Counter based plans

Dear all,
Please be so good and clarify, for me, the following:
For Counter based plans, does the call horizon use measurement documents or calendar days to release the next work order?
Thank you very much.
Sorin

Sorin,
The default is to use a % value of the smallest package/cycle.
Useful info:
Call Horizon:SAP PM
Call Horizon - Maintenance Planning (CS-AG/PM-PRM-MP) - SAP Library
PeteA

Similar Messages

  • Preventive Maintenance Order is not releasing as per scheduled Planning in Counter Based Plan

    Hi Experts
    In The below schenario
    There is a  counter based maintenance plan. of strategy 100 km,200 km,...1800 km..
    Operaton1,  Operation2,... Operation3... defined in maintenance package for 100 km, 200 km,.... respectively.
    Now issue is that system is releasing order as per sequence of scheduled planing & not according to schedule of current counter reading of counter.
    case:  At 200km order 1 is released with operation1 only, logicaly system should release order with operation1, & operation2
              same like that at 300 km, system has released order with op1 & op2, logicaly system should release order with operation1, & operation3 as per strategy defined in maintenance plan.
    In the present condition, what we have to do to get the desired result like for next counter reading of 400 KM system should release order with op1, & op4.
    Best Regards
    Pravin Gautam

    1st order is getting generated by 100 KM. While doing Preventive Maintenance, vehicle will not have any movements so that counter reading at the completion should as same as 100 KM.
    I am not clear how & why you entered 200 KM for completion of PM order.
    Also, if you complete the 1st Preventive Maintenance at 200 KM, from there only system should calculate the next order. Its not Time based as this will come automatically with predefined frequency. Your plan is Performance based & system will act according to the completion of previous Preventive Maintenance.
    I don't find any reason to change behavior which is correct. I am not convinced with the development which is giving wrong details to the business.

  • PP-PM Integration: Counter based Plan

    Hi All,
    I am creating a maintenance plan with counter. I have created a measuring point. When I create measuring document the counter gets updated and maintenance plan works fine.
    When it comes to automatically update the counter when the production plan is released, the measuring document is created but the measuring point did not get updated. We have assigned the PRT in routing.
    Pls help.
    Thaks,
    Sanjay
    Edited by: Sanjay 1t on Mar 17, 2011 11:36 AM

    Hi,
    Have you assigned Usage value or Usage formula for PRT in Routing?
    Regards,
    Maheswaran.

  • Counter based startegy plan

    HI Friends,
    We have created a counter based startegy plan. the order should be generated at 500/1000/2000 hours.
    Current counter reading is 5, still when the maintenance plan was scheduled 3 orders got generated for the same day.
    Could you let me know why this happened? isithis standard system behaviour.
    thnaks in advance
    Warn regards
    Vivek

    Hi
    counter based plan count the counter on the basis of annual estimate in measuring point
    and on the basis of that value only generate the order
    so enter the practical value in annual estimate
    keep the scheduling period small
    try background scheduling
    hope will be work
    Jitender

  • Counter based maintenance plan triggered improperly

    Hi,
    we have created one counter based maintenance plan with cycle unit 1000 hours  offset unit 0 hours this plan was created on 21.04.2008 . But 68 orders triggered on 19.04.2011 why it was happend.
    how find start of cycle reading  for the Maintenance plan?
    Regards
    Ganesh

    Hi,
    Counter based plan will work based on the Measuring point assigned to that.
    In Measuring Point, you would have defined the Annual Estimate. Based on the Annual Estimate & Cycle value in Plan & Scheduling period in the plan, based on all these, call object would be generated.
    Doubt in Single Cycle Performance based Plan
    Regards,
    Maheswaran.

  • Counter Based Maintenance

    Hello All
    Can any one let me know how the counter based planning can be execute.
    If the maintenance is required oon one equipment after 300 hrs & 1000 hrs.
    I try to do this but not able to execute properly
    1) create equipment
    2) create 2 measuring point against the same equipment.
    3) create cycle (ip11z) with same frequency.
    4) create plan (ip43) and then assign the cycle set and then attach both counter to that plan.
    5) after scheduling ip10 then  creating measuring document
    6) finally move to dead line monitoring
    here at 260 hour the system is generating order but that order contain operation of both frequency (300 hrs &1000 hrs)
    i also check the hierarchy, in  (ip11z ) the hierarchy field is not available like as in ( ip11)
    Thanks in advance
    kapil

    Hello Sandeep
    Thnx for your reply but still i am in vain pl have a look elow what i did
    I create strategy (E)
    Scheduling indicator u2013 time
    Strategy unit- H also mention call horizon, n some other parameters
    In Packages
    1)     288           H          300 hour           1H                             1
    2)     984           H          1000 hour         2H                             2
    hour      UOM     Description     Short Descript            Hierarchy
    Then I create M-Plan via IP42 with the same strategy and attached the task-list. So there is no field to put the counter
    May be I am wrong some where ,just review the same and let me know if miss some thing
    Regards
    Kapil

