I have a requirement wherein when the user sets the cProject status to "Flag for Transfer", I want to throw up an error message depending on certain conditions. Do we have any event for this?
Also while creating the WBS element, I plan to use the BADI Implementation CPRO_PROJECT_LABEL. I kept a breakpoint in GET_WBS_ELEMENT method to observer the parameters, but it didn't stop there though the WBS element is created succefully.
Do we have any other ways of debugging this?
I am sure its going into CPRO_PROJECT_LABEL because I enhanced GET_WBS_ELEMENT  and hardcoded the WBS description and the new WBS element has this hardcoded description.
Thanks
Regards,
Ravikanth

Hi Ravikanth,
For the event handling, you can use the BADI  DPR_EVENTS  to implment your own logic to react of the status change.
Regarding Breakpoint, if the implemented codes works and breakpoint not stopped, it can be the problem with different servers.
Either make sure, that the UI (Internet explorer) uses the same  server where the break-point is set. Alternative start tcode SRDEBUG to active for all servers.  Additionally the user-id should be the same for the UI and the break-point.
Kind regards,
Zhenbo

Similar Messages

  • CProjects-PS Integration (Automat. Case) PS profile missing from install.

    We need to create PS-project automatically form cProject project. We know there is a standard project profile cProjects-PS Integration (Automat. Case) for this purpose. However, for some reason this profile is not installed in our development system. SAP told us to manually create this profile and so we did, but still we are not able to create the PS-project. Have someone else had the same problem? Is there something else required to get the profile working than just creating it? We donu2019t find any IMG node where the PS profile would be activated to automatic creation.
    Any help appreciated

    Hi,
    Difficult to say what is wrong here.
    Did you check the error messages in the Controlling Cockpit in your PS system? Transaction COCPCPR.
    BR
    Matthias

  • CProjects-PS Integration - ERROR

    We are on PPM5.0
    We are working in cProjects-PS integration.
    At the flag for transfer, we get to see cockpit errors (COCPCPR).
    "Entry Profit Center = SAP-DUMMY does not exist in CEPC (check entry)"
    There are some more errors but the source of all other seems to be the one above.
    How can we get rid of this error?
    How can we refer to some other profit center so that the system does not reference this?
    Or else, what is the other option?
    Thanks.

    Dear madam
    Please if you explain how you solved this issue it might me help to me because presently i am using same process in my client
    Regards
    Senthilkumar N.K.

  • CProject PS integration steps

    Hi,
      Can u pls anyone send me the cProject PS integration guide with complete steps(if Possible with screen shots). Right Answers will be awarded.
                       Thanks
    Regards,
    Ramesh
    muthurameshsap at gmail

    Hi Ramesh,
    check whether you can access this link
    Account Integration : [https://websmp107.sap-ag.de/~form/sapnet?_SCENARIO=01100035870000000202&_SHORTKEY=01100035870000712381&]
    and then select project accounting ( lot of material PDF and tutor rec ).
    Regards,
    Jatin

  • CProject-CATS integration

    Hello,
    I want to run cProjects CATS integration scenario. Can somebody share relevent documentation? I am using cProjects 4.5.
    Regards,
    Milind Dumbre

    Hi Milind,
    For Integrating CATS need to make relevant settings in Project type.
    Make settings in Data entry profile.
    If cProjects & CATS (ECC) are on seperate servers ref Note 954860 - Setting up ALE to integrate cProjects with CATS.
    You also need to have account integration & HR integration to use CATS with cProjects.
    Ref the link for furthur details.
    [http://help.sap.com/saphelp_ppm450sp04/helpdata/en/43/054880bbe822f5e10000000a1553f7/frameset.htm]
    Regards
    Sejo

  • CProjects - DMS integration:26 036 You are not authorized for with doc.type

    Hi Experts,
    I need to use cProjects integration with DMS. When I try to create a link to an existing document I find the following error:
    26 036 You are not authorized for with document type DRW
    My user has authorization to the doc type in the DMS system (linked by RFC to cProjects system). I also have defined the object link in the document type.
    Do you know which configuration may be missing?
    Thanks in advance!
    Neil

    Hi Niel,
    How is the RFC connection established between DMS and cProjects system? Do check the authorizations of the RFC user through which the connection is established.
    Regards,
    Vivek Pandey

  • CProjects DMS Integration

    Hi,
       I am working on cProjects and trying to understand integration with Easy DMS.
    Can anyone explain the following :
    2)What further ability does the integration offer in addition to the document management functionality in cProjects? I understand that the documents are stored in DMS as Document Inforecord with integration.
    3) Can a user create document Info records in DMS from cProjects or does cProjects just allow the user to link to a record created in EDMS ?
    4) And finally, could some one direct me to any documentation on cProjects and Easy DMS Integration, if any ?
    Thanks,
    Rajesh.
    Thanks
    Rajesh.

