Hi,
We're in the BBP phase and wondering if we are going to use DMS for structuring documents in relation to cProject. However as I can read this is more or less an object link. Is there possibilities to automatically copy the cProjects structure into a DMS structure?
When using easy document management it is possible to a link from the document to project definition level and tasks in cProjects?
All relevant documentation and desciptions are interesting!!!
Regards Camilla
Message was edited by:
        Camilla Eikeland

This is the procedure for transferring documents from cProjects to SAP DMS
1) In the project type definition in the back end, select the check box for SAP DMS
2) Ensure that you have specified the RFC destination for the sytem to which you have to transfer the documents by using transaction SM59
3) For the document type that you would be using, include the object link DPR_OBJLINK inside the configuration for document type
4) Once you log into cProjects you can find the tab SAP DMS .
5) You can continue creating the document info record once you are inside SAP DMS
6) You can upload the document of the type for which you had defined the object link DPR_OBJLINK
7) Once steps 5 -6 are done you can view the document inside SAP DMS
P.S. Please kindly give me points if you find the answer useful
cheers

Similar Messages

  • CFolders and DMS Integration

    Hi,
    At present we have DMS. We are going in for cFolders now.
    How do we integrate cFolders and DMS? What are the pre-requisites / configurations needed?
    Where can I find the related documents?
    Regards,
    Rajesh

    Hi,
    please check the cFolders configuration guide (for release 4.0, the guide is also attached in note 973764), chapter u2018cFolders Back-End Integrationu2019 or the Online Help in the SAP Help Portal under http://help.sap.com/ > SAP ERP > SAP cProject Suite > Project and Portfolio Management XX > Design Collaboration with cFolders > cFolders Functions > cFolders Back-End Integration.
    For example, you can use the back-end integration for cFolders to exchange DMS documents. In the DMS system (or so-called back-end system), use transaction CFE02 to export DMS documents to cFolders and CFI01 to import documents from cFolders into DMS.
    Please read the above documentations to see the system and installation requirements.
    Besides creating a RFC destination in transaction sm59, you need to maintain the backend system using transaction CFC01 in the DMS system. At least one cFolders system must be defined in the customizing before backend integration can be used.
    In order to allow the user to create new documents in cFolders, he/she needs write and create authorization in the relevant folder.
    Regards,
    Silvia

  • Integrating cProject to DMS

    hi,
    I am integrating cProject to DMS system.I have done all the configuration required from cProject side. The problem is...in DMS IMG setting, I can't find object link DPR_OBJLNK to attach to my document type.
    regards
    Ram

    Hi Ram,
    I am not 100 percent get your question, but you can check the following thing:
    1. SE16, Table DRAD,
        field DOKOB = DPR_OBJLNK,
    If there is any entries in the table.
    If there is no entry, that mean, no link is created till now. And the transaction like cv02n, cv03n will certainly not show the link.
    Kind regards,
    Zhenbo

  • What is data archiving and DMS(Data Management System) in SAP

    what is data archiving and DMS(Data Management System) in SAP
    Welcome to SCN. Before posting questions please search for available information here and in the web. Please also read the Rules of Engagement before further posting.
    Edited by: kishan P on Aug 31, 2010 1:06 PM

    Hi,
    Filtering at the IDoc Level
    Identify the filter object (BD59)
    Modify the distribution model
    Segment Filtering
    specify the segments to be filtered (BD56)
    The Reduced IDoc Type
    Analyze the data.
    Reduce the IDoc type (BD53)
    Thanks and regards.

  • Solution Manager and DMS

    Hi,
    Am pretty confused between use of Solution Manager and DMS.Can they be used interchageably? What are the differences

    Hi Gopal,
    Presume DMS is something you are already familiar with. Hence wont go into the details.
    The SAP Solution Manager, on the other hand, is a platform which provides integrated support of the life-cycle of a business solution, from the Business Blueprint via configuration to production operation. The SAP Solution Manager provides central access to tools, methods and preconfigured contents, which you can use during the evaluation and implementation, as well as in operation processing of your systems.
    The SAP Solution Manager also provides an authoring function, with which you can create your own project templates, which you reuse in an implementation. The SAP Solution Manager is thus also a tool for SAP partners and companies performing a global rollout.
    Hope this sets in the required clarity.
    Regards,
    Pradeepkumar Haragoldavar