  • Error while creating measurment documents for a counter (counter based strategy Plan)

    Dear Experts
    Pl suggest the possible solution for below case
    I have a counter based preventive maintenance Plan of 100km, 200km,.....  with op1,op2,..... respectively.
    Now I have done maintenance for 600 km and going to enter another reading in IK11.
    Here, system is giving error
    Counter reading in doc. 251591 larger than in subsequent doc. 251585
    Message no. IR171
    Diagnosis
    No counter overflow reading has been defined for the measuring point, and the counter reading that you have entered is larger than the one in the subsequent measurement document.
    This is not allowed, since the counter is not marked as running backwards.
    System Response
    Processing will not be continued.
    Procedure
    Check your entries and the counter data of the measuring point.
    screen shot for measurement document earlier created is as

    Hi Akhilesh
    okay . I have not found any error in my last and current reading date and time
    screen shot is attached again here for ur reference
    now, what thing I have to checked, pl suggest.

  • Performance/Counter Based Maintenance Plan

    Dear All,
    Please guide me the detailed process related with "Performance/Counter Based Maintenance Plan" with step wise(with Tcode) .
    its urgent
    Please help.
    Sushant

    Hi Sushant,
    as it's urgent, I simply refer to a blpg document created by Maheswaran KD:
    Behavior of Performance Based Plan in SAP Plant Maintenance
    Please, all credits to Maheswaran!
    Regards,
    P.

  • Steps to create the counter based Maintenance plan

    Hi!
    Can any body give "Steps to create the counter based Maintenance plan"
    (Mater Data,Transactional Data and Customizing Data creation)
    Regards,
    MDSFR

    hi
    please refer the following link
    http://help.sap.com/saphelp_46c/helpdata/en/fe/67ef189d6f11d189b60000e829fbbd/content.htm
    regards
    thyagarajan

  • Counter Based Strategy Plan

    Hi Dear All,
    as per client requirement I want to create Strategy Plan (Counter Based) in which Maint call has to due on after every
    100Hr & 300Hr. for that I created Meas Counter & assigned Lower Range: 0Hr & Upper Range: 100Hr.
    after assigning Maint Strategy & counter to Maint Plan, I scheduled it. Initialy no any Meas Documents created so no any
    Maint call due but after 1st Overflow at 100Hrs their r number of maint calls due(near about 42 maint calls due) on same
    date for both maint packages. I didn't understand that, how miant call due for 300Hr Package(even it is not overflowed)?
    Could any one plz explain me in details?
    afterwords i created few more meas documents upto 320Hrs which would not make any effect on next scheduled calls. The
    Scheduled call Status list is same as it is after 100Hrs.
    Plz let me know where I was wrong?
    Thanks in Advance...
    Amol.

    Hi Amol,
    When you are maintaining a counter, you should not normally give Upper & Lower Limit.
    You should Maintain Annual Estimate. What is that you have maintained in your Counter. I hope you have maintained a very low value or none.
    Hence when you have created a measuring document of 100 Hrs, it has considered very short duration and calculated many calls same day.
    Just Enter a Annual estimate say 8000Hrs (maximum possible practically is 8760).
    Create anothert plan and just check with same measuring point after entering the annual estimate & removing limits. It should work.
    MLN Prasad

  • What is the use of OR and AND functions in counter based maint plan

    Hi
    I want to create a counter based maintenance plan...
    I entered the measurement reading for the counter, reading is 4000 hrs
    IN IP43
    I created the counter plan with cycle as 6000 hrs. Once the document reaches 6000 order will be created. While creating the maintenance plan, in the maintenance schedule parameters, i check there is OR and AND functions avaliable...
    I know the basic use of both the functions..
    But what is the significance in the maintenance plan....
    Will it give any effect, between the schedule date and measurement docu entries...
    Since i need to maintain like... once the counter reaches 6000 hrs only order should be created.. it should not create once the date as been reached... since due to present condition, i am not running the DG....
    Give ur inputs
    - Pithan

    Hi
    Thank you for your reply
    As you said...
    If you want order to be created only after certain Hrs to be reached to cycle value then you may opt for single cycle or strategy cycle
    can u explain how to do it...
    In single cycle or stratergy... if u schedule the plan itself, the dates will be populated.. it will calculate with respect to the annual reading we have entered in the measurement document...
    My DG overhaul to be taken in every 6000 hrs... i create a plan... i have given the annual reading as 8000 hrs... if i schedule the plan for 5 yrs... wat will be the call objects...
    Then i am running the DG for 3 hours a day... my annual running hrs will be 1000 hours.. but my order will be released since it has crossed the dates...
    how to control... is it possible to do it in IP43 with multiple counter...
    How to do this ?
    Cna u explain
    - Pithan

