CProjects rescheduling:: Role-task assignment adjustment

All,
We create a project with phase and task & role with staffing. We assign role-resource to task.
After sometime, we reschedule the project. Dates of project, phase, and task are changed. But the role validity, the role staffing duration, role-resource-task assignment remain unaffected.
Am I wise to expect
-automatic adjustment of role's validity to the new Project Dates? ('General' tab)
-automatic adjustment of role staffing? and ('staffing')
-automatic adjustment of role-resource-task assignment? ('task')
Have anyone customized in this area?
thanks,
Mathavan

Hello!
We had the same requirement as yours, and we had to develop everything to automatize such needs. It's not available in standard.
For information, we are working on SAP cProjects/xRPM 4.5
Regards,
Matthias

Similar Messages

  • CProjects-MS Projects Export - Role-Task assignment...

    When I export from cProjects, I have data mismatch from cProjects to MS Project.
    A task of 5 days is assigned to 3 roles:
    Role 1 for 2 days
    Role 2 for 1 day
    Role 3 for 2 days.
    However, in MS Project, the Role-Task-Assignment gets uniformly distributed across all tasks.
    It shows:
    Role 1: 1.67 days
    Role 2: 1.67 dats
    Role 3: 1.67 days.
    Please suggest.
    Thanks in advance.

    Hi Girish,
    it might well be that this kind of scenario is not supported by the cProjects MSP interface.
    I'd advice to check note 1126395 and what it has to tell about your scenario.
    Best regards,
    Thomas

  • Include Phase for Phase with role task assignment in cProjects

    Hi,
    When I include a Phase with different tasks and the tasks with Role assignment in to a project,  the task-role assignment is not gettting copied.
    But when I use a Project template with the same Phase-task-Role task assignments, every thing is getting copied. But for Include phase the task-role assignments are not getting copied.
    Can anybody help me how to achieve this functionality?
    Thanks and regards,
    Jashua

    Hi Matthias,
    Thank you very much for your reply.
    Here I have a question.  Because the method ''SET_DEFAULTS_UPON_COPYING'  of the class 'CL_DPR_TASK' is being called in the both cases Create project from template and include a phase in to an existing project.  So, if I implement the BAdI method I think it would effect both the times.  wouldn't it create the role task assignments twice at the time of project creation.
    Also please give me some more details about creating the role-task assignments in this BAdI.
    Thanks and regards,
    Jashua
    Edited by: Jashua Andra on Jan 4, 2012 12:42 PM

  • CProject 4.0 Task Assignment/ Scheduling Changes

    Hi All,
    My Question is about Task Assignment with the Role Functionality,
    Scenario: I have created a Task A with validity Period 08/1/07 - 08/31/07
    and than created a  Role A with validity Period 08/1/07 - 08/31/07, and than hard booked a  resource (Bob) with validity 08/1/07 - 08/31/07 {30 hrs} to the Role A,
    Now as a part of Task Assignment I have linked the Role A to the Task A.
    Question 1) If the Project Manager now changes the Task A validity Period 08/1/07 - 10/31/07,  and does the scheduling in the project ,Is there any way to automatically shift the dates of Role A to 08/01/07 - 10/31/07 and than the Resource to 08/01/07 - 10/31/07,
    Question 2) Is there any Mass tool option to change Dates other than the Table view
    Hope I made my questions 2 clear,
    Thanks

    Thanks Shiv for the response,
    You are right, I change Task dates by using the Graphical view, but it will not change the Role Dates, assigned to the Task, as they both are not tied together,
    I wanted to know if there is anyway, i can shift theRoles dates using the Task Date Shifting, other than coding
    Thanks
    Praveen

  • CProjects-MS Project - import and export of task-role-resource assignment

    Hi,
    We are on PPM5.0
    We are currently working on cProjects-MSP client integration.
    What we have not been able to configure for import/export so far is:
    1. Task-Role-Resource assignment
    Whereas we are are able to import/export the "Person Responsible" and "Role Responsible" fields, we have not been able to align the task-role-resource assignments.
    We see a "Resource Name" column (Standard) in MSP. When we click on the drop down, we see all the roles from the cProjects project. But the alignment does not happen.
    Summary:
    On export and import, we need to automatically see the role-resource-task assignment. How is this possible?
    2. Code field to "VC_BUPA_GUID" gets a number which is not the BP ID.
    Is it possible to import the BP numbers in MSP. Also, how can we assign a number to the role in MSP such that on import into cProjects, the role is already staffed with the corresponding BP.
    3. Is it possible to export all the resources (BPs) into a drop down in MSP - like we see the Project Type, Role Type etc.
    Thanks.

    Hi Anuradha,
    Thanks for your inputs.
    When we export to MSP, we see the cProjects roles under the "Resource Name" drop down in MSP.
    However, they are only seen when we expand on the drop down.
    For e.g. RoleA, and RoleB are two roles in cProjects project, along with many other roles.
    Both of these roles are assigned to a task, say TASK1.
    When exported to MSP, we expect both of these roles to show against TASKI, as "RoleA, RoleB" under the "Resource Name" column. However, these roles are not seen. They only appear as elements of drop down, along with all other roles in the project, when we explicitly click on the drop down.
    Please let me know if I are missing out on something.
    Thanks.

