Costing varient/Activity types tab

hello gurus,
                in costing variant/activity types tab my strategy sequence is 1.plan price for the period and 2.actual price for the period.here my question is from where the system will pickup these prices.please explain this
thanks
rihana

Hi Samaar,
Based on this configuration, system will read the Planned Price or Actual Price of the Activity Types maintained in the recipe.
You can see these Planned Prices & Actual Prices of the Activity Types  using T-Code # KSBT
Regards,
Pandu

Similar Messages

  • Master record for cost center/activity type

    Hi all;
    How create a master record between an cost center and activity type?
    Thank you

    Hi
    You can create master data between cost center / activity type.
    You can link the two by planning for activity qty the combination of a cost center / activity type in KP26. Then you do a detailed planning for costs for the cost center / activity type / cost element in KP06.
    I hope it is clear..
    Regards,
    Suraj

  • Table for cost center / activity type prices

    Can someone give me the table name where cost center/activity type prices are stored?
    Regards,
    Manohar

    hi,
    for cost centers
    table name  =  CSKSZ
    field name =  KOSTL
    Activity prices
    table name = RKPLN
    field name =  TKF
    HOPE IT HELPS
    regards
    sayeed

  • CATS INTEGRATION WITH PP AND PM MODULE ( TO FIND ACTUAL MANPOWER COSTING THROUGH ACTIVITY TYPE)

    Hi Experts,
    We have a scenario like, Client wants to track the actual manpower costing through activity type ( Ex: How much hours an employee worked on a particular work center to produce an “X” product, So that his actual cost should be loaded on that product.
    We have employee ( 1. Staff 2. Worker 3. Contract labor employee and apprentice from third party roll and staff and worker we plan to go with negative time management and for contract labor and apprentice will go with through cats.
    Since we are not going to run the payroll for contract labor employee and apprentice, we just maintaining the employee data as a group ( Ex: Group A,B,C etc.. Each group consists 20 or 30 employees, According to system each group as one employee and according to us each group consists as 20 or 30 employee.
    The Activity type as well cost center will be created by Co module, the same will be assigned in info type 0315, but still i want more input from experts on the same, since i am new to cross application time sheet configuration, could any one help me out to find the actual manpower costing in a better way.
    Regards,
    Prem

    Hi Experts,
    Can any one please reply on the same.
    How to arrive the exact manpower costing through activity type ?..
    Regards,
    Prem

  • KSPP error: Plan/SOP order &: Reference to cost center/activity typ

    Dears,
    I need to know how to correct the error: "Plan/SOP order &: Reference to cost center/activity typ" that I received when I run the KSPP.
    Error code kp603.
    Thanks in advance
    KR
    Vincent

    Hi everbody,
    I found that when we have a formula in Resource -> Costing view but no quantity ( zero ) in Standard Value for operations (Master recipe) then we face the error.
    Other tips could be found in sapnote 1770587 and sapnote 380282.
    I hope this help to solve the issue.
    Regards

  • Cost element/activity type planning upload

    Hi,
    When doing the cost element/activity type planning upload via KP06, can I assign only one characteristic in the element definition level?   Because I want to put in the excel upload layout  the cost elements, cost centers and activity types.  But ECC 6.0 is allowing only one characteristic in the element definition level.  Has anyone encountered this problem?
    Thanks and best regards,
    Thess

    Hello,
    This is controlled by planning are in your planning profile. You need to use "Cost ctrs: Cost element/activity inputs" planning area for this purpose.
    Hope you are conversant with Integrated excel upload.
    To do integrated excel upload of cost center plan data.
    IMG ==> Controlling ==> Cost Center Accounting ==> Planning ==> Manual Planning User Defined Layouts - Create your own layout or copy from standard layout and change it.
    IMG ==> Controlling ==> Cost Center Accounting ==> Planning ==> Define User Defined Planner Profiles
    Copy the SAPALL to ZSAPALL. You cannot change SAPALL as it is standard.
    In ZSAPALL planner profile, select proper planning area and enter your layout.
    Tick Integrate Excel.
    Once the popup for KP06 comes, you need enter the data and save it. It would generate the file name.
    With the same file name you need upload the plan data by using KP06.
    In KP06
    Extras ==> Excel Planning ==> Upload
    Select the file as prepared in accordance with format at the time of generating the file name.
    Hope this solves your problem.
    Please let me know if you need futher help.
    Regards,
    Ravi

