Cost-reducing revenues

Hi,
1 Can have example of Cost-reducing revenues cost element?
2 what is the difference between cost reducing revenue element and revenue element? i know cost reducing revenue is category 1 whereas revenue is category 11 but i do not know what is the difference between them.
3 as category 1 is both primary cost and cost reducing revenue, so how can i know the posting is primary cost or cost reducing revenue?
thanks

Primary cost = Cost Element (Category 01) =It is a Business Cost (Purchase of Raw Materials,Salraies paid to employees)
Revenue element( Category 11) = It is a Business Revenue ( Sale of Finished Goods,Trading Goods etc.,)
Other Income is also Revenue element.(Category 11) = Rent received ( which is not reducing business cost)
Where as Cost reducing revenues (Category = 01) is the revenue which reduces the business cost (Discount received on Purchases, Discount received on early payment made to Vendors etc.,)
Srinivas

Similar Messages

  • Settlement of Project Cost and revenue to GL

    I am trying to Settle the project Cost and Revenue to GL account. For the same I have defined settlement profile maintaining GL as optional receiver and then I have maintained Source structure for cost and revenue as to separate them at the time of defining settlement rule, defined Allocation structure where in receiver against source, I have assigned GL as by cost element receiver. After that I have maintained settlement rule for WBS element, but when I am running a settlement is done to either of the GL for cost or Revenue which ever is defined first in settlement rule. It is not creating any settlement for second line item of the settlement rule and system is not giving any error message as well.
    Where as if I am trying individually only for cost or revenue , settlement is completed with all the values but with any accounting document generated, but if I see the entries to that GL, a settlement entry is created for that transaction.
    Can anyone please help in solving this issue ASAP.
    Thanks and Regards

    Hi,
        If it is posting to the first line means....
    Follow the steps below:
    First try to create a project and post the actuals and revenues.
    Go to cost element report pick up those cost elements both for costs and revenues.
    Go to Soruce Structure in the config, define the structure with name for Ex: 'Z1' and define two assignments, one is Costs and other Revenue, by selecting the costs go to Source mention the cost element where the actual costs are posted on (Mention only that cost element no other cost elements), next select the Revenue assignment and click on Source and mention the only cost element where the revenue wsa posted (Mention only that revenue cost element no other cost elements) and save the transaction.
    Come back to project builder, select the wbs and click on settlement rule, in the menu goto-->settlement parameters and check whether the source and settlement profiles are correct or not, incase source structure is not available mention the same.
    come back to settlement Rule overview and fill the fields as mentioned below:
    1st line:   Category: GL
                  GL Account: GL Account Number
                  Source Structure: COSTS
    2nd Line: Category: GL
                  GL Account: GL Account Number (Revenue Account)
                  Source Structure: REVENUE.
    Now Run the Settlement for the specific period costs posted, the costs will be posted seperately to the two different GL Accounts.
    I think this will resolve your problem.
    Rgds
    Sudhir Reddy

  • Cost and Revenue of Internal Order

    Hi
    The table for internal order master data is AUFK
    but when we assign internal order to sales order and subsequently revenue and cost are booked ,it is accumulated in the same internal order
    In which table do we find the actual cost and revenue for  the internal order
    Thanks and Regards
    Sunil

    hi..
      For internal order level expenses elementwise please use table COEP. Earlier one i mentioned for Material Ledger related cost componant split.
      thanks
      kkumar

  • Project Management -Automatic process to approve Forecast Cost and Revenue?

    Hello,
    If anyone can help me with this it would be greatly appreciated.
    Due to our business requirements, we have to run the "PRC: Generate Financial Plan Amounts" program every week for 40-50 projects.
    The issue with this is that after running this program we have to manually go into each project and approve the latest cost and revenue versions. Is there a program or an api that I can use to automatically approve these projects without going into each project and manually update them?
    Thank you in advanced.

    Hello,
    I found a way to approve the budget costs and revenues using the PA Budget workflow. In order to kick off this workflow I still have to submit the budget costs or revenue. Is there anyway I can by pass this submission process? Is there an api I can use to submit the latest budget costs so it will kick off the workflow?
    Thanks
    -Nelly

  • Costs and revenues for service contracts

    Hello,
    Does anyone know a transaction where you can retreive a simple overview of the costs and revenues for contracts (contract type WV Service and Maint.)? Within transaction VA43 there is a cost report but that report only lists only the data of the processed contract.
    Sebastiaan Bakker

    Hi,
    Check out the following site for your querry.
    http://help.sap.com/saphelp_nw04/helpdata/en/3c/aba8e6413911d1893d0000e8323c4f/frameset.htm
    regards,
    Siddharth.

