same that company code. Come back and uncheck the test box and execute. This will do the marking of the std cost in material master as future price. After doing the marking, you have to click on release button and then execute. This will release the future price to current price in material master.
Do remember, release will happen only if the std cost run is for the current date means, validity of STD Cost is from the date when you release. in case it is for future date, release will be done on that particular date and not in advance.
Hope this may help.
Rewards points if helpful.
Regards,
Harish

Similar Messages

  • Transfer cost price from free of charge item to main item but not for VPRS

    Hi,
    I want to transfer cost price from free of charge item to main item but not for VPRS but for a new Z contidion type.
    For CO-PA proposes. Can you help me with This?
    Catarina Alves

    hi,
    transfer of cost from sub item to main item is configured in the delivery to billing copy control for the main item. go to VTFL  > select the required item cateogry > here at the bottom you will find a check box Cummulate cost. Tick it.
    Not really what you meant COPA purposes. But the pricing conditions are mapped to COPA value fields at KE4I transaction.
    regards
    sadhu kishore

  • Material cost / Price on sales order ?

    Do we get the material Cost / Price (Vendor Material price ) on sales Order ?
    I means can we see the material Cost and Material Sales price in Sales order ?
    Hope my question clear .

    Hi -
          Please follow above answer and ignore my reply. 
    Thanks!
    Anesh B
    Edited by: Anesh B on Oct 7, 2009 4:28 PM

  • Is it possible change cost price when poss goods issue?

    Hi experts,
    I create a return sales order,then create delivery and post goods receipt,it generate a accounting document,the cost price take from material standard cost, is it possible change the cost price before post goods receipt.
    thanks.
    lance

    Dear anand,
    I have tried what you said,but it seam not in use.The VPRS in the delivery is 10, MAP in material is 12, after PGR the price in the accounting document is also 12, But I want the price in the accounting document is 10.
    Could you tell me is there any mistake.
    thanks.
    Lance.

  • VPRS - Cost price from sales to billing not valuation record

    Hi,
    I need to get the cost to flow from the sales document to the billing document for the cost price.
    We allow selected users to change the cost price at the time of the sales order. But when I create a billing document the moving average price is determined and not the cost price on the sales order.
    In copy control pricing is 'G' and price source is order.
    Is there a way around this via configuration ?

    Dear Javaid
    Can you confirm that the sale order quantity and the billing quantity are same.  In most of the cases, these would be different and hence the cost also.
    Meanwhile, in V/06, for this condition type VPRS, ensure that the Calculation Type is "C"
    thanks
    G. Lakshmipathi

  • Cost Price for Returns order adopting cost from preceding billing doc

    Hi Forum Experts,
    Our Returns Order (SO) currently obtains cost price (VPRS) based on material moving average price.
    However, what we really need is to copy the cost price from the preceding Billing Document.
    I've explored using VOFM and created a routine under (Formulas --> Condition Value) as per below.
    I found that while the debugger steps through this code, the value of the cost gets copied from the preceding document.
    However, immediately after the code finishes execution, the value gets resetted back to the material moving average price again.
    What can I do do let the system keep the copied cost price from the preceding document instead?
    FORM FRM_KONDI_WERT_998.
    DATA: lv_kbetr TYPE kbetr,
          ls_vbfa  TYPE vbfa,
          lv_knumv TYPE knumv.
    IF SY-TCODE = 'VA01' OR SY-TCODE = 'VA02' OR
           SY-TCODE = 'VA21' OR SY-TCODE = 'VA22'.
    IF xkomv-kschl EQ 'VPRS'.
    Get billing doc and position
    SELECT SINGLE vbelv posnv
    INTO corresponding fields of ls_vbfa
    FROM vbfa
    WHERE vbeln EQ komp-aubel "returns order number
    AND posnn EQ komp-aupos "returns order item
    AND vbtyp_n EQ 'H' "returns order
    AND vbtyp_v EQ 'M'. "invoice
    IF sy-subrc EQ 0.
    Get billing doc conditions key
    SELECT SINGLE knumv
    INTO lv_knumv
    FROM vbrk
    WHERE vbeln EQ ls_vbfa-vbelv.
    IF sy-subrc EQ 0.
    Get moving average price from billing doc conditions
    SELECT SINGLE kbetr
    INTO lv_kbetr
    FROM konv
    WHERE knumv EQ lv_knumv
    AND kposn EQ ls_vbfa-posnv
    AND kschl EQ 'VPRS'.
    IF sy-subrc EQ 0.
    Recalculate condition values
    xkomv-kbetr = lv_kbetr.
    xkomv-kwert = lv_kbetr.
    xkwert = xkomv-kwert.
    ENDIF.
    ENDIF.
    ENDIF.
    ENDIF.
    ENDIF.
    ENDFORM.
    Regards,
    Edric

    Hi,
    If you bring the Freight condition after PBXX and include in the net value, your problem will be solved.  so it will be 120 in MIGO, MIRO, Dellivery and VPRS in billing.
    We have the same situation and its working fine for us. 
    Thanks
    Krishna.