  • Resource - cost center - activity type

    Hello,
    I can see the link Resource - Cost center  (in the resource master data)
    I can see the link Activity type - cost element
    I can see where the activity type's planned cost is done, for such or such cost center
    I cannot see the relationship Resource - Activity type
    isn't there any direct link or is it only an indirect link, through the cost center
    Thanks for your help
    KR - Loï

    I need to post 2 diferent type of costs to 2 different accounts (cost elements) my question is what impact is if I mantain in one resource with cost center 1000 2 activity types, one is also linked to CC 1000 but the 2nd is linked to CC 2000
    In the costing tab at the Resource there is a field for the cost center so my question is what are de implication with this cost center and the link between the activity types and the cost centers
    you can maintain 2 cost element for two activity.
    But you can't combine two cc in one resource
    then you need to create two resource, one with cc 1000 and other with cc 2000,
    the second question is, I have to maintain these 2 different cost at the time of confirmation, Is it correct that I mantain the cost of an HOUR in KP26 so when the confirmation happens I just have to say in COR6N that 15 hours were used so based on rate given in KP26 system will calculate and allocate that cost properly, Is this how it works?
    as per the formula in OP54, assigned in resource with respect to activity.
    at the time of actual booking, system will calculate the actual cost of the activity ( as per the formula maintained in resource)
    Also I want to ask if like the activity described before I can have 2 of these attached to the same work center and same phase? I know I can have up to six per Resource but how is the confirmation done, in one step at COR6N you give the 6 parameters to each of the activities or you have to go one by one and saving in this transaction??
    In resource for each activity ( parameter) you need to assign formula and activity type, while creating process, system will copy all the parameter and formula in process order, while booking  in cor6n system will copy all the parameter.

  • Actual Costs and Activity Type - Process Order

    Hi,
    I'd like to know if there are any tables recorded with activity type and actual costs from process order.
    Thanks in advance.
    Osmar Tardivo.

    Osmar,
    Check table COEP

  • Actual activity price does not exist for cost center / activity type

    Hi,
    We are trying to upload the time sheet related data(number of hours an employee workred on a project) ect from Non SAP to SAP.
    We have used a customized program and have loaded the data from se38.
    All this HR data will be saved in CAT2
    Later we transfer the time related data into SAP FI/CO using CAT7.
    +When  tested  with a couple of employees time sheets, they got uploaded in SE38 proerly and when transfered it through CAT7 it was properly taking the hour*rate is cost and was reflecting in the respective cost element.
    For a few time sheets in SE38 we were getting an error saying that the cost center(100501)/ activity type(EAT001) does not exist for 2010.
    Hence we have taken, FY 2010, the cost centes and activity types in KP26 and have given the planned Activity as 1. No planned cost in KP06.
    We have run the price calculation forr the FY 2010.
    Then we were able to uplaod the time sheets, but when we tried to transfer the data through CAT7, it throws an error saying no activity price exist for cost center 100501/ activity type EAT001. If I ignore the warning an proceed, no amount is being calculated.
    When uploaded employee time sheets before, all the cost were getting claculated and were entering into  the respective cost elements, but now no amounts are being calculated and it is taking Zero.
    When checked the previous years data i.e, 2009 all amounts are fine, in KSII I can see the activity quantity filled with some numbers in 2009, where from are they comming? I have checked KBk6 nothing was mentioned.
    PLease assit
    Regards,
    shilpa

    Hi
    I never used CAT* though, but the error means that you need to maintain a activity price in KBK6 (Actual price)
    Regards
    Ajay M