    Hello, you can create Document Info record directly from cProjects. First step you need to define in the "Define Project type". You need to check the box for SAP DMS. Also inside cross application for DMS, go inside define document types and you have to include the object "DPR_OBJLINK" for the document type that you would be interested. Once inside cProjects, SAP DMS button would be visible and you may proceed creating Document Info record. It automatically creates in the backend SAP system. You can also load the documents inside that. In case you need more information please let me know your email address and I would send you the screen shots.
    thanks

  • Internal Order not being created in cProjects-Accounting Integration

    Dear All,
    We are working on cProjects 4.0 with ECC 6.0,
    Trying to do Accounting Integration.
    For only one Project I am able to create Internal Order,
    But I am getting following error.
    “Cost/revenue rate YP002 is not valid in organization 00000000   “
    Inspite of assigning these rates to the organization 00000000
    For other projects, when I click on accounting:
    I get following error
    "Single-Obj.Controlling on InternalOrders 0188993B3E343947A046B554FD886E03 000006000032 does not exist"          
    When I go to Controlling Cockpit, I see this Internal Order not being created.
    Have revisited all settings, project type, etc.
    How do I go about this.
    Kindly help,
    Navendu

    Dear All,
    I was able to solve the one of the problem, with the following settings,
    Assign Cost Elements & Activity Types:
    Choose Organization, Start & End Dates, Cost and Revenue Elements, Currency.
    The start and end date of the cost/ revenue did not fall within the start and end date of the Organization.
    Regards,
    Navendu Shirali

  • CProjects HR Integration: Data format synchronizing

    Hi Experts,
    Going into the HR Integration synchronizing we are finding an error on the iDocs:
    Filtering data for central person 00070355 (IDoc 0000000000000016 , segment 000001 - )
    Message no. HRALX00_ORG512
    We suspects from some CRM threads that we are missing some data synchronizing between the two systems. How can this data format comparing / synchronization can be done from a cProjects 4.5 system?
    Thanks in advance.
    Best regards,
    Neil

    Hi,
    Pls check out OSS Note 1052449 - HRALX: Employee is linked with BP without role "Employee".
    Regards
    Sejo

  • CProject - Accounting Integration

    Hi,
        Pls brief me the accounting integration and configuration of cProjects. send me the docs for my id muthurameshsap ingmail
    Thanks
    regards,
    Ramesh

    Hi,
    You can do account integration in cprojects by two way. one by collecting cost to internal order and then settling it to Asset. Another is collecting cost to WBS element and the doing settlement run and creating AUC. Once project Phase (WBS) is technically completed settle this AUC to Fix asset.
    Creation of fix asset depend upon asset class. While creation of AUC in WBS element depend upon investment profile attached WBS element.
    Document sent with internal order scenario
    Regards,
    Hemant
    Edited by: Hemant Patil on Apr 16, 2009 1:19 PM

  • CProjects-PS integration (PPM5.0)

    Hi,
    We are on PPM5.0
    We have a scneario where there are more than one PS Project profile, and therefore we need dynalic linking of project type (in cProjctes) to PS Project profile.
    We understand that BAdi IAOM_BUSINESS_SCENAR can be used to manipulate the setting.
    We have two queries:
    - CPR001 is the standard profile. If we copy this and name it as Z_CPR001, which profile does the system use? We need to use the profile to change some settings, and then try this to create project in PS
    - Where does the system allow to dunalically link the Project Type (cProjects) to the PS profile for the scenario defined above - where we need to link profile dynamically because there's more than one PS profile to be used.
    Please advise.
    Thanks.

    Thanks Matthias.
    What we are not sure of is where (at the front end) do we link the cProjects Project Type to the PS Profile. I am talking about the user - where at the front end, does the user specify this link.
    Also, for the standard profile, if we create a new one, with a copy of CPR001 (say Z_CPR001), does the system use Z_CPR001 as the standard profile. We need to test a scenario where the standard settings need to be changed.
    Thanks.

  • Error - cProjects PS integration

    Hello,
    I am carrying out the automatic creation of projects in PS from cProjects. I have done all the required configurations for the same.
    While creating the project in cProjects, I entered the number for Project and phase as per the mask id in PS.
    But while creating project automatically, the wbs element of PS project for cProject phase is still taking the internal no.
    And in cocpcpr, I am gettting the error - Object WBS Element 190000000000000002762009 could not be created.
    Any pointers why this error is coming.
    Regards
    Amit

    Dear madam
    Please if you explain how you solved this issue it might me help to me because presently i am using same process in my client
    Regards
    Senthilkumar N.K.