  • Role - Resource - Task Assignment

    All,
    We have a requirement where a cProjects task may spread along for, say, 6 months. Resource needs to work on this task for only 2 days per month, every month (say) (Work - 12 days).
    When the role is staffed for 6 months, this resource will not be available for the other projects. And therefore, we want the resource assignment to the task to drive his availability.
    Is there a way out? Or do we have to staff the role 6 times (with the right dates)? The second option works, I know, but is not an elegant way to do it.
    Thoughts/opinions.
    Regards.

    Thanks Niranjan for your attempt.
    The business isn't quite liking the idea of doing so much when a resource is supposed to be working on the task 2days/month. For every time that the resource is to work, the cProjects user would have to staff to the role (or create a role, as you suggested). Everytime, the dates have to be mnaully entered for staffing, Project Role, Resource to task assignment and so on.
    They want this to be done at one place and would like this data to reflect elsewhere. For e.g. when the resource is assigned to the task, this data should drive availability of the resource - is what they want.
    Let me know if I am missing on any of the obvious functionalities of cProjects resource management that I may try to resolve this issue.
    Thanks again.

  • SharePoint's role and its task assignment

    SharePoint's role and its task assignment list below:
    *Workflow
    *App
    *PowerShell
    *SharePoint migrering
    *Enterprise Content Managment
    *Business Intelligence
    *social business platform
    *SharePoint analyst
    *SharePoint Enterprise Search
    *Document management
    *SharePoint Cloud
    *SharePoint BDC (Business Data Catalog)
    What more am I missing that is important to add?
    Please remember that I'm a newbie in SharePoint 2013.

    I understand you have added ECM but I would also add Records Management, Machine Translation Service and Community Sites.
    If you want to add features then you should also include Office Web Apps, Cross Browser Support and Responsive Web Design.
    Amit

  • Roles tasks and resources assignment

    Hi there.
    I'm working in CProjet and I need to complete role definition; I can define staf (STAFFING TAB) and assign task (TASK TAB).
    In TASK TAB I can create also association between role, task and resource; now, I seem that STAFFING TAB considers TASK TAB assignment, but instead no automatic workload distribution happen.
    It looks like no resources link exist between TAB...
    Any suggestion about?
    Thanks
    Luciano

    Hi,
    In Staffing tab there is required capacity and available capacity.
    Required capacity is given to role and that can be distributed in general tab if distribution activated to that role type.
    Available capacity will be associated with the resource and that is given during staffing.
    You can not distribute required capacity in staffing tab as it is taken from Role.
    Hope this will help you
    Regards,
    Karan Hon.

  • CProjects Internal Order, Tasks in CATS

    I am working on cProjects 4.0
    I want tasks (and project) to appear in CATS against which assigned resources would capture effort.
    Do I have to have the Controlling Method as "Internal Order (Structure Element, Manual)" to have the project and tasks appearing in CATS?
    In case I have the Controlling Method as "Internal Order (Project Definition, Automatic)", don't I get to see the tasks and Project definition in CATS?
    My requirement is that the project definition and tasks assigned to a resource in cProjects 4.0 should appear in CATS. By doing the later, my fear is that only the internal order (created/triggered from cProjects) would appear in CATS.
    Please suggest.

    Hi Bittu,
    I am not 100 percent get what you mean. The note suggested by Subramanian  should give you about the technical settings to configure the CATS.
    From my point of view, it does not matter, which controlling method are used. Certainly you have to check, the settings for the confirmation object, to the task or to the role. The user may get empty work list in CATS due to incorrect settings, but I think internal order will never be showed x in the CAT2 transaction only, there must be a the object of cProject (role or task) as well.
    Please take a look my other post regarding parameter settings for CATS profile as well.
    Kind regards,
    Zhenbo

  • Human task assignment for users in Group1 and Role1

    Is there a way to make a Human Task assignment in Oracle SOA Suite BPM 11g for all the users in Group1 who has the Role1 role?.
    I don't want to assign the task to all the Group1's users plus all the Rrrole1's users. I only need the users who belong to both: Group1 and has Role1, but I don't know how to configure this in the HumanTask.
    Edited by: alfredozn on Feb 23, 2011 10:04 AM
    Edited by: alfredozn on Feb 23, 2011 10:06 AM

    repost.