  • Plz explain use of  MeasPoints & counters and counter based MaintenancePlan

    Hi!
    My dear PM Gurus
    Can any body explain how to create the measuring points and counters and detailed steps
    to create a counter based, performance based and condition based maintenance plans, plz.
    Regards
    MDSFR

    Hi
    Create the measuring point for the equipment in IK01. Before you need to create the characteristics for the measuring point in CT04.
    For the Maintenance plans, pls find link below from SAP help
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/f9/548ab8cdeb11d1950e00a0c93029cf/frameset.htm
    Sachin

  • Problem with Hierarchies in BPS- Web-Based Planning Applications

    Im trying to use a Web-Based Planning Application in BPS. The Datacolumns consist of a charecterisitc with a hierarchy. this hierarchy is time dependend. The timeframe is set correctly but i still receive an the following error message in my web browser:
    "Hierarchy 'Hierarchy_name' is not valid for date 26.06.2004"
    Does this error message look familiar to anybody? In the moment I have no clue what went wrong

    Hello Tobias,
    I assume you are talking about error message UPC 413 (it always helps to mention the message class and number). Please check table RSHIEDIR. The hierarchy you are using is not valid for the key date you specified (RSHIEDIR-DATEFROM > KEYDATE or RSHIEDIR-DATETO < KEYDATE). If you do not enter a key date in the planning area, the system will always use the system date. So either use a different hierarchy or maintain it differently to be valid on keydate (26.6.2004).
    Regards,
    Marc
    SAP NetWeaver RIG, US BI

  • Scheduling agreement with Consumption based planning

    Dear Experts,
    I Have a Scenario,
    I need to Bulit a Laptop which is a Finished Material, and the Components like Hardisk, Processor, Ram, Casing, Monitor are my Rawmaterials. By using these rawmaterials we are building the parent material.
    My Client requirement is 1) Plan and schedule the requirement
    2) Replenish the stock based on consumption based planning.
    My query is
    1) How should i proceed for mm based procurement ?
    2) Does i need to create scheduling agreement for rawmaterials and and maintain schedule lines ?
    3) For which materials i need to run the MRP ? weather its parent material or Component material ?
    4) What are the sequence of process need to be carried out ?
    Required ur valuable inputs on this.
    Best Regards
    SAP LEARNER
    Edited by: JAVEED AHAMED on Feb 12, 2010 8:34 AM

    Hi
    Consumption based planning and Scheduling agreement are two different functions.
    Consumption-based planning is based on past consumption values and uses the forecast or other statistical procedures to determine future requirements. The procedures in consumption-based planning do not refer to the master production schedule. That is, the net requirements calculation is not triggered either by planned independent requirements or dependent requirement. Instead, it is triggered when stock levels fall below a predefined reorder point or by forecast requirements calculated using past consumption values.
    A form of outline purchase agreement under which materials are procured on predetermined dates within a certain time period.
    With release documentation (in the standard system, document type LPA)
    The schedule lines in the system have internal character. This means that you can change them in any way you wish. The schedule lines stored in the system are not transmitted to the vendor until you explicitly create a scheduling agreement release (which may take one of two forms: a forecast delivery schedule or a JIT delivery schedule).
    The release documentation allows you to display the releases transmitted to a vendor over a certain period in order to establish exactly when you transmitted which information to the vendor.
    Without release documentation (in the standard system, document type LP)
    The schedule lines immediately have official character, i.e. they are immediately transmitted to the vendor the moment you save them (transmission time-spot 4 for messages). There is no release documentation in this case.
    It cannot be explained in few lines. You need to study the below link.
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/75/ee1fa755c811d189900000e8322d00/frameset.htm
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/7d/c2821c454011d182b40000e829fbfe/frameset.htm

  • Which table can we see consumption and forecast values in forecast based planning

    Dear SAP Gurus,
    I am working on implementing forecast based planning for Spare parts for my client. They have one Main Plant which do purchase of Spare Parts and through Stock transfers moved to 60+ Plants from where Spares are being sold.
    Now I am carrying out SAP trial runs for a set of 160+ materials with various models and want to compare with their existing methodology of requirement calculation.
    I want to compile Consumption and Forecast data month wise for these trial materials (160+ materials in 60 Plants) . One way I thought is to go individual Material Master and looks for values in Forecast view. However it is tedious and time consuming.
    The table name shows RMCP2 and RM03M for forecast and Cons values, but I could not find the table.
    Hence I want to know which table if I can view I can get the consumption and forecast data calculated for quick copying and compilation. 
    Thanks and Regards,
    R.Velmurugan.

    Dear Mariano,
    Thanks for your valuable inputs.
    Like I could able to get the consumption values for materials using table MVER and fields GSV01,GSV02 etc.,
    What field I need refer in table PROP for getting forecast values.
    As such I could not see any column where in data are similar to Forecast view.
    Thanks and Regards,
    R.Velmurugan.