  • PS: planned costs by activity type

    Hi experts,
    I have a problem about an activity type.
    I have created an activity type and planned it on a cost center. This activity type is inserted in a work center with standard formala key "SAP003".
    I insert my activity type in an internal processing of WBE and I calculate costs for this internal processing.
    When I see the cost report of internal processing, the system returns this message: "No costs were calculated for the activity".
    Why? Is it correct?
    Thank you
    Nicola

    Hi Ashish Jain,
    I have planned activity type/price with the transaction KP26, but the system doesn't return any value in planned costs of WBE.
    Why?
    Thanks
    Nicola

  • Costing for activity types in CS

    Dear All
    Hope you all are doing well.I want to perform costing on service order based on activity type for Customer Services. These activities should be assigned to service material. How can activities assign to service materail? Currently I have configured  valuation catagories , assign cost elements to value catagories, define activity types,Price planning for activity type and assign these activity types to work center.
    Your immedite response is higly appreciable
    Thank you,
    Nomi

    Dear All
    Really sorry for late reply! DIP Profile helps a lot in Configuring Quotation and Billing document. What I did was
    1. I create activities with the help of CO consultant and give price to the activities type.
    2. Setting performed for DISPLAY OF COST in Maintenance and Service       ProcessingBasic settings for these activities.
    3. Assign Cost element for these activities. 
    4. Assign these activities type to the work center.
    5. Define Services Materials for each activity type so that they can be displayed in my quotation and billing document.
    6. Assign services materials to DIP Profile as such:
    u2022     Define planned cost u2013 Total Record as source.
    u2022     In Material Determination for profile I assign each of my service material to Transfer cost and Quantity and assign respective cost and revenue element of that activity type to the Service material.
    When I create a service order with revenue u201CSM02u201D.I do not specify service material. I assign my activities types in operations and when I calculate costing it sums up all the revenue in costing for planned costs but when I create quotation and billing document for the service order it shows individual material for each activity type and its amount on item data and total is displayed in header data against EK01 condition type moreover planned and actual cost are displayed in service order.
    The problem is, I have not create any condition record nor assign these condition type to my pricing procedure as value is arising from activity type.
    Which condition types can be assigned to pricing procedure so that they can pick up the value of the activity type?
    Thank you
    Nomi

  • Cost center & Activity types

    Res all,
    how to define cost center for work center ?
    and how to define activity types for SETUP , MACHINE , LABOUR etc activity?
    plz send details with TCODES
    regards

    Hi Ajay
    For defining Activity types T code KL01
    Then you have to plan the activity by using T code KP26
    Here you assign the activity type to particular cost center
    To define cost center T code KS01
    Then in CR01 (work center) u will assign the cost center and activity type
    to that cost center
    Thanks
    Ansuman

  • Activity Type set up for cost center

    Hi All ,
               While creating a task list i m getting a message
    Activity type is not set up for cost center in the year 2008
    Message no. CR062
    How could i set the activity type for cost center? Plz tell the procedure.
    regards
    sunil
    Edited by: sunil gupta on Sep 19, 2008 10:12 AM

    Dear Sunil,
    Check out this,
    1.Create a Cost center using T code - KS01.
    2.Create an activity type using T code - KL01.
    3.Assign the Rates for an activity type & cost center combination using T code KP26.
    4.In the input screen of T code KP26 ,enter version as 0, from period 1 and to period as 12 and the Fiscal
    Year as 2008,enter the cost center, activity type click on overview screen (F5)---> enter the per hour Rate
    under Fixed price and set value as 2 for distribution key and plan price indicator as 3.
    5.After performing this ,while creating the work center ,this combination of activity type & cost center
    should be assigned.Then while creating routing/task list this work center can assigned for performing
    operations.
    Check with this & revert back if you need any further help.
    Regards
    Mangalraj.S

  • Activity types cost Elements not reflecting in Cost Centre Report.