  • Refx and dms

    Dear Friends,
    I am looking for integration between refx and dms. Kindly provide me some details related to that as how we can use DMS with REFX.
    Regards
    Abhishek

    Dear Abishek,
    SAP note 860779 provides further information to configure DMS with RE-FX.
    Hope it helps you further.
    Regards, Franz

  • CProjects and external ressources

    Hello community,
    I would like to know how you are using external ressource (material and human ressources) in cProjects in the normal business? Are you using SRM and are you using CATS or the mm's "activity confirmation" to enter the working time?
    What does a normal process looks like?
    Thx in advance,
      Max

    Hi,
    You can use following steps in case of using CATS and MM.
    Make External resources as a business partner in cProject by BP role as a contractor or if you are importing from HR then external resources can be classified by some specific no range.
    Make resources  as a Vendor in MM, You need to pay to them so raise PO and link to Internal order of cProjects. same will work for material too.
    You will be able to see Project worklist and corresponding PO no in CATS with ref to EMPNO.
    Resources has to fill the time against the activity and time can be transfer to cProject and MM from CATS which will help for paying to contractor and Projct costing.
    There is possiblity by Using SRM too. Need to check for the same.
    Regards,
    Karan Hon.
    Award if useful.

  • CProjects and xRPM Testing

    Hi All,
       What do we do test in cProjects and xRPM? Is it just the navigation and creating the roles, authorizations etc? or do we need to go into the backened (ECC) and validate? can someone throw some idea of testing cProjects. Also if we need to go into the backend, what are the tcodes we need to know? Someone please help me. I am a newbie.
    Regards,
    Vin

    Hi Vinu,
    From an end-user perspective, cProjects/xRPM is a pure web-based application. Everything is done in the browser.
    Backend transactions are mainly used by:
      - system administrators: authorizations, user accounts, monitoring (SU01, PFCG, SM37...)
      - technical experts / ABAP developers: SE80, SE11...
      - system configuration depending on your architecture and integration: HR module (PPOSE, PP01...), PS (CJ20N, OPSN, OPSI...), CRM... Actually all transactions linked to the corresponding module
    Regards,
    Matthias

  • Same numbers in cProject and PS

    Hello,
    when I create a new project and transfer it to PS the numbers are completly different. could someone explain me how I get the same numbers/id in cProjects and PS?
    Thx, Vanessa

    Hi Vanessa,
    There is a BADI in ERP system: GCC_PS_PROJECT_LABEL, implementation CPRO_PROJECT_LABEL.
    Here you can enhance method GET_WBS_ELEMENT at the end, to change WBS name.
    Matthias

  • Migrating cProject and cFolder into a single server instance

    Hi,
    Has anyone had the experience to migrate cProjects and cFolderon seperated server instances into a single server instance? How data migration can be performed assuming cProjects server will be upgraded to 4.5 and the cFolders content will be ported over? is this something do-able? Or it is easier to upgrade cFolder first and migrate the cProjects data over?
    Since documents link in cFolder/cProjects could be captured in transaction table, how to resolve it?
    Would like to hear from anyone with such experiences... thank you.
    Yeu Sheng

    Hi,
    Is your new server Unix based? Are you planning to have 2 separate instances with separate DBs or are you planning to do a MCOD? Can you more details on what you mean by "2 in 1"?
    -RK

  • Integration of KM and DMS.

    hi,
    I have one requirement to integrat KM and DMS.
    Please let me know the ways and some documents also so i can propose some solutions.
    helpful answers will rewarded.
    thnaks in advance.
    jayesh talreja

    Hi,
    Following link has everything for integration with DMS:-
    http://help.sap.com/saphelp_erp2004/helpdata/en/e6/8eae22d46455479a09f7ba5f12730e/frameset.htm
    Using KM..it provides umbrella like connector...to connect to DMS.. You can search more on SDN ...
    Regards,
    Jigar Oza

  • Setting up ALE to integrate cProjects and HR CATS

    Hi Gurus,
    We're wondering if it is mandatory to set up ALE to integrate cProjects and HR CATS.  We found SAP note 954860 and we were trying to understand it, on a functional point of view, before to send it to our Basis team.
    We would like to get some advice on this.
    Could you please give us any hint?
    Thanks in advance for your response,
    Best regards,
    TP