  • Service Order Costs and Revenue

    Hi,
    Can you please let me know how to find costs and revenue related to service orders?
    what tables to go to?
    Thanks,
    MS

    Hi Mahesh,
    Thank you very much for that quick response.
    EKKO is for purchasing documents. Can you please let me know how to use it for my service order?
    Thanks,
    Maulik Shah

  • Actual Cost & Actual Revenue

    Dear Sir,
    Can you please tell me what Actual Cost & Actual Revenue & also what is difference between Actual cost & Actual Revenue.
    Regards,
    Gagandeep Singh.

    Hi,
    IN any project you incur some expenses and at the same time when you sell something you generate revenue. But in the intitial stages you cant say what is the actual cost that you are going to incur or what is the actual revenue you are going to generate at a certain point/phase in a project.
    Actual Cost refers to for eg. suppose you procure a bearing for your project. You will create a PR and then a PO. Until this stage system will treat this as a commitment. Once you do the GR/ GI this cost is converted to actual cost. Similarly lets say that you are building a ship and you have procured some components to build that ship. That procurement will lead to a cost because you are incurring some expenditures. Once you build that ship and sell it and bill the customer you will generate revenue. Till the time you receive the payment/revenue from your customer system treats this as Planned revenue. Once you bill your customer and receive the payment system will treat this is as the actual revenue.
    So basically Actual Cost refers to the expenditures incurred in carrying out a project and Actual revenue refers to the income generated after billing the customer and receiving the payment for the goods sold.
    Its just a basic explanation but hope this clears your query.
    Best Regards,
    Gokul

  • Planned cost and revenue changes

    Hi,
    Upto which event we can change planned costs & revenue?
    How to track planned cost and revenue changes?
    Thanks!

    Hello Harsh,
    The planned cost and Revenues can be changed during any phase of the project. As far as monitoring goes you can create versions (snap shots) each time when you change the planning. You can use s_alr reports to compare 2 different versions.
    On costing side you can use supplement budget or return functionality. You can use tcode CJ3A or CJ3B to chk the Budget document.
    Hope this helps.
    Sarang

  • Service Order Actual costs and revenue

    Hi,
    Can you please let me know how to find actual costs and revenue related to service orders?
    what tables to go to?
    We are planning on going back to a service order from the billing document and get the actual labor costs.
    Thanks,
    MS

    Hi Mahesh,
    Thank you very much for that quick response.
    EKKO is for purchasing documents. Can you please let me know how to use it for my service order?
    Thanks,
    Maulik Shah

  • Depreciation cost to revenue

    Hi All,
    How to transfer the depreciation cost to revenue in the middle of the year???
    Regards

    Hi Siva,
    Please Have a look to these SAP documents: very useful they explain all.
    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/MYSAP/SR_CS.pdf
    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/CS/PMSMASC.pdf
    http://help.sap.com/saphelp_47x200/helpdata/en/31/03953401024735e10000009b38f83b/frameset.htm
    Please Reward If Really Helpful,
    Thanks and Regards,
    Sateesh.Kandula

  • Free of charge Item determination in SO with cost and revenue transfer

    Hi,
    Please guide me on the followings.
    I have a following requirement for determining the free goods in the sales order .We have two plants
    1.     Plant 1 is for valuated materials
    2.     Plant 2 is for Free of charge Items
    Free of charge items which are given to the customers are supplied by the vendors and stored in the plant meant for the Free of charges items. But sometimes when free of charge items are not available in the stock then user take FOC item from the plant which is meant for the valuated materials and send it to the customers as a free of charge item.
    User wants to transfer the cost of the FOC item to the main item when FOC material is taken from the valuated plant and sent to the customer.
    Similarly  when there is no stock of material in the valuated plant then user take the same material from the Plant2(Non-valuated) and send the material to the customer. In this case user wants to have the revenue posted in the respective  G/L  Account.
    But it should also appear as a free of charge items in the billing document.
    Regards
    Rahul

    hi,
    transfer of cost from sub item to main item is configured in the delivery to billing copy control for the main item. go to VTFL  > select the required item cateogry > here at the bottom you will find a check box Cummulate cost. Tick it.
    Not really what you meant COPA purposes. But the pricing conditions are mapped to COPA value fields at KE4I transaction.
    regards
    sadhu kishore

  • Report to see the actual cost and Revenue..