  • Cprojects-xrpm integration error

    Hi
    I need to integrate cprojects and xrpm (both are on different systems). When I try to do so, it gives me "No system found for alias SAP_RPM" error at source "Application".
    How do I resolve this?
    Preeti

    Hi,
    in the portal, you have to define a "system" for your RPM backend system and also
    define the alias SAP_RPM for this "system" in the portal. Same has to be done for
    cProjects and the alias SAP_cProjects.
    Kind regards,
       Florian

  • CProjects Accounting / CATS integration

    Hi
    I am working on cProjects Accounting Integration and CATS integration.
    During same I am getting following messages:
      1. Acct Int.: Single-Obj. Contr. in SAP R/3  DCE458547A88A6F1B3640002A5CD3FB0 does not exist
    2.  Inconsistency between currency type 30 and currency EUR  
    Also, Internal Order is not getting generated.
    It is on ECC6 and cProjects 4.0
    Can anyone help me on the same?????
    If someone has any document to share please send it on [email protected]
    Niraj Sikliogar

    Hi Niraj
    To create the internal order , check the following things
         do the following things,
    .1)     Define company Name
    2)     Define company code, Credit control area, business area, Functional area, FM area.
    )3)     Maintain Controlling area.
    Prerequisite:  Need to define to Company following four things
    a)     Currency type: Defined in Company code
    b)     Currency: Defined in Company code
    c)     charts of account:
    d) Maintain Fiscal variant and assign it to company code.
    4)     Create Cost center
    Prerequisite for cost center:  Need to define 1) Standard Hierarchy 
    5)     Create cost element
    6)     Do the following assignment
    a)     Company code to company
    b)     Company code to credit control area
    c)     Company code to FM area
    d)     Profit center to Company code
    7)     Assignment company code to controlling area
    8)     Create model order: put $$  sign as order type.
    9)     Create the order type
    do the following things ,it will help you.
    any problem put the query
    Reward point if useful
    Regards,.
    nitin

  • Message no. DPR_FIN_GECCO024 Error occurred in accounting - see link controlling cockpit (cProjects)

    Hi, everyone
    I'm integrating PS( which is on IDES system ECC6 PH6) with cProjects( which is on DEV system ECC6 PH6 PPM 5.0). I've done customizing in DEV and IDES. The Controlling Method is Multilevel Controlling (Structure Element, Automatic).
    When I'm saving a project with status 'to be transferd', the warning message appeared and I'm failing to assign PS Project automaticlly. But manual assignment works fine.
    Error occurred in accounting - see link controlling cockpit (cProjects)
    Message no. DPR_FIN_GECCO024
    Diagnosis
    Errors occurred when transferring to accounting.
    System Response
    DPR_FIN_GECCO 024
    Procedure
    Choose the Controlling Cockpit (Project Management) link on the Accounting tab page. In the cockpit, you can create a variant with your Project Management project under Selection Variant Orders Project Management. The errors that occurred are then displayed. If no messages are displayed in the controlling cockpit, they have already been processed or deleted. If this is the case, trigger the transfer again.
    No more messages are displayed once the transfer has been carried out successfully (that is, no errors occurred).
    Here is the problem:
    In this Message, I was told to Choose the Controlling Cockpit (Project Management) link on the Accounting tab page. But actually, I can not find the Controlling Cockpit (Project Management) link on the Accounting tab page. It was missing.
    I don't konw what‘s the problem with the missing Controlling Cockpit and how to deal with this warning message getting automatic PS assignment done.
    By the way, I've done IDES test, cProjects and ERP system were integrated on the same system with RFC destination NONE. And that works fine on IDES, so I guess I've done the right customizing in the ERP system( IDES).
    Best Regards,Yemi

    Hi Yemi,
    Controlling cockpit is accessed to view the error details in the accounting integration. This can be accessed through two ways.
    1) In Project-->Accounting tab
    2) Through tcode - COCPCPR
    You can try the second method to view the error details.
    And coming back to your query on project profile config in PS, as Pramod said, by standard SAP delivers a standard profile in SAP PS for cProjects-->PS integration. You can find the same in the below SPRO path.
    Project System-->Structures-->Operative structure-->Work Breakdown structure(WBS)-->Create Project profile
    Project profile name : CPR0001
    This project profile is used when an automatic PS project is created through accounting integration.
    Hope this helps.
    Regards,
    Ravi