    Hello SAP Gurus,,
    1. Here we are facing one issue in Zreport. total is not matching, compare with KSB1.
    Values are more in Zreport, in other words activity type cost elements are not reflecting in Zreport, but it reflecting in KSB1.
    example: flow from PM module.
    Actually we had used logic based on the Cost Centres, in that cost centre by taking Object number and it passes to COEP table, then we are getting values as same as KSB1.
    As per investigation i found that the object number is differ from COEP table and CSKS table.
    Exapmple : 1410000 object number in CSKS table, 1410000EL in COEP table, thats why in Zreport these values are not reflecting.Finally our requirment is , Zreport values should same as KSB1 vlaues.
    2. We need same functionality as same as KSB1 for match code or drop down menu functionality for Cost Centre Group and Cost Element Group,  but while user wants select from match code or drop menu (F4), as of now i didnt given any logic to abap for match code functionality or drop down menu (F4),so in this case which logic or table i have to use.
    So please give me inputs or logic how to over come the above points.
    Regards,
    Raj.

    The OBJNR field structure is as follows :-
    AABBBBCCCCCCCCCCDDDDDD
    AA = object type eg. KS (cost center)
    BBBB = controlling area
    CCCCCCCCCC = cost center
    DDDDDD = activity type
    Based on the structure, you will be able to filter the relevant cost center/activity types. You can also use other fields eg. cost element, partner object, source object, value type, etc. to get your desired figures as per KSB1.

  • Physical significance of activity type on cost center

    Hi,
         I want to know what is the phsical significance of definiing activity type on cost center.In my situation the activity type is defined on the cost center assigned to the maint. work center.Due to this actual cost is geetting reflected on my order due to the activity rate but physically no such cost is being incurred by the maintenance people.As when any material is consumed on a PM order then the MAP of material  is shown as actual cost in PM order.This is ok.Then how this activity type defining is valid on the cost center when no such work is being carried out.Pls. reply.

    As mentioned in earlier posts, we will assign Cost center & Activity types in Labor work center. In KP26, for this Cost center, Activity type & period (say Jan to Dec 2011), cost (Fixed & Variable) will be maintained.
    Reason to maintain the KP26:
    In Business, sometimes contract labors will be paid on hourly basis. If those people do the Maintenance job, as we are paying them, we need to calculate the labor cost.
    For Permanent employee, company used to pay salary (fixed & variable component on monthly basis). That will be converted into hourly basis & the same will be maintained.
    So that, for expense company doing (paying salary), there should be some offset (getting the work). If you have integration with HR & PM, you can capture the actual hours entered in IW41 in HR time sheet.
    Even though there is no such cost explicitly, these cost should be calculated to arrive at the actual work done on equipment.

Maybe you are looking for

  • Installing multiple instances accessing the same database

    Hi, I want to install two different instances of Oracle 10g in two different machines which will access the same database which will be stored in the shared storage. Is it possible to install them without installing RAC? The instances will be one act

  • Mavericks Mail won't update Exchange 2013 email

    I see people have written about this already but there doesn't seem to be a solution posted in these forums and it seems like a major bug. I use Apple Mail to connect to my work Exchange email. We use Server 2013. Mail worked perfectly under Mountain

  • Sun One Java mobile Application start error

    Hi, I established sun one java mobile application builder but I coudn not start it . when it come to %27 it show me this messagebox "This application has unexpectedly has caused an ExceptionInInitializerError. This Application will now exit (LAX)" in

  • Where is magic content?

    I downloaded the instruction manual when I installed PSE13. It says that Magic Content is under Image>Magic Content and that this brings up a dialogue box. However, I don't have Magic Content listed under images in either Quick or Expert mode. Does a

  • Changing font of a StringItem

    Font font = Font.getFont(Font.FACE_SYSTEM, Font.STYLE_UNDERLINED | Font.STYLE_ITALIC, Font.SIZE_LARGE); label = new StringItem("TIME I AM", null); label.setFont(font); This code does seem to be changing the font. Any thoughts? Suresh