    Hi all,
    My Sales Cycle is Sales Order --> Delivery --> PGI --> Invoice --> and Accounting.
    When we do the PGI GOGS account entries will generate,
    When we do the Invoice Revenue and customer account entries will generate.
    Now my customer wants to see the total Actual cost as well as total revenues in a single report (Sales order wise).
    Is there any Standard report availble for this?????
    Thanks and Regards,
    SUBBU..

    Hi,
    You will have to use LIS and develop a std or flexible analysis to develop this report.
    Check the below links
    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/LOLIS/LOLIS.pdf
    http://help.sap.com/printdocu/core/print46c/en/data/pdf/LOLIS/LOLIS_KOMPONENTEN%20DES%20LIS.pdf
    Regards,
    Amit

  • Planned Cost & Planned revenue - Not displaying data in Bex.

    Hi BW Experts,
    I have installed 0PS_C04_Q002 query from the business Content and loaded the data for the Cube 0PS_C04.
    While executing the query, I am not getting data for Planned Cost and Planned revenue. I am getting data for Actual Cost and Actual revenue. As I am using standard restricted key figures, I am not getting the data. Can you please help on this Issue.
    Thanks in Advance.
    Thanks,
    Jelina.

    Hi Jelina,
    Is the load successful to the cube?
    Did u check the data in the cube?
    Is the data populated fine?
    Otherwise check the properties of Planned Cost and Planned Revenue by changing the Infoobjects. And check the lengths given and the datatypes. Compare them with the length and the datatypes of the fields u  are retrieving from your source system.
    Hope this helps u...
    Regards,
    KK.

  • Capture costs and revenues - WIP

    In CO module, we have a issue: manage all costs of sale project (Zeetech)
    For example: The customer has a building, then Zee will install the electric system, air condition systemu2026. The requirement of Zee that: they want to control both revenue and cost for each sale project.
    In SD module: they will create a sale order for a sale project. But in sale order, we only see the revenue.
    The cost account  include:  main material cost account, auxiliary material cost account, labor cost account, overhead cost account
    At the end of the period (monthly): we have 2 case
    ·         Case 1: The sale project finished: all cost account will be transferred to COGS account
    ·         Case 2: The sale project havenu2019t finished: a part of cost will be transferred to COGS, a part of cost will be transferred to work in process. In the next period, if  the sale project finished, we will transfer WIP to COGS
    We test the solution that use internal Order: all cost will be captured to IO. we can set the settlement rule in IO: settle from IO to SO, so in SO we can see both revenue and cost (COGS). But the COGS account and WIP account which we settle is secondary cost. So, after settling the accountant have to post transaction manually in FI module. This solution is OK in case 1. But in case 2 : we have a problem: settle cost to WIP, if in the period we have many sale project havenu2019t finished, we only use one WIP account. In the next period, have some project finished we donu2019t know which cost of which sale project need to be settled from WIP account to COGS account.
    So, if you have an other solution, please reply in the forum

    You can meet this requirement thru configuration of Results Analysis Key.
    Design the suitable RA key and assign RA key in Sales order master data.
    At period end , You have to run Tcode KKA3 - Results Analysis / WIP , for all Sales orders which are still open.

  • Cost & AR revenue problem

    Q1. my company is a marketing company ,finance dept. have  
          to place an invoice and bill  to department store every 3
          month ,but sales input sales orders into SAP system and
          post good issue everyday , cost account will be create
          when post good issue .how to put cost and A/R in the
          same month or balance both ,tks
    Q2. another one , goods will be delived to customer once , but 
          the payment are separated in different month ,for example
          7/1     sales order creation , 1000usd
          7/3     post good issue and create cost account
          7/20   payment 200 usd
          8/20   payment 500 usd
          9/20   payment 300 usd,
          How to balance between cost and A/R revenue
          thanks very much

    no answers