  • Reminder email notification and task assignment notification from humantask

    Hi All ,
    We have developed a 3 level approval SOA composite which sends the 1st level approval to a Manager and once Manager approves the request, the approval task is assigned to a 2nd level approver role(Group) for approval and after the approval from 2nd level approver group , the approval task is assigned to a 3rd level approver group .
    After the request is submitted and the task is assigned to Manager for approval. Manager receives a task assignment notification (defined in the notification tab of the .task) and a reminder notification is fired after X hours of the task assignment. The issue is, the assignment notification and reminder notification are same, is it possible to send different notification on task assignment and a different notification on reminder.
    Appreciate your help on this !
    Thanks
    suren

    The default email solutions in planning are using workflow or task lists, though the task lists are based on due dates.
    If you wanted a solution where an email is sent out when a task list is complete, then one route could be to have a business rule attached to a task list and then the business rule uses a custom CDF to send out email notication.
    If you are interested in sending emails from business rules then I did write a blog on the subject a while back.
    Cheers
    John
    http://john-goodwin.blogspot.com/

  • Error " no portal roles are assigned"

    hi experts,
    i am getting Error while opening portal page with user J2EE_ADMIN
    it is netweaver 2004ssr2.Error is "no portal roles are assigned".
    and this user has role "sap_j2ee_admin"o
    Just after completed installation i tried to open portal page.but this error i am getting.
    Please help me.
    i will reward points for help.
    thanks in advance,
    regards,
    raju.

    Hi,
    Please make sure it has super admin role and objects are added to role and define entry points and portal permissions are defined which enables the delegation of administrative tasks and content in the portal environment.
    Hope it helps.
    Regards,
    Mona

  • Business role not assigned..

    Hi,
    I am not able to see the webclient UI and it shows message " logon is not possible because you have not been assigned to a business role.
    Please suggest me the steps need to be done to get the webclient UI for user.
    Regards,
    Nex

    Hello Nex,
    Do the following steps:
    Txn:PPOMA
    Click on Position and expand.
    Click on 'Search Term' With Name* and Execute
    You would see the list of Business Roles.
    Double click on any of these roles like SALES PRO or SERVICE PRO or TPM PRO .
    On RHS, Task Assignment , Right Click and select 'Assign'
    Choose Holder- User and give your user name and save.
    Or
    In Txn:SU01 ,under the tab 'Parameters, you can give
    Parameter ID CRM_UI_PROFILE
    Parameter Value  Role Name and Save.
    Hope this helps!
    Best Regards,
    Shanthala Kudva.

  • What roles to assign for managing comments?

    Hi,
    I am setting up a separate user role for managing comments, orders, and product inquiries.    I am not sure what roles to assign in the user role area.  There are areas for approving, deleting and editing comments, but I need them to be able to reply to comments, work on orders, etc.  I don't need to give them full Admin access, but there are so many choices, I'm not sure which ones are needed for these tasks...
    TIA,
    Jeff

    Thank you Annett.
    It  seems, that in SM4 SAP has provided list of authorization objects (in the Excel 'Delta_Information_Customers_EN.xls' and customers should gather a new composite roles of their own.
    I consider SAP should have provided a template composite role in standard for Test and test coordinator users.
    SAP knows very well the needs of a tester and test coordinator, and STWB_WORK is surely not the only authorziation object needed.
    Here are some topics that I consider typical needs for a TESTER in project implementation (in parenthesis a proposal from SAP's Excel):
    No authorization for project admin nor SOLAR01, nor SMSY
    Display authorization for SOLAR02 (sap_solar02_dis)
    Display authorization for SOLAR02 documentation (?derives from sap_solar02_dis?)
    Not able to switch to other projects in SOLAR02 (?invidual rights to auth.object S_Project?)
    Execute transactions from SOLAR02 (?derives from sap_solar02_dis?)
    all rights to STWB_WORK (sap_stwb_work_all) and everything inside it: create message, execute test cases, enter test results
    If there are any SDN members having already defined tester and test coordinator composite roles in SM4, I am interested to hear which roles you used.
    br: Kimmo

  • Unable to fetch task assigned to particular group from user

    Hi,
         I am usinf BPEL 10.1.3.0. The BPEL is configured to use the Oracle Infra as directory server for providing identity service.
         I have a two group created in oid by name AdminRole and TestRole.Have a one user assigned to each group.
         If i create a new user and assigned to both the role, so any task created for both the group will be visible to new user.
         But this is not happening the new user is not able to view any task assigned to AdminRole or TestRole.
         Any Help Apprecited.
    Regards,
    Bhavik

    Hi Dasaradh,
    If earlier issue (Pop message with 60) is not resolved, then it means your Service Constructor is old one. You will see this pop error message when you have more than 60 records to be fetched. The service solution component tables's maximum capacity was 60 only. We fixed the issue later.
    So if you still see this issue, I would suggest you to update your service constructor.
    For later issue [(Unknown Source)Error: Extension ID oracle.aia.codegen.codegenwizard in extension.xml does not match jar filename oracle.aia.aiaserviceconstructor], it looks like your Service Constructor install is not successful.
    Thanks
    Vikas
    Edited by: user10866611 on Nov 24, 2010 3:15 AM
    Edited by: user10866611 on Nov 24, 2010 3:16 AM

Maybe you are looking for