  • Is there any standard report available to show cost prices from infor recor

    Hi
    Can any one tell help me is there any possiblility to make a report showing cost prices from info-records on purchasing org. level incl. prices scales?
    We need a report showing the following:
    Supplier no.
    Supplier name
    Material no.
    Material name
    Price
    Price scales (if registred in the info-record)
    Purchase organization to be showed
    Selection of the report can be done with the following entries:
    Supplier no.
    Sourcing (material group)
    Purchase organization
    Please be informed that the above mentioned information and selections are just my first and best guess.
    We have tried to use transaction MC$4 - however, this one is only showing the purchased quantity in the period selected.
    There must be a standard transaction in SAP R/3, which can show us the prices from info-records.
    Best Regards,
    Sairam.

    Hi!
    ME1P is the best report for you although it lacked the supplier name, material name and price scales. You can ask your ABAPER to create your desired report by copying the program running ME1P and then creating a Z* report which contains all your desired fields.
    Hope this helps! =)

  • Cost price calculation of raw material

    I want to know how cost price of raw material is calculated in sap.  Is it when ever price changes we have to go to each material code and change the price  or we can have our own policy?
    Edited by: gururaj gadgoli on Sep 18, 2008 1:05 PM

    Dear,
    For Raw material costing please have a look at :
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/b8/9c76a0c89c11d189990000e8214595/content.htm
    and also
    http://www.sap-basis-abap.com/sapcostd.htm
    http://www.sap-img.com/materials/price-control-v-or-s-in-material-type.htm
    Regards,
    Syed Hussain.

  • Cost Price Calculation

    Hello Gurus,
    How to calculate the cost price of an Article in Retail, how does the system calculate it?
    I did try looking for SAP note for help. However I couldnu2019t find one. Would appreciate your responses. 
    Thank you for your time in advance.
    Regards,
    Gareth.

    Hi Gareth,
    If by cost you mean the moving average price the system deos the calculation as mentioned below
    MAP = (Current stock value + Receipted stock value) / (Current stock quantity + Receipted stock quantity).
    For e.g. if you had 5 quantities of material X with unit price as $10 your current stock value is $50.
    now if you take a GR 10 quantities of the same material wih unit price $15 your receipted stock value will be $150.
    The MAP in this case will be: (50150) / (510) which is $13.33.
    Regards
    Kaizad

  • Cost price Problem for repair FG.

    hi,
    Business scierio-
    Mat "A' Done GR aginst Production order, Now the Same FG undergone the repair, we use to do Creating New FG Mat "B" and making old FG (mat "A") as a component of Mat "B" .
    Note- for every FG we having the BOM (universal).
    Now the Problem is- Components used in Mat "A" having Valution is MAP (CP), but the FG Valuation is Standard price (Selling Price).
    During issue of Mat "A" to floor the selling price get updating in the cost price GL account During repair process.
    What should i do to get the actual Cost price for Mat B.
    Is it require to change the valuation of the Old FG i,e Mat "A" in to actual Cost Price before issuing to floor?
    Waiting for reply
    Veera.

    While creating cost estimate with Qty Structure, first BOM is exploded by the system & prices are picked up from material master as per this sequence.
    Ideally, the 1st preference should  be - valuation according to price control in MM.
    so that if a material is valued at MAP, it's MAP will be picked up for costing & if valued at Std Price, it's std price will be picked up.
    In your case 1st it will check for Planned Price 1. If the system finds a value in the Planned price 1 field (costing view), this value is taken as the value for valuating the material & so on.
    Regards,
    Amol

  • Cost/Price diffrences posting (PRD)