    Hi TP,
    it is not mandatory. Basically you have two options for resources:
    - you can create resources (business partners) manually in cProjects. then you do not need the ALE integration to HR
    - or you can replicate the employee master data to cProjects. then you don't need the manual maintenance, but you have to setup the HR integration
    for CATS:
    - if you like to do time recording through CATS, you need the corresponding integration
    - alternatively you have some easy-to-use task dashboard for the resources involved in the projects inside the cProjects appliation. Users can access the tasks they are responsible for through there. but you do not have full CATS functionality then
    best regards
    Thorsten

  • Content Manager and DMS

    Hi,
    I have only had a high level understanding of Content Management up until now.  I am currently planning for the storage of CAD, PDF, and Microsoft files for our ECC environment.  We are running ECC 6.0.  We are planning on using KPro to connect to the content server to retrieve the files.  I have reviewed the help on Content Server 6.3 and how that is suppose to be installed and configured.  I am not sure how DMS fits into the architecture, does it? 
    Can you use DMS instead of a seperate content manager server or do they work together? 
    Can Content Server be installed on and ECC server or must it be on seperate hardware.  I was thinking it would be best to have a development content server to test with and a production content server.  (If I need a content server at all).  If I have to build a content server for development can it share hardware since it will not do very much... only for testing.
    Any assistance on this architecture would be great.
    Thanks,
    Lee

    Hi Lee,
    You are thinking on right track. Any Pc you can take and make it as a development content server and one important thing, K-Pro and DMS both are different thing. In DMS you can store your documents either in K-Pro or SAP standard server, which can again make it down. So to make use of K-Pro server is best option along with DMS.
    Regards,
    Punam

  • ADF Mobile application and DMS synchronization

    Hi all,
    I'm working on a demo based on a multi-platform mobile application working mostly offline (using a local database which must be manually synced when the device is online).
    I've started watching at ADF Mobile Framework and Oracle Database Mobile Server.
    Now I'm a little confused about how these two components interact each others.
    Looking at some video/documentation I see that using ADF MF I can create a mobile APP for iOS/Android writing pure java code. Then I can deploy the application using a deployment profile to obtain my application, ready to be installed on my device.
    The question is, how my mobile app can be kept synced to a MW running DMS?
    I've read Invoking Synchronization in Applications With the Mobile Sync APIs,  Using an Android Application on the SQLite Mobile Client , Integrate ADFm applications into Database Mobile Server
    but I didn't get how that is supposed to work.
    It seems like I have to add osync_me.jar library to my project, set parameters for my ose.ini file (using SetParam.run) then create a OSESession and use sync() method. This is supposed to get from DMS delta modification and put into it my modifications performed locally.
    That's it? Do I need something more?
    Here How to Integrate Oracle Adf Mobile App and DMS? there's a very similar question without public response, is there any detailed documentation about this topic?
    thank you all

    Thank you for the answer.
    The link you suggested is the one where I've found http://www.oracle.com/technetwork/database/database-mobile-server/documentation/dmstoadfm-2228124.pdf
    Looking at that document it seems I should import libraries, edit programmatically ose.ini and than invoke OSESession.sync() using my user e pass as stated in my previous post, and everything is supposed to work fine.
    But I'm a bit confused because looking at more tutorials and documentation I saw more steps like application publication through mobile server (packaging wizard), installation of oracle update app on mobile device and so on... and I didn't get what these steps are useful for and if they are mandatory for ADFm developed app too? (I'm referring to Database Mobile Server Demonstration - YouTube for example)
    Thank you

  • PS roles for making object links between cProjects and PS

    Hello to everybody!
    Does anybody could give me a favour and tell which role I should grant to the user in order to allow him make object links between cprojects and PS elements from cProjects. I have already granted authorization to CJ01, CJ02, CJ03 and CJ20N transactions, but JA 027 == No authorization for action Display === error message still occurs. SU53 shows that everything is OK. 
    Thank you.

    Hi,
    I´ve the same problem, I´m in tx CJ20N but I don´t know how to add my user in Access Control List (ACL) in CJ20N
    Could you explain me how I can do that?
    thnaks a lot and best regards, Sapera