    Dear ALL,
    I am facing the issue in (PRD)Cost price diffrence account postings.
    In Article Master (Retail) using Moving avg price while doing GR price diffrence posting to PRD account due to negative stock indicator in Article master.
    Ex : In Article master having negative quantity 1 at MAP 10.
    Now i am procurring 2 qty at MAP 20 with purchase record. while doing GR for  the qty 2 system calculating for 1 qty at 20  and 1 qty calculating 10 at old MAP  diffrence 10 rupees posting to PRD account .
    This is wrong this needs to go Inventory but it is going to PRD, please let me know how to avoid this with out unchecking negtive qty in Article master. 
    Please respond
    Cheer's
    Ram
    Edited by: Ram on Mar 19, 2010 11:02 AM
    Edited by: Ram on Mar 19, 2010 11:07 AM
    Edited by: Ram on Mar 24, 2010 4:39 PM

    Hi,
    Check your settings in OBYC.
    Regards,
    Mohan.

  • Cost price update

    Hi guys
    i have a problem in updating cost price for all finished goods
    we set in MM for all Raw Materials, process chemcials and packaging materials as moving average price and semi and finished goods  items as standard
    our raw material and packaging items changes prices once in a month based on international market prices. when we started SAP we updated these items prices and that price showing standard price field.
    now when i updated FG cost price it is taking standard price cost for BOM and updating cost price and is not giving accurate costing. everymonth cost price is same since it is not taking moving average field price which is correct one
    so guide me everymonth how to replace standard price field with moving average price field in MM so that cost price of the finished product will be accurate
    total items are more than 4000 so please do not guide me to change manually by using MR21
    Regards
    Ved sai dut

    Hi Ved,
    Please check the priority of strategy sequence in the Valuation variant assigned to your Costing variant in Tcode OKKN. The first priority might have been set to standard price.  So, Change it to 'Moving average price' and the system will read the prices in the Moving average price field in the material master.
    You DO NOT have to use MR21 or change any material prices or use material ledger. If you set the priority to moving average price, the system  automatically reads those prices in the BOM items while costing.
    Hope this should resolve your issue.
    Regards,
    Vishnu.

  • In Which table  Cost Price of Items stored  in SAP?

    Hi Friends,
    I am extracting Items details using DI API.
    I want the cost price of items purchased? In which table
    the cost Prices stored? And What is the Price which is
    displayed in SAP B1 Item master data?

    Hi Sooriya,
    There are three calculation metods in SBO.
    You find Basic Init. under menu Administration | System Init...
    1. Moving avarage
    2. Standard
    3. FIFO
    If I understand you correctly - you need to find costprice per item in stock.
    I think there is not such possibility - The only way to find such link between Sales Order/Purchase Order is that user generate PO when creating SO. This way Base/Target document link is established. You need to make a join query of Sales Order/Purchase Order to find the linked costprice of the item.
    Value AvgPrice in item wareh.table is only a calculated or fixed value.
    Hope this helps something.
    -Regards,
    Geir

  • Cost price differences in subcontracting PO's invoicing

    Hello,
    Which transaction key (of automatic postings) will be used by the system if I create an invoice for a subcontacting PO for a bigger value (in price) than the receipted?
    Is it allways the PRD (Cost (Price) differences)? If not, on what does it depend?
    Thanks!

    Hello,
    Thanks for all your replies (even if they were not 100% helpfull).
    My problem is exactly the following:
    For subcontrating PO's we have a price condition which imputates a % of the total cost to an account which will be payed to the carrier (this works perfectly) for the freight.
    The problem is that if we try to invoice this document (which is not against the vendor of the PO but against a vendor which is the carrier) for more value than the expected then the Price Difference is not charged against any account! (the warning of the price tollerance is showed but the system doesn't know were to charge this difference).
    Please help!
    Thanks!!

  • Cost & Price Calulation in decimal

    Hi Expert!!
    We want to maintain & calculate the cost / price in 3 to 4 decimal for the MM module the other module will maintain the 2 decimal, the solution will be only MM module without interrupting the other module configuration which are maintaining the 2 decimal.
    Please provide the possible solution of above issue.
    Regards
    Anwer Waseem
    SAP BASIS

    Hello,
    Thanks for all your replies (even if they were not 100% helpfull).
    My problem is exactly the following:
    For subcontrating PO's we have a price condition which imputates a % of the total cost to an account which will be payed to the carrier (this works perfectly) for the freight.
    The problem is that if we try to invoice this document (which is not against the vendor of the PO but against a vendor which is the carrier) for more value than the expected then the Price Difference is not charged against any account! (the warning of the price tollerance is showed but the system doesn't know were to charge this difference).
    Please help!